"Following our meeting on 5 December we have agreed the above to be discussed and agreed once you have gone through the receipts given"
"You have proposed you will be making a payment of£13,000 ‑odd (that is,£9,251 plus£4,070 ), and the remaining balance after the above will be£25,465 , and should be paid by the end of February."
"The disputed balance is not in the above until agreed, as Remon is still going through the building materials for all of these. If you have a question please do not hesitate to contact me."
"We understand there is a dispute sheets that need to be solved. As soon as the disputes mentioned solved (inshallah) we will then know exactly the balance to pay and when."
"The meeting concluded with an agreed figure of£48,652 . Mr Makkar's wife sent us a breakdown, and it clearly states following our meeting we've agreed the outstanding amount of£38,652.52 , and there remained a disputed amount, it was of£5,854 ."
"Any payment delays with the second instalment will result in the delay of the work process. If the final instalment is not paid within 15 days following the completed job a surcharge fee will be applied to the remaining balance at the rate of 2 per cent per week. In the case of a snag list the customer has a right to retain 10 per cent of the final instalments until the completion of the snag list."
"The true test is whether the impugned provision is a secondary obligation which imposes a detriment on the contract‑breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation. The innocent party can have no proper interest in simply punishing the defaulter. His interest is in performance or in some appropriate alternative to performance."
"But compensation is not necessarily the only legitimate interest the innocent party may have in the performance of the defaulter's primary obligations"
"33. The penalty rule is an interference with freedom of contract. It undermines the certainty which parties are entitled to expect of the law. Diplock LJ was neither the first nor the last to observe 'The court should not be astute to descry a "penalty clause"
'A millionaire may enter into a contract in which he is to pay liquidated damages, or a poor man may enter into a similar contract with a millionaire, but in each case the question is exactly the same, namely, whether sum stipulated as damages for the breach was exorbitant or extravagant …' 35. But for all that, the circumstances in which the contract was made are not entirely irrelevant. In a negotiated contract between properly advised parties of comparable bargaining power, the strong initial presumption must be the parties themselves are the best judges of what is legitimate in a provision dealing with the consequences of breach. In connection, it is worth noting in Philips Hong Kong at pp 57-59, Lord Woolf specifically referred to the possibility of taking into account the fact 'one of the parties to the contract is able to dominate the other as to the choice of the terms of a contract' when deciding whether a damages clause was a penalty. In doing so, he reflected the view expressed by Mason and Wilson JJ in AMEV-UDC [ Finance Ltd v Austin[1986] 162 CLR 170 ] at p 194 that the courts were thereby able to strike a balance between the competing interests of freedom of contract and protection of weak contracting parties' […]. However, Lord Woolf was rightly at pains to point out this does not mean the courts could thereby adopt 'some broader discretionary approach'
"The rule against penalties has often been seen as anomalous because it applies even to clauses that are negotiated between experienced parties of equal bargaining power. In the Cavendish Square case Lords Neuberger and Sumption described it as an edifice which has not weathered well. The Privy Council has cited with approval the view of Dickson J in the Supreme Court of Canada that the power to strike down a penalty clause is a blatant interference with freedom of contract and is designed for the sole purpose of providing relief against oppression of the party having to pay the stipulated sum. It has no place where there is no oppression. "
"In Cavendish Square a majority stated whether a clause is a penalty is a question of construction. From this it follows, Lord Neuberger and Lord Sumption said, the test must be applied as at the date of the agreements, not when it falls to be enforced. A penalty clause is a species of agreement that is by its nature contrary to public policy. It also follows the application of the test does not involve a discretion and if the clause is penal it is wholly unenforceable. These points suggest the question is one the other courts have preferred to call one of characterisation rather than interpretation or construction. However, construction in the normal sense may also be relevant, though it is usually accepted the words used by the parties are not determinative. If the parties' intention was to compensate rather than to deter it seems the validity of the clause should be judged by whether it is extravagant by comparison to genuine pre‑estimate test, disregarding any interest that might have justified the deterrent."