“The Tribunal's view of the expert and factual evidence lead inexorably to the conclusion that: The wall works were not justified and should not have been carried out accordingly it was not reasonable to incur any sums in carrying them out. There was no genuine intention at the date of the service charge demand to carry out the works in the original Litespeed quote. Instead Mr Edmunds was intending to redevelop the building in accordance with the planning application. In these circumstances the sums claimed are not reasonable. Mr Roberts in an effort at damage limitation sought to persuade the Tribunal that at the very least the original Roger North report confirmed that some works were necessary in the building and that therefore the Applicant was entitled to at least a share of the cost of these works. With respect to Mr Roberts this was at best a speculative argument. Moreover the Tribunal's view of the overall conduct and behaviour of Mr Edmunds does not support any form of concession in relation to the application.”
“This application is dismissed. It is clear from the Lapider reports that the water ingress into Ty-n-Coed was not caused by any action or omission by the Respondent.”
“AND UPON the Court further noting that: · The Claimant has failed to comply with the directions made on the last occasion to file a case summary and draft directions · The claimant is unable to explain to the court’s satisfaction which parts, if any of the claim remained for determination once the wall works and breach of covenant claims are removed since the claim for house works in the county court proceedings and in the tribunal appear to be based on the same quotation but for different amounts (£65,766.66 in tribunal proceedings,£79,919.99 in the county court proceedings) · The Court cannot carry out proper case management of the remaining issues for trial without proper consideration being given in advance of the hearing as to what the parties consider the remaining issues are”
“At a quorate and properly constituted meeting of the RTM Company on27 May 2015 , at which the Defendant was present, the RTM Company considered these quotes and approved the scope of the works and costs set out in the quote of Litespeed. The Defendant raised no objection.”
“The Defendant again raised no objection, but did not, and has not to date, paid this sum.”
“Although both parties were self - serving in their evidence to some degree the evidence of Mr Newell was preferred. He was largely honest although the Tribunal does not accept that he did not originally agree the Litespeed quote. He was at the RTM meeting when it was agreed. His unwillingness to admit that is attributed to the trench mentality that he and Mr Edmunds have developed during the dispute such that any concession would be considered a sign of weakness. In contrast to Mr Newell the Tribunal found Mr Edmunds' evidence to be thoroughly unreliable. His account altered during his evidence as he recognised the weaknesses in his own case. His explanation that he had changed his approach and decided not to redevelop the building lacked any credibility and was not borne out by the objective facts that he had been pursuing works in accordance with a planning application he had submitted. Mrs [Edmunds] gave no evidence that assisted the Tribunal. She plainly knew nothing about what was going on and deferred to her husband in this regard. She was defensive and uncooperative when being cross examined.”
“The Claimant submits to the Court that the recovery of the sum of£77,586.64 under contract still continues in these present proceedings…”