“1.5 A party may believe they can show without a trial that an opponent's case has no real prospect of success on the facts, or that the case is bound to succeed or fail, as the case may be, because of a point of law (including the interpretation of a document). In such a case the party concerned may make an application under rule 3.4 or apply for summary judgment under Part 24 (or both) as they think appropriate.”
“Furthermore, I bear in mind that the warranties are standard terms of the Defendants’ Multiline Commercial Combined Policy, which may affect many other policyholders, and that provisions in the Warranties such as “be in full and effective operation at all times” and “put into full and effective operation at all times” are said to have even wider currency in the insurance market. In those particular circumstances, combined with the arguability of the Claimant’s points on interpretation, I can understand why the Judge considered it would also be appropriate to give the Claimant the opportunity to seek and adduce any relevant and admissible factual material available by the date of the trial.”
“An application to strike out a statement of case underCPR 3.4 (2)(a) should not be granted unless the court is certain that the claim is bound to fail – Hughes v Collin Richards & Co[2004] EWCA Civ 266 at [22] per Peter Gibson LJ; Barrett v Enfield LBC [2001] 2 All 550 at 557 per Lord Browne-Wilkinson.”
“WHEREAS (1) By a contract (the “Contract”) entered into or to be entered into between the Employer and the Contractor particulars of which are set out in the Schedule the Contractor has agreed with the Employer to execute works (the “Works”) upon and subject to the terms and conidiations therein set out. (2) The Guarantor has agreed with the Employer at the request of the Contractor to guarantee the performance of the obligations of the Contractor under the Contract upon the terms and conditions of this Guarantee Bond subject to the limitations set out in clause 2. NOW THIS DEED WITNESSES as follows: (1) The Guarantor guarantees to the Employer that in the event of a breach of the Contract by the Contractor the Guarantor shall subject to the provisions of this Guarantee Bond satisfy and discharge the damages sustained by the Employer as established and ascertained pursuant to and in accordance with the provisions of or by reference to the Contract and taking into account all sums due or to become due to the Contractor. (2) The maximum aggregate liability of the Guarantor and the Contractor under this Guarantee Bond shall not exceed the sum set out in the Scheduled (the “Bond Amount”) but subject to such limitation and to clause 4 the liability of the Guarantor should be co-extensive with the liability of the Contractor under the Contract. (3) The Guarantor shall not be discharged or released by any alteration of any of the terms, conditions or provisions of the Contract or in the extent or nature of the Works and no allowance for time by the Employer under or in respect of the Contract or the Works shall in any way release, reduce or affect the liability of the Guarantor under this Guarantee Bond. (4) Whether or not this Guarantee Bond shall be returned the Guarantor the obligations of the Guarantor under this Guarantee Bond shall be released and discharged upon Expiry (as defined in the Schedule) save in respect of any breach of the Contract which has occurred and in respect of which a claim in writing containing particulars of such breach has been made upon the Guarantor before Expiry. (5) The Contractor having requested the execution of this Guarantee Bond by the Guarantor undertakes to the Guarantor (without limitation of any other rights and remedies of the Employer or the Guarantor against the Contractor) to perform and discharge the obligations on its part set out in the Contract. (6) The Guarantor is therefore entitled to replace the Contractor with another one in case of breach of the contract or any delays accumulated on the schedule of execution, in order to perform the obligations undertaken by the Contractor with the Employer. (7) The Employer may assign this Guarantee Bond and the benefits of it, to any party to whom it assigns its interest under the Contract at any time, upon prior written consent expressed by the Guarantor References to the Employer shall include its assigns. The assignees should be the next listed: - Crestline Direct Finance L.P. as agent for the Secured Parties … … (8) The Guarantee Bond and the benefits thereof may be assigned to any party that has taken a valid assignment of the Contract but otherwise shall not be assigned without the prior consent of the Guarantor and the Contractor. (9) The parties to this Guarantee Bond do not intend that any of its terms will be enforceable, by virtue ofThe Contracts (Rights of Third Parties) Act 1999 or otherwise, by any person not a party to it. (10) This Guarantee Bond shall be governed by and construed in accordance with the law of England and only the courts of England shall have jurisdiction hereunder.”
“The Bond Amount: the sum of three million six hundred and ninety thousand two hundred and ninety six pounds sterling (£3,690,296.00 ) Expiry: Upon issue of the Practical Completion Certificate in respect of Section 2 or Section 1 if later for which the agreed date for completion is28th February 2022 .”
