"1.1. The Contractor shall: 1.1.1. start the Works on the Start Date; 1.1.2. carry out the Works regularly, diligently and in a good and workmanlike manner to ensure that they are completed properly in accordance with the Contract and all statutory requirements by the Date for Completion ..."
"2.1. The Customer shall allow the Contractor reasonable access to the site for the following purposes … 2.1.2. carrying out the works. 2.2. The Customer has appointed the Architect/Contract Administrator and may replace it by informing the Contractor of the replacement and the date the replacement takes effect."
"5.4. The Architect/Contract Administrator may issue the following instructions: 5.4.1. Change to Work Instructions … 5.4.7. instruction requiring further documents … 5.6. All instructions from the Architect/Contract Administrator shall be in writing. The Contractor shall comply with instructions immediately … 5.9. Within 10 days of receiving a change to Works Instruction the Contractor shall calculate the effect (if any) of the instruction on the Contract Price and/or the Date for Completion and shall submit details to the Architect/Contract Administrator. After this period the right to a Revision of Time and additional payment will be lost."
"7.1. At the frequency specified in Item (O) of the Contract Details the Architect/Contract Administrator shall issue the Parties with a Payment Certificate … 7.3.1. the Contractor shall issue the Customer with an invoice based on the Payment Certificate; 7.3.2. the Customer shall pay the invoice within 14 days of receipt."
"Invoices to be raised by the Contractor on Payment Dates. The invoice to be submitted by the Contractor must include a full breakdown of costs spent to date and a copy of all receipts for goods purchased on behalf of the client together with a running summary against the overall Contract Sum."
"9.9. The Contractor may apply (with supporting documentation) for a revision of time if the works are delayed by any of the following: 9.9.1. the Architect/Contract Administrator issues a Change to Works Instruction … 9.9.3. the Customer or its agents cause delay or disruption … 9.9.6. the Architect/Contract Administrator issues an Instruction resolving an inconsistency unless the inconsistency is due to a document prepared by the Contractor … 9.9.8. the Contractor suspends some or all of its duties … 9.9.11. the Customer's risks (including errors in the design prepared by the Customer: see Clause 9.1.2) … 9.10.1. if the event is a single event the Contractor shall apply for the Revision of Time within 10 days of the event ending; 9.10.2. if the event is a continuing event the Contractor shall inform the Architect/Contract Administrator of the event within 10 days of its commencing and shall apply for: (a) revision of Time (with supporting documentation) within 10 days of the last element of the event … 9.10.3. if the Contractor fails to apply within these periods it will lose the right to a Revision of Time … 9.13. If an event attributable to the Customer or its agents adds costs and expenses to the Works the Contractor may apply for an adjustment to the Contract Price … 9.13.2. if the event is a continuing event the Contractor shall inform the Architect/Contract Administrator of the event within 10 days of it commencing and shall apply for the additional payment (with supporting documentation) within 10 days of the last element of the event; 9.13.2. if the Contractor fails to adhere to these time periods the right to the additional payment will be lost"
"If a Revision of Time and/or a request for an additional payment are submitted these will be assessed via a Change Order. Change Orders must be completed with the following information: Description of the proposed change; Reason for the proposed change (client request, instruction from Building Control etc); Time impact of the proposed change to the building programme in days; Cost impact of the proposed change to the works - £+/-. Additional payments will only be approved if a Change Order has been submitted prior to the additional works or change has been carried out. Once completed and issued Change Orders must be approved or rejected within 7 days of this in order to avoid secondary impact for the project programme."
"Any change to the Contract that the parties agree shall be written down and signed by both parties."
"If the Contractor: 12.3.1. abandons the Works; 12.3.2. fails to proceed regularly and diligently; 12.3.3. consistently fails to comply with instructions; 12.3.4. is in material breach of the Contract; 12.3.5 then the Architect/Contract Administrator may issue the Contractor with a Notice of Intention to Terminate referring to this clause and stating the reason. 12.4. If the Contractor has not remedied the default within 14 days of receiving the Notice the Customer may end the Contractor's employment under the Contract by issuing a Notice of Termination."
"assessed as the cost of providing overnight accommodation off-site for a family of four in rented accommodation."
"Drawings, Design Cube Contract Pack March 2015. Pricing Documents, Outline Specification and Tender Price Rev.B March 2015. Specification noted on Contract Pack Drawings."
"Some significant investigations in terms of trial pits be undertaken to ascertain exactly what foundation was installed in terms of width and depth and … a further assessment of loadings … can be undertaken based on the findings."
"The plaintiff who carries out either repair or reinstatement of his property must act reasonably. He can only recover as damages the costs which the defendant ought reasonably to have foreseen that he would incur and the defendant would not have foreseen unreasonable expenditure. Reasonable costs do not however mean that the minimum amount which with hindsight it could be held would have sufficed. When the nature of the repairs are such that the plaintiff can only make them with the assistance of expert advice the defendant should have foreseen that he would take such advice and be influenced by it."
"The Court has to choose between them or variants of them … The assessment has to be made on the basis of what the plaintiff can reasonably do."
"It is not for the Court to consider de novo what should have been done and what costs should have been incurred either as a check on the reasonableness of the plaintiff's actions or otherwise."