“no further sum shall become due to the Contractor under this Contract other than any amount that may become due to him under clause 8.7.5 … .”
“following the completion of the Works and the making good of defects in them (or of instructions otherwise, as referred to in clause 2.35), an account of the following shall within 3 months thereafter be set out in a statement prepared by the Employer: 1. the amount of expenses properly incurred by the Employer, including those incurred pursuant to clause 8.7.1 and, where applicable, clause 8.5.3.3, and of any direct loss and/or damage caused to the Employer and for which the Contractor is liable, whether arising as a result of the termination or otherwise; 2. the amount of payments made to the Contractor; and 3. the total amount which would have been payable for the Works in accordance with this Contract;”
“if the sum of the amounts stated under clauses 8.7.4.1 and 8.7.4.2 exceeds the amount stated under clause 8.7.4.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor.”
“I cannot assume that it did not incur any such cost”
“[w]hat is the value of the works pursuant to clause 8.7.4.3 of the Contract”
“the total amount which would have been payable for the Works in accordance with this Contract”
“… while declarations are for the most part statutory in origin, they have throughout their history had a close affinity with equitable remedies which has left its mark upon them. This is especially evident in the discretionary nature of the declaration. This discretion is employed, as it was originally employed with regard to all equitable remedies, primarily to do justice in the particular case before the court. It is wide enough to allow the court to take into account most objections and defences available in equitable proceedings.”
“where it is a condition of enjoying the benefit that a burden is assumed, the assignee cannot enjoy the benefit without discharging the burden”