“1. The Claimant is the freehold owner of 166 Croydon Road, SE20 7YZ, a mixed use property comprising a shop and residential flats. 2. On/About1st August 2024 , the Defendants commenceed [sic] party wall construction works at 164 Croydon Road. Within 2 weeks, severe cracking and movements were observed at the Claimant’s property. 3. The damage was reported on 20th August and worsened by3rd September 2024 , leading to forced evacuation of tenants by the London Fire Brigade and the Council’s Building Control. 4. The Defendants failed to carry out adequate pre-construction surveys, failed to safeguard adjoining structures, and ignored multiple warnings and formal objections. 5. On/About June 2025, the Claimant’s property was partially demolished on emergency grounds due to total structural failure, resulting from the Defendants’ acts and omissions. 6. As a result, the claimant has suffered - Full rebuild costs … 7. The Claimant asserts that Defendants 2 and 3, as directors and controlling minds of MYK Property Holdings Limited, were personally involved in directing or supervising the negligent works and failed to act to prevent the damage, despite being repeatedly notified. The Claimant brings this action against them in their personal capacities for negligence and breach of duty of care. 8. The Claimant seeks general and special damages as set out in the Schedule of Losses, interest and legal costs.”
“16. As to paragraph 4, the Claimant has failed to set out his case as against the Defendants. The Claimant has failed to set out, as against each of the 6 defendants against whom he has commenced proceedings, a concise statement of the facts on which he relies. 17. Further, the Claimant has failed to set out as against the Defendants, adequate allegations of negligence and/or nuisance to enable them to understand the claim which they have to meet. The Claimant’s general allegation that “The Defendants failed to carry out adequate pre- construction surveys, failed to safeguard adjoining structures, and ignored multiple warnings and formal objections” lacks specificity and particularisation. 18. The Claimant is invited to set out his case against the Defendants and, specifically: - 18.1 The grounds upon which he is pursuing the Defendants, as opposed to MYK; 18.2 What he says that the Defendants, either collectively or individually, did that they should not have done, or not do which they should have done; 18.3 How any loss and damage sustained (none admitted) is said to have been caused by any negligence and/or nuisance on the part of each of D1, D2 and D3 (none admitted).”
“The Claimant has made it expressly clear that the proceedings are against D1-D3 in their personal capacity as duty holders, not against MYK Property Holdings Ltd. The Defendants were each responsible for overseeing structural safety, compliance with CDM regulations, appointment of competent teams, and ensuring the structural integrity of adjoining properties. These duties arise independently of their corporate status and are based on direct negligence and nuisance. Evidence of failures to survey, stop works, or respond to repeated notifications has been included in the served materials.”
“2. The Particulars of Claim are vague, insufficiently particularised, fail to comply with significant provisions of the Civil Procedure Rules (“CPR”) and disclose no discernible grounds for a claim against the Sixth Defendant. … 5. The Claimant has pleaded no: 5.1 particulars of any contractual, tortious or statutory duty that might be owed by the Sixth [Defendant]; 5.2 particulars of the scope of any such duty; 5.3 particulars of the way in which any such alleged duty is said to have been breached; 5.4 expert evidence upon which he relies to establish either the scope of duty or breach; 5.5 particulars as to how any alleged breach of duty has caused any loss to the Claimant; 5.6 detailed particulars of the loss said to have been so caused. 6. The Claim Form and Particulars of Claim therefore disclose no reasonable grounds for bringing a claim, fail to comply with a rule practice direction or order and have no real prospects of success. ”
“The Sixth Defendant accepted service as the Claimant’s surveyor of No. 166 and engaged in multiple inspections, correspondence, and monitoring of movements of the party wall and structure. Accordingly, he cannot now disclaim all involvement. The Claimant contends the Sixth Defendant failed to identify critical risks, failed to recommend suspension of works, failed to insist on protective works or security, and thereby breached his professional and statutory duties.”
“1. The Claimant is the freeholder of 166 Croydon Rd SE20 7YZ (“the Property”), a mixed-use building which sustained significant structural damage due to works undertaken at the adjoining property 164 Croydon Rd, owned and/or developed by the First and Second Defendants via MYK Property Holdings Ltd (now dissolved). … 4. The Defendants owed the Claimant statutory, common law, and professional duties which they breached individually and/or collectively, causing damage to the Property and financial losses. 5. The Claimant relies on breaches of duties under the Party Wall etc Act 1996, CDM regulations 2015, professional negligence, and the general duty of care under common law. 6. As a direct consequence of the Defendants’ failures, the Property became unsafe and was evacuated on3 September 2024 . The following losses are claimed until2 July 2025 … Total:£1,503,818.00 . 7. The Claimant apportions liability jointly and severally as follows: First and Second Defendants - as freehold owners and developers, principal responsibility for structural collapse. Third Defendant - as contract administrator. Fourth Defendant – [as] director of Crown Builders Contractors, liable for construction-related failures. Fifth Defendant - Party Wall Surveyor for 164 Croydon Rd, failed to halt works despite evident risk. Sixth Defendant - Party Wall Surveyor for 166 Croydon Rd, failed to act impartially and protect the interests of the adjoining owner.”
“The basic purpose of pleadings is to enable the opposing party to know what case is being made in sufficient detail to enable that party properly to prepare to answer it.”
“CPR 16.4 (1)(a) requires that a particulars of claim must include "a concise statement of the facts on which the claimant relies". Thus, where the particulars of claim contain an allegation of breach of contract and/or negligence, it must be pleaded in such a way as to allow the defendant to know the case that it has to meet. The pleading needs to set out clearly what it is that the defendant failed to do that it should have done, and/or what the defendant did that it should not have done, what would have happened but for those acts or omissions, and the loss that eventuated. Those are 'the facts' relied on in support of the allegation, and are required in order that proper witness statements (and if necessary an expert's report) can be obtained by both sides which address the specific allegations made.”
“The court may strike out a statement of case if it appears to the court: … (a) that the statement of case discloses no reasonable grounds for bringing or defending the claim; … (c) that there has been a failure to comply with a rule, practice direction or court order …”
“The court may give summary judgment against a claimant or defendant on the whole of a claim or on an issue if – (a) it considers that the party has no real prospect of succeeding on the claim, defence or issue; and (b) there is no other compelling reason why the case or issue should be disposed of at a trial.”
“The statutory procedure is intended to be a simple, inexpensive dispute resolution mechanism. It enables reasonable and common sense solutions to be reached to the problems which inevitably arise when adjoining owners share a party wall. Whatever the surveyors decide is likely to cause some degree of inconvenience to both parties. The surveyors are not assuming a design obligation towards the adjoining owner. Both the building owner and possibly the adjoining owners may engage their own designers. They may put before the surveyor whatever submissions they wish.”
“Any agreement or acceptance made by either surveyor in this Award or subsequently during works on site shall not be taken to imply any responsibility by them or their appointed technical delegates for any structural or any other insufficiency in any part of the works whether existing or executed. Any drawings, calculations, specifications and design details either appended to this Award or provided to the Two Surveyors, are accepted in good faith and the Two Surveyors shall not be held accountable for any defective design or specification appearing in any such drawings, calculations, specifications and design details.”
“THAT we, being the appointed Two Surveyors, declare that insofar as theConstruction (Design and Management) Regulations 2015 (CDM) may apply to the said works, we have not contributed, developed or approved any design, such matters being the responsibility of the Building Owners, the Building Owners’ Designer and Principal Designer/Contractor.”