“A person who has made or agreed to make any payment in bona fide settlement or compromise of any claim made against him in respect of any damage (including a payment into court which has been accepted) shall be entitled to recover contribution in accordance with this section without regard to whether or not he himself is or ever was liable in respect of the damage, provided, however, that he would have been liable assuming that the factual basis of the claim against him could be established.”
“I think that the judge here was wrong in regarding the settlement as wholly irrelevant. I think, though it is not conclusive, that the fact that it is admittedly an upper limit would lead to the conclusion that, if reasonable, it should be taken as the measure. The result of the judge’s conclusion is that [the claimants] must prove their damages strictly to an extent to show that they equal or exceed£43,000 ; and that if that involves, as it would here, a very complicated and expensive inquiry, still that has to be done. The law, in my opinion, encourages reasonable settlements, particularly where, as here, strict proof would be a very expensive matter.”
“If, upon the evidence, the judge is satisfied that the damages would be somewhere around the figure at which the plaintiffs had settled, he would be justified in awarding the settlement figure. I do not consider that it is part of his duty to examine every item in those circumstances.”
“The question is not whether the plaintiffs acted reasonably in settling the claim, but whether the settlement was a reasonable one; and, in considering it, the court is entitled to bear in mind the fact that costs would grow every day the litigation was continued. That is one reason for saying that it is sufficient for the purpose of the plaintiffs if they satisfy the judge that somewhere around the figure of settlement would have been awarded as damages. This view is supported by Fisher v. Val de Travers 45 L.J. (C.P.) 479, 35 L.T. 366, where the second of the questions left by the judge to the jury had been whether the sum paid as compensation was reasonable, and the jury found that it was. In that case, in the course of the argument, Brett J, asked counsel: ‘Supposing Hicks had claimed£1,000 , which, as the damages really amounted to£110 , we now know would be excessive, and the plaintiffs had paid, could they have recovered that from the defendants?’; and counsel answered: ‘No, because the plaintiffs would have to show they paid the proper compensation.’ That I believe to be the test.”
“It is possible to identify agreed costs of£1,423.86 that were clearly referable to defects 17(i)-(ii), and I award that sum.
“Motors shall be of the totally enclosed air-cooled type and have a degree of protection of not less than IP54 except in dirty areas subject to wash down such as the lime preparation area, or IP55 unless they are situated outdoors, exposed to weather, or situated in areas covered by water-spray fire fighting equipment, when they shall be weatherproof and have a degree of protection of not less than IP56.”
“any change from that stated in the Subcontract to the Subcontract Plant, to the Subcontract Works, to the Site, to the method of working, or to the sequence or timing of the work.”
“The Contract Manager may at any time instruct the Subcontractor to prepare or to assist him in the preparation of a potential Variation and the Subcontractor shall comply with such instruction and give to the Contract Manager his recommendations for the form and scope together with an estimate of the Cost and impact on the Approved Programme of the Variation at such time and in such detail as the Contract Manager shall require.”
“The Subcontractor shall be entitled to an addition to the Subcontract Price determined in accordance with and subject to Clause 19 (Claims) in respect of the Cost of preparing a potential Variation in accordance with Sub-clause 16.3, of commenting upon a proposed Variation in accordance with Sub-clause 16.4 or of responding to a Variation Order in accordance with Sub-clause 16.5 and 16.6, whether or not any such potential or proposed Variation is ordered or amended or such Variation Order is confirmed or withdrawn.”
“If the Subcontractor intends to claim any additional payment which does not arise out of a Variation, he shall notify the Contract Manager of such intention within ten days of becoming aware of the event which gives rise to the claim, and shall establish and maintain records relevant to the claim, together with such additional records as the Contract Manager may direct. All such records shall be open to inspection by the Contract Manager.” 74.2 Clause 19.3A provides: “Service of notice in accordance with the Subcontract Conditions is a condition precedent to the entitlement of the Subcontractor to any compensation for any matter to which clause 19.1 relates.”
“We can help, but it will require much more than the Contract stipulate (sic), and what we have agreed to. Please find a Variation Order in this regard – please sign and send back if you would like Outotec’s help.”
“The Subcontract shall make no Variation except as ordered by the Contract Manager.”
“The Contract Manager shall have the right at any time on reasonable notice to examine any Documentation which has been or is being prepared by the Subcontractor or his Sub-subcontractors for the purposes of the Subcontract except any Documentation of a class or description which Schedule 2 or any Special Condition states shall not be shown to the Contractor or the Contract Manager.”
