41 Morton Road, 4 Ecclesbourne Road, London NI 3GF: LON/00AU/LDC/2024/0501 LON/00AU/LDC/2024/0501
FIRST-TIER TRIBUNAL
PROPERTY CHAMBER (RESIDENTIAL PROPERTY)
Case No LON/00AU/LDC/2024/0501
Between
41 Morton Road, 4 Ecclesbourne Road, London NI 3GF Ecclesbourne Management Company LimitedApplicantThe leaseholders, as listed in the application formRespondent
Before
Tribunal Judge I MohabirPrime Property Management, Managing Agent for the ApplicantN/A For dispensation under section 20ZA of the Landlord & Tenant Act for the RespondentDate 3 February 2025Property: Road, London NI 3GF Ecclesbourne ManagementType of application: 1985
DECISION
[1]The Applicant seeks an order pursuant to s.20ZA of the Landlord and Tenant Act 1985 (“the Act”) for retrospective dispensation with the consultation requirements in respect of fire safety works (fire alarm installation and associated work to electrical wiring) at the property known as 41 Morton Road, 4 Ecclesbourne Road, London, NI 3GF (“the property”).[2]The Applicant is the management company for the property and the Respondents are the long leaseholders.[3]The property is described as being residential flats in a purpose-built block of 15 flats.[4]It is the Applicant’s case that following an FRA type-2 report, undertaken by GF Fire Solutions on 27 March 2024, it was found that the property had substantial compartmentation defects. As the compartmentation defects were so severe, the risk assessors expressed that “this building cannot be guaranteed to provide adequate compartmentation in order to enable a Stay Put Unless in Danger evacuation strategy. The strategy should be changed to Simultaneous evacuation with the installation of an automatic fire alarm system.” The FRA type-2 detailed that this action should be taken immediately. Delaying the installation of the fire alarm by undertaking a section 20 consultation would have compromised resident’s health and safety.[5]Apparently, the Applicant considered interim measures such as a “waking watch” whilst section 20 consultation took place. However, the cost exceeded £10,000 per week. The weekly cost estimate far outweighed the cost of expediting a fire alarm installation, which would be required at the expiry of the section 20 period anyway of approximately 13 weeks.[6]The view taken was that, in addition to the cost saving to leaseholders, the alarm would be more effective for evacuation due to its speed, automatic nature, and ability to cover large areas simultaneously. A waking watch is less reliable and more prone to human delays or errors and was not a sufficient interim measure for the section 20 period, and as such the alarm installation should be expedited instead.[7]On 3 April 2024, the Applicant informed the Respondents of the FRA type 2 report, and the necessary fire alarm installation works and change to evacuation policy from stay put to simultaneous evacuation.[8]On 5 April 2024, the contractor, Triple Star Fire and Security Limited, commenced the installation of the fire alarm system, which was completed on 11 April 2024.[9]BY an application dated 4 April 2024, the Application made this application to the Tribunal. On 29 October 2024, the Tribunal issued Directions requiring the Applicant to serve the Respondents with a copy of the application. The Respondents were directed to respond to the application stating whether they objected to it in any way.[10]None of the Respondents have objected to the application. Relevant Law[10]This is set out in the Appendix annexed hereto. Decision[11]As directed, the Tribunal’s determination “on the papers” took place on 3 February 2025 and was based solely on the documentary evidence filed by the Applicant. As stated earlier, no objections had been received from any of the Respondents nor had they filed any evidence.[12]The relevant test to the applied in an application such as this has been set out in the Supreme Court decision in Daejan Investments Ltd v Benson & Ors [2013] UKSC 14 where it was held that the purpose of the consultation requirements imposed by section 20 of the Act was to ensure that tenants were protected from paying for inappropriate works or paying more than was appropriate. In other words, a tenant should suffer no prejudice in this way.[13]The issue before the Tribunal was whether dispensation should be granted in relation to the requirement to carry out statutory consultation with the leaseholders regarding the overall roof works works. As stated in the directions order, the Tribunal is not concerned about the actual cost that has been incurred.[14]The Tribunal granted the application for the following main reasons:(a) at all material times, the Tribunal was satisfied that the Respondents have been kept informed of the need, scope and estimated cost of the proposed works.(b) the Tribunal was satisfied that the Respondents have been served with the application and the evidence in support and there has been no objection from any of them. The Tribunal attached significant weight to this.