“an Order for summary judgment and/or strike out of the majority of the Claimant’s case (as set out in the Draft Order served with this Application), for the reasons set out in the witness statement of Thomas James Bourne dated1st April 2025 .”
“the claims for declarations set out in paragraph 97 of the Particulars of Claim be struck out pursuant toCPR 3.4 (2)(a) or summary judgment be entered in favour of the Defendant pursuant toCPR 24.3 in relation to the declarations set out in paragraph 97 of the Particulars of Claim and the claims for quantum in relation to Milestone 14 - Take-Over, acceptance (payment and interest) RR1 (payment and interest) and RR2 (payment and interest), as set out, inter alia, in the Quantum Appendix to the Particulars of Claim be struck out pursuant toCPR 3.4 (2)(a) or summary judgment be entered in favour of the Defendant pursuant toCPR 24.3 in relation to the claims for quantum in relation to Milestone 14 - Take-Over, acceptance (payment and interest), RR1 (payment and interest) and RR2 (payment and interest), as set out, inter alia, in the Quantum Appendix to the Particulars of Claim.” or or summary judgment be entered in favour of the Defendant pursuant toCPR 24.3 in relation to the claims for quantum in relation to Milestone 14 - Take-Over, acceptance (payment and interest), RR1 (payment and interest) and RR2 (payment and interest), as set out, inter alia, in the Quantum Appendix to the Particulars of Claim.”
“Remedies and Declarations BioConstruct is entitled to and/or claims declaration or declarations that: 97.1 A Take-Over Certificate ought to have been issued on or around1st April 2020 and/or that the Plant was in any event taken over on that date (or such other date as the Court shall determine). 97.2 GTP’s defaults and/or acts of prevention meant that the Performance Tests could not be carried out. For the avoidance of doubt, the defaults and/or acts of prevention relied on are: 97.2.1 Ms Billings’ refusal to issue and/or re-issue a Take-Over Certificate on or around1st April 2021 , which was unreasonable and/or a breach of duty’s obligations of the provisions referred to in paragraph 63 above. 97.2.2 GTP’s refusal to pay Milestone 10 and/or Milestone 12 and/or Milestone 14 no later than 14 days before the relevant FDP for each of these Milestone. 97.3 If (which is denied) BioConstruct is not entitled to the declaration sought in the proceeding sub-paragraph, a declaration that BioConstruct’s ability to deal with the Performance Test and procedures and/or COC Protocol/Snagging List was adversely affected by Force Majeure, as detailed in Section D.7.1 above. 97.4 The defects liability period ended on1st April 2021 in relation to all works other than the Tank Works, and that BioConstruct is not viable for any defects appearing or notified over the expiry of the relevant defects liability period for all works other than the Tank Works.”
“The claims for payment of sums due BioConstruct is entitled to and claims the sum set out in the Quantum Appendix from GTP. The total claimed is£918,480 . I apprehend that those claims are the subject of the relief proposed at paragraph 2 of the Draft Order.”
“In my judgment, the terms of r. 16.4(1)(a), the optional nature of the Reply, the rule restricting subsequent statements of case and the terms of the Practice Direction all point to the clear conclusion that any ground of claim must be pleaded in the Particulars of Claim. New claims must be added by amending the Particulars of Claim and cannot simply be pleaded by way of Reply. ... A Reply can be particularly useful in order to refute a ground of defence. For example, a Reply can properly plead) 20.1 a later date of knowledge pursuant to ss. 14 or 14A of theLimitation Act 1980 , or that the court should disapply the primary limitation period pursuant to ss. 32A or 33 of the Act, in answer to a plea in the Defence that the claim is statute barred; 20.2 that an exemption or limitation clause was not incorporated into the parties’ contract or that it was of no effect in excluding or limiting liability because the clause did not satisfy the condition of reasonableness within the meaning of theUnfair Contract Terms Act 1977 ; or 20.3 that the defendant is estopped by some earlier judgment or representation from relying upon a particular defence. In each example, the claimant would be pleading new facts in order to refute a defence, but it would not be pleading a new claim.”