“The Employer has assigned its interest in the Contract to Crestline Direct Finance LP (as security trustee for the Secured Parties) and now intends to assign its interest in the Bond to the same party.”
“By the captioned Assignment, the Employer assigned its interest in the Bond to the Assignee by way of security. The said Assignment was notified to Euroins contemporaneously, and Euroins expressly consented to the Assignment in writing by its letter dated29 April 2020 . The Assignment was therefore valid pursuant to clauses 7 and/or 8 of the Bond.”
“Moreover, we see any debate as regards assignment as an attempted side-show. Since the demand is being made by both Crestline and Click jointly and severally, it does not matter what the status of the assignment is because: (i) if the assignment is invalid, Click would be entitled to make the call and be paid, (ii) if the assignment is valid either legally or equitably, then Crestline would be entitled to make the call and to nominate Click as an agent to receive the payment from Euroins. For this reason, we shall not perpetuate the assignment side-show by providing copies of documents relating to it.”
“68.2 Any claim made under the Bond on that date would lead to a £nil recovery under the Bond since, by clause 1, the Employer would only be entitled to damages “sustained by the Employer” and, as a result of the alleged assignment, the Employer would have sustained no loss. 68.3 An assignee can recover no more than an assignor could have recovered. As such, any claim by Crestline made under, and as assignee, of, the Bond would suffer from the same deficiencies and fail for the same reason as identified in paragraph 68.2 above.”
“Thank you for your recent correspondence which we acknowledge receipt of. Please accept our apologies for the delay in reverting. We are taking our client’s instructions and will respond substantially. Please bear in mind that we are seeking instructions from a client in Bulgaria on quite technical legal points and this is not matter where it is possible to get an instantaneous response. We are also grateful to you for providing a copy of the Assignment document of 28/5/24, which we are considering. You of course must do as you see fit in order to protect your client’s best interest. However, we would urge you to withhold taking any action in this matter until you hear from us and have an opportunity to consider our client’s response.”
“72.1 Crestline is not entitled to payment under the Bond for the reasons set out in this Defence. Further or alternatively, Crestline has failed to prove entitlement to sums claimed under the Bond for the reasons set out in this Defence. As such, it is denied that Euroins is in breach of the Bond (whether as alleged or at all). 72.2 It is denied that Euroins has caused Crestline to suffer loss and/or damage. 72.3 The basis of calculation of the losses said to have been sustained by Crestline are not admitted and Crestline is required to prove all losses. 72.4 Save as set out above, paragraph 29 sets out the basis of Crestline’s claim and is accordingly denied.”
“48. It was common ground that, in approaching the construction of the contracts, the court is required to determine the objective, natural and ordinary meaning of the relevant provisions against the background knowledge which would have been reasonably available to both parties and which may have affected the language used: see e.g. per Lord Hoffmann in Investors Compensation Scheme v West Bromwich BS[1998] 1 WLR 896 at 912H-913F. Adopting this approach, I have no doubt that, on the true construction of the contracts, the judge was wrong to conclude that clauses 8.5.3 and 8.7.3 could have no application if the contracts had already been terminated prior to the insolvency. My reasons may be summarised as follows. 49. First, it is clear that the provisions of clause 8.7.3 are intended to operate after termination of the contract. Indeed the entire scheme of clauses 8.7 and 8.8 are directed at setting out the respective rights and obligations of both parties after the contractor's employment under the contract has been terminated by the employer and necessarily the contract has come to an end: see the opening words of clause 8.7 – "if the Contractor's employment is terminated under clause 8.4, 8.5 or 8.6". To similar effect is clause 8.12 which addresses the consequences of termination by the contractor under clause 8.9 or by either party under clause 8.11 upon the happening of certain specified events. There is no wording in clause 8 which in any way suggests that the consequential provisions are not to apply after termination, or are not to apply after a termination by the contractor (pursuant to the saving provisions of clause 8.3.1) on the grounds of repudiatory breach (as opposed to pursuant to the express termination provisions contained in 8.4, 8.5 or 8.6). 