“... to ensure that all such arrangements have been made— (a) for providing supplies of water to premises in that area and for making such supplies available to persons who demand them; and (b) for maintaining, improving and extending the water undertaker’s water mains and other pipes, as are necessary for securing that the undertaker is and continues to be able to meet its obligations under this Part.”
“The Undertaker and the Promoter are entering into this Agreement for the purposes of addressing concerns expressed by the Undertaker as to the potential effects of the construction and operation of the authorised works on its interests.”
“In consideration of the terms of this Agreement (and their correct implementation) the Undertaker shall withdraw its petition in relation to the Bill ...”
“The Promoter and the Undertaker acknowledge that they have consulted and cooperated to assess the preliminary impact of the proposed Authorised Works on the Undertaker's statutory operations and that they will continue to engage in the development of the requirements identified in the Technical Appendices.”
“Through previous assessments and agreements between AW and HS2, AW has identified apparatus that is affected or is likely to be affected by Phase 1 and determined that protective measures are required. AW and the Secretary of State for Transport have agreed the Protective Provisions Agreement to address the concerns expressed by AW regarding the potential effects of the proposed Phase 1 on the Apparatus and the Sources, the resilience of public water supplies, and AW's ability to service its customers.”
“2 HS2 OBLIGATIONS 2.2 HS2 shall observe and perform its obligations in accordance with the terms of this Agreement including carrying out actions or providing information as soon as reasonably possible following reasonable request from AW from time to time. If any Costs are incurred by AW as a result of any breach of contract or negligence by HS2, then HS2 shall pay to AW all Costs incurred by AW as a result of HS2's breach or negligence. 2.3 HS2 will design, carry out and complete or procure the carrying out or completion of the APA Works in accordance with the Design Principles and exercising the reasonable skill, care and diligence as may be expected of a properly qualified and competent person engaged in carrying out works of a similar size, scope and complexity to the APA Works. 2.4 HS2 shall design, carry out and complete or procure the carrying out or completion of the APA Works in accordance with: .... (c) AW’s Requirements, including such other conditions or further works: i) As AW may reasonable consider necessary to prevent, address, alleviate or comply with (as applicable) an AW Operation Issue” (c) AW’s Requirements, including such other conditions or further works: i) As AW may reasonable consider necessary to prevent, address, alleviate or comply with (as applicable) an AW Operation Issue”
“7.6 Without prejudice to AW's other rights under this Agreement, where HS2 fails to fulfil any of its obligations under clause 2.2 and/or this clause 7 and such failure has a material adverse effect on the Sources, Apparatus, any land and property of AW or the ability of AW to perform its function as a statutory water undertaker or the ability to perform its statutory functions: (a) AW may (acting reasonably) issue a notice stating the steps to be taken to address the issue and requiring HS2 to remedy the situation within a specified time, taking into account these circumstances; and (b) in the event that HS2 is not able to or does not comply with the notice, AW shall take such steps as it reasonably considers appropriate to address the position and HS2 shall indemnify AW in respect of all resulting Costs. HS2 shall carry out or procure that the APA Works are carried out to AW's reasonable satisfaction.”
“Settlement Assessment Model 7.1 Before the commencement of any HS2 Works the Parties agree that HS2 shall prepare a Draft Settlement Assessment Model which addresses the following issues as applicable to the whole of the Apparatus and any land and property of AW prior to the Completion of the said works: An assessment to identify all AW assets within the zone of influence of the works and examine the impact of ground movements on these assets. The assessment shall consider the nature and asset condition of the AW assets and incorporate the asset specific protection and mitigation requirements of AW. ... 7.2 The HS2 assessment process shall follow three phases but will commence at the appropriate stage to the extent that each stage is necessary: Phase 1 - A `greenfield' movement assessment; Phase 2 — An assessment of the impact of the Phase 1 ground movement on AW assets using moderately conservative assumptions with respect to an asset's behaviour and its ability to resist movements; Phase 3 - A detailed analysis, with reassessment of the Phase 1 and 2 assumptions and parameters and taking into account the construction methodology and sequence.... 7.6 No part of the following below ground HS2 Works shall be commenced until the Final Settlement Assessment Model has been agreed in accordance with this paragraph 7 of Schedule 3: tunnelling and associated works including portal, shaft and cross passage construction;” tunnelling and associated works including portal, shaft and cross passage construction;”
“2. Existing Water Main crosses above HS2 Tunnel and would be affected by Settlement It anticipated that works would fall into one of the three categories below. Analysis would need to be carried out in advance to understand the combined effect that settlement, ground conditions and tunnel construction methodology will have on the existing pipe material in order to classify the works on each asset in to the categories below. Options Where assessment of the risk or consequence of the existing service failing due to settlement is significant the existing asset should be replaced by a flexible pipe capable of coping with the expected differential settlement. These replacements would be carried out in HPPE or other materials or solutions that provide a flexible pipeline that will accommodate the predicted settlement: material Selection would be based on upon the specific circumstances and ground conditions relevant to each site. The extent of the replaced sections would depend upon the settlement analysis and the effect / risk of failure of the existing pipework /material. Where risk of catastrophic failure risk of an asset is perceived to be low and there is no risk of significant damage from a burst, an alternative approach would be to set up leakage monitoring on the existing asset to detect failure. Do nothing —Existing Pipe is flexible and settlement will not cause this asset to fail.”
“This Agreement is the contractual framework to enable the instruction of Work Orders for the DCA Works to be undertaken by AW on behalf of HS2. It is intended that the Initial Work Order will be instructed by HS2, after signature of this Agreement pursuant to clause 7.10 hereof, to cover the reasonable project management and other initial costs of AW as agreed between HS2 and AW prior to the date hereof. HS2 may instruct subsequent Work Order Requests on or after the date of this Agreement. The instruction of all Work Order Proposals (following a Work Order Request) will be subject to approval through HS2's governance and assurance processes.”
“Without prejudice to clause 5.2, HS2 shall be responsible for coordinating the DCA Works with the other Phase 1 works (including the APA Works) to be carried out by HS2 or its contractors or other utilities and/or undertakers so as to avoid any adverse impact on AW’s Apparatus aquifers and groundwater sources (including the Sources) and the resilience of public water supplies.”
“HS2 and AW agree to work collaboratively to proactively manage risk, with the intention of avoiding risk or, where avoidance is not possible, mitigating any impacts on AW arising as a result of the HS2 Works so far as reasonably possible.”
“Pursuant to the APA and the DCA, the Defendant accordingly became obliged to procure the timeous execution by the Claimant of the Original Diversion Works via the mechanisms of the DCA, at the expense of the Defendant.”
“Analysis would need to be carried out in advance to understand the combined effect that settlement, ground conditions and tunnel construction methodology will have on the existing pipe material in order to classify the works on each asset in to the categories below.”