“The interpretation of a document as a whole necessarily involves giving effect to each part of it in relation to all other parts of it. Accordingly, as a corollary of the principle that a document must be interpreted as a whole, effect must be given to each part of the document. This in turn means that in general each part of the document is taken to have been deliberately inserted, having regard to all the other parts of the document”
“1. The Tender Clarifications entitled “Baltic Exchange - Final Clarifications.pdf” has been incorporated into and forms part of the Contract (under item 2.19 of the ERs in Volume 2 of the Contract)… 2. The Schedule of Derogations entitled “Derogations Final.pdf” has been incorporated into and forms part of the Contract (under item 3.3 of the CPs in Volume 3 of the Contract)”
“3. On a proper interpretation of amended clause 1.3 of the Contract, the Schedule of Derogations and/or the Tender Clarifications are not superseded or overridden by the Amended JCT Terms, but have to be given effect as part of the Contract as a whole to define, qualify and/or clarify the contractual allocation of risks and responsibilities in respect of design and consents (under clauses 2.1.1, 2.1.3 and 2.17 of the Contract or otherwise); 4. At the time of contract, Mace did not take on any design responsibility and any associated risks of discrepancies, inconsistencies and inadequacies (under clauses 2.1.1 and 2.17 of the Contract or otherwise) in respect of the Derogation Items identified in the Schedule of Derogations; 5. Until the design solution for the Derogation Items was finally approved and instructed by Baltic, Mace did not take on any design responsibility and any associated risks of discrepancies, inconsistencies and inadequacies (under clauses 2.1.1 and 2.17 of the Contract or otherwise) in respect of the Derogation Items identified in the Schedule of Derogations.”
"8.6A.1 The Contractor shall only be entitled to proceed with the Initial Scope of Works and shall not carry out any other part of the Works on or prior to28 February 2024 unless and to the extent confirmed by the Employer or the Employer's Agent in writing. The Contractor shall proceed to carry out the Works in full with effect from1 March 2024 or such other date agreed between the Parties in writing provided that the Employer has not issued a notice to terminate the Contractor's employment under this Contract in accordance with sub-clause 8.6.2A. 8.6A.2 The Employer shall be entitled by notice to the Contractor to terminate the Contractor's employment under this Contract at will provided that it issues a notice to the Contractor doing so on or prior to28 February 2024 … 8.6A.3 This clause 8.6 shall take precedence over all other clauses of the Contract."
“1. Mace Construct Ltd are unable to take design responsibility, associated risk of any discrepancies, inconsistencies and inadequacy of the below listed items until the period of initial design development is complete on the2nd February 2024 , 6 working weeks from anticipated contract execution date (08 December 2023 )… (a number of items were then listed, with commentary) 2 Once the derogations listed in this document have been concluded and approval from all parties obtained, and formal instruction received Mace Construct Ltd will take design responsibility on the items listed above. Mace Construct Ltd will take design responsibility, excluding planning approval from the 2nd of February 2024 , 6 working weeks from anticipated contract execution date (08 December 2023 ). The Heritage Windows will be completed within 5 weeks due to the criticality of these works.”
“30 Window meeting - Fabric / Jon Lowe / Structural 31 Progress meeting - Fabric / Structural 32 Revised drawings & details - Fabric / Structural 33 Heritage / Acoustic / BREEAM Approval 34 Final Drawing amendments 35 Submission for Approval 36 Client Approval Period 37 Instruction to MACE 38 Submission to Planning”
“An adjudicator and/or the court does not have the power to fix a completion date which is earlier than that which has previously been fixed by the Employer’s Agent, by virtue of clause 2.25.4 and/or clause 2.25.5.2 of the Contract”
“2.25.1 If on receiving a notice and particulars under clause 2.24: 2.25.1.1 any of the events which are stated to be a cause of delay is a Relevant Event; and 2.25.1.2 completion of the Works or of any Section is likely to be delayed thereby beyond the relevant Completion Date, then, save where these Conditions expressly provide otherwise, the Employer shall give an extension of time by fixing such later date as the Completion Date for the Works or Section as he then estimates to be fair and reasonable... 2.25.4 After the first fixing of a later Completion Date in respect of the Works or a Section…the Employer may by notice to the Contractor, giving the details referred to in clause 2.25.3, fix a Completion Date for the Works or that Section earlier than that previously so fixed if the fixing of such earlier Completion Date is fair and reasonable, having regard to any Relevant Omissions for which instructions have been issued after the last occasion on which a new Completion Date was fixed for the Works or for that Section. 2.25.5 After the Completion Date for the Works or for a Section, if this occurs before the date of practical completion, the Employer may, and not later than the expiry of 12 weeks after the date of practical completion shall, by notice to the Contractor, giving the details referred to in clause 2.25.3: 2.25.5.1 fix a Completion Date for the Works or for the Section later than that previously fixed if it is fair and reasonable having regard to any Relevant Events, whether on reviewing a previous decision or otherwise and whether or not the Relevant Event has been specifically notified by the Contractor under clause 2.24.1; or 2.25.5.2 subject to clauses 2.25.6.3 and 2.25.6.4, fix a Completion Date earlier than that previously fixed if that is fair and reasonable having regard to any instructions for Relevant Omissions issued after the last occasion on which a new Completion Date was fixed for the Works or Section; or 2.25.5.3 confirm the Completion Date previously fixed.”
“ 8-039 Prospective and retrospective extension of time The question of whether an extension of time (or an assessment of a reasonable time for completion) should be made prospectively or retrospectively raises important points of principle when identifying the critical path and causes of delay. In broad terms a prospective assessment may overestimate the delay since it will take no account of mitigation measures taken by the employer or contractor to reduce the delay or delay subsequently caused by the contractor’s default but, in certain circumstances, it can also underestimate the delay. The position is further complicated by the fact that both the Standard Form of Building Contract and the Infrastructure Conditions of Contract require extensions of time to be granted during the course of the contract (provided the appropriate notification and particulars have been given) as well as a review of the extensions of time once work is completed. Where an extension of time granted during the course of the works underestimates delay, this can be corrected on the review at completion, but overestimates cannot be corrected since the review process prohibits an earlier date being fixed. Where extensions of time (or an assessment of a reasonable time) are considered by a tribunal long after the events relied upon have occurred, it is suggested that it would be artificial to ignore entirely what in fact happened by adopting a wholly prospective approach. However, in Walter Lilly & Co Ltd v DMW Developments Ltd it was held that Cl.25.3.3 of the JCT Standard Form of Building Contract required a consideration of what critically delayed the works as they went along, as opposed to a purely retrospective exercise.”
“20. The adjudicator shall decide the matters in dispute. He may take into account any other matters which the parties to the dispute agree should be within the scope of the adjudication or which are matters under the contract which he considers are necessarily connected with the dispute. In particular, he may- (a) open up, revise and review any decision taken or any certificate given by any person referred to in the contract unless the contract states that the decision or certificate is final and conclusive”