“Dear Peter Thank you for your emails. As discussed, it remains our current intention to continue with all Work Orders signed between Grain Communications Ltd and Shepherd Groundworks Ltd. However, as mentioned on Monday's call, we are in further discussions with relevant stakeholders in relation to our build programme, and it currently does not look like we will be able to commence Works on Site in relation to the following Work Orders before the end of 2023: * Blyth Phase 3; * Newcastle Phase 8; * Newcastle Phase 9; and * Wallsend Phase 5. All other Work Orders are unaffected. We will continue to keep in touch with you regarding our programme for the Works under these Work Orders and will let you know when anything changes. Regards Richard”
“84. However, I do not consider that under the definition of a Variation in this Contract that GCL can cancel the commencement of the whole of the Works, or postpone the commencement of the whole of the Works without clear words which would convey to the reasonable recipient that that is what was intended so that the Contractor would know that the Variation mechanism had been triggered under the Contract. 85. In my opinion, the reasonable recipient of the email issued by GCL on24th October 2023 (12:13) would not understand that it was being issued either as a Variation to the Work Order, under clause 11.1, or as confirmation of an oral variation to the Work Order, under clause 11.2, for the simple reason that it does not make any mention of the fact that it is being issued either as a Variation, or as a confirmation of any oral variation that may have been given in the telephone conversation held on Monday23rd October 2023 . 86. As it seems to me that GCL’s email seeks to cancel the commencement of the Works under the Work Order and is not labelled in any respect as a Variation I do not consider that it can be interpreted as something that in my opinion it was not intended to be.”