“The Subcontract Agreement comprises the design, manufacture, factory testing, painting, and advice on the following: installation and erection, commissioning, putting into normal operation, testing for performance, certification, reliability on completion, instruction of the operator’s personnel in the operation and maintenance of the Works. The Subcontractor’s responsibilities under the Subcontract are limited to the Subcontract Works and advisory services during construction and commissioning.”
“The Sub-Contract Works shall include the design, manufacture, supply, commissioning, advice and testing advice of a fluidised bed gasification Facility. The Subcontractor shall include for all Works associated with the Sub-Contract Agreement and elsewhere in the specifications … The Scope of Works shall include, but not be limited to: … • On-site advisor during installation and integration • On-site advisor during testing, commissioning and certification … The Subcontractor shall provide the complete fluidised bed energy system, including but not limited to: … • Advisory and attendances”
“The Subcontractor shall provide all services required under this Sub-Contract Agreement to provide an operational gasification plant. The scope of services shall include but not be limited to … • Project management, implementation and construction advisement … The scope of work shall include supply and service as listed below but not be limited to … • commissioning and performance testing advisement • on-site advisory services (for installation and commissioning”
“In any event, if a right to abate did remain, M+W would need to show that, by reason of Outotec’s breaches of contract, the value of their work was less than the sum claimed. This M+W have not sought to do.”
“Although there is not a complete harmony of approach to be discerned from this line of cases, I derive seven legal principles from the authorities cited: (i) In a contract for the provision of labour and materials, where performance has been defective, the employer is entitled at common law to maintain a defence of abatement. (ii) The measure of abatement is the amount by which the product of the contractor’s endeavours has been diminished in value as a result of that defective performance. (iii) The method of assessing diminution in value will depend upon the facts and circumstances of each case. (iv) In some cases, diminution in value may be determined by comparing the current market value of that which has been constructed with the market value which it ought to have had. In other cases, diminution in value may be determined by reference to the cost of remedial works. In the latter situation, however, the cost of remedial works does not become the measure of abatement. It is merely a factor which may be used either in isolation or in conjunction with other factors for determining diminution in value. (v) The measure of abatement can never exceed the sum which would otherwise be due to the contractor as payment … (vii) Claims for delay, disruption or damage caused to anything other than that which the contractor has constructed cannot feature in a defence of abatement.”
“If the Contractor does not make payment in full by the Final Date for Payment of the amount of an instalment: (a) in accordance with any notice issued under Sub-clause 41.7; or (b) certified and notified in accordance with Sub-clause 41.4; or (c) where applicable in accordance with Sub-clause 41.6; or if either party does not make any payment due under any other provision of the Subcontract by the Final Date for Payment the amount not paid shall bear interest compounded daily from the Final Date for Payment until the amount not paid is received by the other party at an annual rate which is two per cent above the Agreed Rate for the first month of delay. The annual rate of interest shall be increased by a further two percent at the end of each further month of delay, up to the end of the third month. If the delay exceeds three months the annual rate of interest shall thereafter be ten per cent above the Agreed Rate.”
“Any sum certified and notified as due in accordance with Sub-clause 41.4 shall be due for payment fourteen days (or fifty-six days in the case of the final request for payment) after the date of receipt by the Contract Manager of the Subcontractor’s request for payment in accordance with Sub-clause 41.3. The Contractor shall pay the amount so notified by a date (the Final Date for Payment) which shall be thirty-five days (or seventy-seven days in the case of the final request for payment) after the date of receipt by the Contract Manager of the Subcontractor’s request for payment in accordance with Sub-clause 41.3.”
“If for any reason the Contractor, or the Contract Manager on his behalf, fails to notify the sum due in accordance with Sub-clause 41.4 by the payment due date determined in accordance with Sub-clause 41.5 the sum notified by the Subcontractor in his request for payment in accordance with Sub-clause 41.3 shall be due for payment by the Final Date for Payment.”
“If the amount of a payment which is: (a) notified in accordance with Sub-clause 41.4 (and no notice is given by the Contractor under Sub-clause 41.7 in respect of such payment); or (b) stated in a notice given by the Contractor under Sub-clause 41.7; is referred to an adjudicator appointed in accordance with Clause 47 (Adjudication) and if the decision of the adjudicator as to the amount which is to be paid by the Contractor is that more shall be paid than the amount stated as in (a) or (b) as applicable, the additional amount shall be paid not later than: (i) seven days from the date of the adjudicator's decision; or (ii) the Final Date for Payment; whichever is the later.”