“In this Part a “construction contract” means an agreement with a person for any of the following— (a) the carrying out of construction operations.”
“This Part applies only to construction contracts which—(a) … (b) relate to the carrying out of construction operations in England, Wales or Scotland.”
“In this Part “construction operations” means, subject as follows, operations of any of the following descriptions— (a) construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings, or structures forming, or to form, part of the land (whether permanent or not); (b) construction, alteration, repair, maintenance, extension, demolition or dismantling of any works forming, or to form, part of the land, including (without prejudice to the foregoing) walls, roadworks, power-lines, electronic communications apparatus, aircraft runways, docks and harbours, railways, inland waterways, pipe-lines, reservoirs, water-mains, wells, sewers, industrial plant and installations for purposes of land drainage, coast protection or defence; … (e) operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works;”
“A pier under which water flows is not normally considered to be within the realm. There are some cases, however, where a structure has specifically been included within the realm by act or order, in which case mean high water (springs) mark and EOR are shown around the limits of the structure”
“… the baselines from which the breadth of the territorial sea adjacent to the United Kingdom, the Channel Islands and the Isle of Man shall be established in accordance with the relevant provisions of the United Nations Convention on the Law of the Sea (Cmnd 8941), as modified and set out in Schedule 1 to this Order”
“… waters on the landward side of the baseline of the territorial sea form part of the internal waters of the State.”
“For the purpose of delimiting the territorial sea, the outermost permanent harbour works which form an integral part of the harbour system are regarded as forming part of the coast ...”
“… (c) Whether something forms or is to form part of land is ultimately a question of fact and this involves fact and degree. … (f) To be a fixture or to be part of the land, an object must be annexed or affixed to the land, actually or in effect. An object which rests on the land under its own weight without mechanical or similar fixings can still be a fixture or form part of the land. It is primarily a question of fact and degree. (g) In relation to objects or installations forming part of the land, one can and should have regard to the purpose of the object or installation in question being in or on the land or building. Purpose is to be determined objectively and not by reference simply to what one or other party to the contract, by which the object was brought to or installation brought about at the site, thought or thinks. Primarily, one looks at the nature and type of object or installation and considers how it would be or would be intended to be installed and used. One needs to consider the context, objectively established. If the object or system in question was installed to enhance the value and utility of the premises to and in which it was annexed, that is a strong pointer to it forming part of the land. (h) Where machinery or equipment is placed or installed on land or within buildings, particularly if it is all part of one system, one should have regard to the installation as a whole, rather than each individual element on its own. The fact that even some substantial and heavy pieces are more readily removable than others is not in itself determinative that the installation as a whole does not form part of the land. Machinery and plant can be structures, works (including industrial plant) and fittings within the context of s 105(1)(a)–(c) of the HGCRA.”
“22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question, then, whether right or wrong, his decision is enforceable: see Carillion v Devonport. 22.2 If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice: see Ballast, Broadwell, and Thermal Energy. 2.3 However, for that result to obtain, the adjudicator’s failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable: see Bouygues and Amec v TWUL. 22.4 It goes without saying that any such failure must also be material: see Cantillon v Urvasco and CJP Builders Ltd v William Verry Ltd. In other words, an error must be shown to have had a potentially significant effect on the overall result of the adjudication: see Kier Regional v City and General (Holborn) Ltd.”
“Firstly, an inadvertent failure to address a particular issue is in the nature of an error within the adjudicator’s jurisdiction rather than a breach of the rules of natural justice. Secondly, and if that is wrong, it would be an unusual case where the court would both draw the inference that an issue had not been addressed and conclude that the failure to address the issue was so significant that it meant that the adjudicator had not decided the dispute referred to him and/or that the conduct of the adjudication was so unfair that the decision should not enforced. The more significant the issue, the less likely it is to be inadvertently overlooked; the less significant it is, the more likely it is that it has been taken account of in the round.”
“150.00 Despite the fact that KML deny that the ground conditions have changed from the site inspection data and therefore do not accept liability they have actually admitted that they agree the ground conditions had changed. 151.00 The KML8 March 2022 email from Simon James of KML agrees and admits there is a change to ground conditions. 152.00 On that basis I find that KML are liable and should pay the sums claimed.”
“At paragraph 84 of its Referral, VEL was content to award KML an “abatement” worth£15,833 in respect of its equipment. KML accounted for the reduction in a different way, but it was not disputed between the parties that KML should have the benefit of an abatement of£15,833 . Indeed, the adjudicator recorded at paragraph 107 of his Decision that “this is a voluntary reduction made by VEL”