50. Second, clause 8.5 ("Insolvency of Contractor") has a wider ambit than simply conferring a right of termination on the employer in the event of the contractor's insolvency. Thus clause 8.5.2 imposes an obligation on the contractor immediately to notify the employer if the contractor makes any proposal, gives notice of any meeting, or becomes the subject of any proceedings or appointment relating to insolvency, to enable the employer to decide on its options. And, most importantly, clause 8.5.3 expressly states that clause 8.7.3 applies as from the date when the contractor becomes insolvent "whether or not the Employer has given such notice of termination" – i.e. a termination notice under clause 8.5 based on the contractor's insolvency. Contrary to the judge's view, therefore, I see no necessity, or basis, for the implication of what would have to be an implied term that clauses 8.5.3 and 8.7.3 have no operation in circumstances where the employer has already terminated the contractor's employment, as it is entitled to do (pursuant to the saving provisions of clause 8.3.1), on the grounds of repudiatory breach (as opposed to pursuant to the express termination provisions contained in 8.4, 8.5 or 8.6), but do apply in circumstances where either: i) the employer has not served any notice of termination; or ii) the employer has already served a notice of termination under clauses 8.4, 8.5 or 8.6. In other words, given that clause 8.7.3 necessarily applies after termination in circumstances where the contractor's employment has already been terminated under clause 8.4 or 8.6, and can apply irrespective of whether the contract has already been terminated on the grounds of the contractor's insolvency under clause 8.5, I see no logical basis for the implication of a term that clauses 8.5.3 and 8.7.3 are not operative in circumstances where the contract has already been terminated by the employer on the grounds of repudiatory breach on the part of the contractor.” …. 53. Fifth, contrary to the submissions of Mr Darton, the obligation to pay under an interim certificate is a payment obligation. The fact that an employer is not obliged, in the event of the contractor’s insolvency, to make an instalment payment does not mean that the employer is discharged from all liability to make such payments as may be due upon the taking of the final account. All that clause 8.7.3, as applied by 8.5.3.1, does is to excuse the contractor from its interim payment obligations under the terms of cll 4.7 and 4.8. The contractor nonetheless remains liable to pay the sums which may be due under cll 8.7.4-8.7.5 and 8.8, if any, once an account has been taken. As Lord Hoffmann explained in Melville Dundas, instalment payments are “in their nature provisional liabilities”…” i) the employer has not served any notice of termination; or ii) the employer has already served a notice of termination under clauses 8.4, 8.5 or 8.6. In other words, given that clause 8.7.3 necessarily applies after termination in circumstances where the contractor's employment has already been terminated under clause 8.4 or 8.6, and can apply irrespective of whether the contract has already been terminated on the grounds of the contractor's insolvency under clause 8.5, I see no logical basis for the implication of a term that clauses 8.5.3 and 8.7.3 are not operative in circumstances where the contract has already been terminated by the employer on the grounds of repudiatory breach on the part of the contractor.”
“49. As part of his argument, Mr Oram submitted that… the fact that they had asserted that the claimant had repudiated the contract by serving a notice two days early, and that this had happened a few days before the insolvency event, meant that the contract had come to an end and there was no obligation on the part of County to pay the clause 8.7.5 debt. In my view, that argument fails for two reasons. 50. First, I consider that this argument is contrary to the scheme provided for in clauses 8.5 and 8.7 of the JCT Standard Form. Those provisions are designed – amongst other things – to ensure that, no matter what could be argued about prior events, the insolvency of the contractor gave rise to a clear and certain process which culminates in the notification of a debt pursuant to clause 8.7.5. This process was designed to prevent a contractor in the position of County from avoiding the consequences of their insolvency by seeking to argue, long after the event, that the contract had come to an end prior to their insolvency and that, in consequence, these clauses no longer applied. 51. Secondly, I am confirmed in that approach by the decision of the Court of Appeal (which is of course binding on me) in Wilson and Sharp Investments. In the passages identified at paragraph 31 above, Gloster LJ expressly rejected the argument that clauses 8.5.3 and 8.7.3 have no operation in circumstances where the employment had already been terminated on other grounds. Although the facts were different, the Court of Appeal made it plain that these clauses were intended to operate after the termination of the contract, without qualification. Indeed, at paragraph 49 of her judgment, Gloster LJ expressly identifies one such situation: "after a termination by the contractor…on the grounds of repudiatory breach." I respectfully agree with those conclusions. 52. Thus, the arguments belatedly raised by County's solicitors as to the validity or otherwise of the termination notice go nowhere. As from the date that County became insolvent, whether or not the employer had given notice of termination, and regardless of belated arguments as to repudiation, clauses 8.7.3-8.7.5 applied in any event. CAG certified that the debt had been calculated in accordance with those clauses, so County were in breach because they failed to pay it. Thus, subject to what I say about Declaration 2, the defendant is liable to pay the debt (subject to the cap introduced by the maximum amount recoverable) as damages under the Bond.”