(c) The Tribunal was satisfied that any delay incurred by the Applicant having to carry out statutory consultation would inevitably have resulted in a significant health and safety risk to the occupants in the block having regard to the findings and conclusions in the FRA type 2 report. This has to be viewed in the context of the post Grenfell era and the present rationale to be applied to building fire safety.(d) In addition, the Tribunal was satisfied that the Applicant had considered other interim measures such as a “waking watch” to enable section 20 consultation to take place, but were rejected for good reasons of excessive cost and the continuing significant health and safety risk posed to the occupiers in the property.(e) importantly, the real prejudice to the Respondents would be in the cost of the works and they have the statutory protection of section 19 of the Act, which preserves their right to challenge the actual costs incurred by making a separate service charge application under section 27A of the Act.[15]The Tribunal, therefore, concluded that the Respondents were not being prejudiced by the Applicant’s failure to consult and the application was granted as sought.[16]It should be noted that in granting this part of the application, the Tribunal makes no finding that the scope and cost of the repairs are reasonable. Name: Tribunal Judge I Mohabir Date: 3 February 2025 Rights of appeal By rule 36(2) of the Tribunal Procedure (First-tier Tribunal) (Property Chamber) Rules 2013, the tribunal is required to notify the parties about any right of appeal they may have. If a party wishes to appeal this decision to the Upper Tribunal (Lands Chamber), then a written application for permission must be made to the First-tier Tribunal at the regional office which has been dealing with the case. The application for permission to appeal must arrive at the regional office within 28 days after the tribunal sends written reasons for the decision to the person making the application. If the application is not made within the 28-day time limit, such application must include a request for an extension of time and the reason for not complying with the 28-day time limit; the tribunal will then look at such reason(s) and decide whether to allow the application for permission to appeal to proceed, despite not being within the time limit. The application for permission to appeal must identify the decision of the tribunal to which it relates (i.e. give the date, the property and the case number), state the grounds of appeal and state the result the party making the application is seeking. If the tribunal refuses to grant permission to appeal, a further application for permission may be made to the Upper Tribunal (Lands Chamber). Appendix of relevant legislation Landlord and Tenant Act 1985 (as amended) Section 20(1) Where this section applies to any qualifying works or qualifying long term agreement, the relevant contributions of tenants are limited in accordance with subsection (6) or (7) (or both) unless the consultation requirements have been either— (a) complied with in relation to the works or agreement, or (b) dispensed with in relation to the works or agreement by (or on appeal from) the appropriate tribunal .(2) In this section “relevant contribution”, in relation to a tenant and any works or agreement, is the amount, which he may be required under the terms of his lease to contribute (by the payment of service charges) to relevant costs incurred on carrying out the works or under the agreement.(3) This section applies to qualifying works if relevant costs incurred on carrying out the works exceed an appropriate amount.(4) The Secretary of State may by regulations provide that this section applies to a qualifying long term agreement— (a) if relevant costs incurred under the agreement exceed an appropriate amount, or (b) if relevant costs incurred under the agreement during a period prescribed by the regulations exceed an appropriate amount.(5) An appropriate amount is an amount set by regulations made by the Secretary of State; and the regulations may make provision for either or both of the following to be an appropriate amount— (a) an amount prescribed by, or determined in accordance with, the regulations, and (b) an amount which results in the relevant contribution of any one or more tenants being an amount prescribed by, or determined in accordance with, the regulations.(6) Where an appropriate amount is set by virtue of paragraph (a) of subsection (5), the amount of the relevant costs incurred on carrying out the works or under the agreement which may be taken into account in determining the relevant contributions of tenants is limited to the appropriate amount.(7) Where an appropriate amount is set by virtue of paragraph (b) of that subsection, the amount of the relevant contribution of the tenant, or each of the tenants, whose relevant contribution would otherwise exceed the amount prescribed by, or determined in accordance with, the regulations is limited to the amount so prescribed or determined. Section 20ZA (1) Where an application is made to a leasehold valuation tribunal for a determination to dispense with all or any of the consultation requirements in relation to any qualifying works or qualifying long-term agreement, the tribunal may make the determination if satisfied that it is reasonable to dispense with the requirements.