‘A result of your failure to proceed regularly and diligently, and your failure to remedy the defaults stated in the Notice of Default this letter should be considered Notice that the Contract is terminated with immediate effect in accordance with clause 8.4.2 of the Contract.’
‘... Further, even if our client was in repudiatory breach (which is denied), you have not challenged the underlying entitlement to terminate. Our client was always entitled to terminate and would have done so. Your client has therefore suffered no loss because our client’s termination can be justified at common law (those rights being expressly reserved: JCT Condition 8.3.1); and, separately, because our client was entitled to and would have terminated the contract in any event. Your client has not claim for damages, because it would never have been permitted to complete the works…’
‘RYC also disputes that there were substantive grounds for MC-L to terminate. The grounds cited by MC-L were RYC’s failure to progress the works regularly and diligently, and to comply with its obligations under the CDM Regulations; but the CA acknowledged that RYC was entitled to an extension of time to the end of March 2022 [Tab 2 / 3 and 45], and RYC obtained an independent report on health and safety matters at the beginning of November 2021, and actioned the one minor issue identified. RYC also disputes that the notices that the CA issued in relation to the termination were sufficiently clear to be valid. However, this adjudication is not concerned with these substantive issues; the Adjudicator is not asked to consider these; and RYC reserves the right to refer these issues to adjudication separately in due course.’
‘5. As explained below, the termination was valid as the exercise of the contractual right under Condition 8.4. In any event MCL is entitled in law to justify that that termination, as an accepted repudiation at common law. Where, as here, the rights consequent upon each method of termination are the same, the same notice (even if expressed to be given under the contractual mechanism) will be capable of operating to terminate both in the exercise of the contractual right, and as an acceptance of a repudiatory breach. 6. The notice of adjudication (in para. 10) purports to confine the scope of this adjudication to the issue of compliance with Condition 8.4. It thereby attempts to preclude the Adjudicator from considering whether (if Condition 8.4 was not operated properly) MCL is entitled to justify the termination as the acceptance of a repudiatory breach. It cannot confine the adjudication in that way.’
‘9. The third declaration sought in this adjudication, is that MCL’s termination was wrongful and invalid, and amounted to a repudiatory breach. The Adjudicator cannot reach that conclusion without considering whether MCL had any lawful entitlement to terminate, and whether it exercised that right. The issues in this adjudication, therefore, concern not simply the meaning and procedural requirements of Condition 8.4, but the substantive entitlement to terminate and whether that has been properly effected on any basis.’
‘66. To terminate at common law, the claimant must establish: (i) that the defendant was in repudiatory breach of the contract, and (ii) a communicated decision to bring the contract to an end, i.e. his acceptance of the repudiation.’
‘2.2 if RYC is correct on point 2.1 above, then MC-L failed to comply with the requirements for a valid termination of RYC’s employment under the Contract and MC-L was itself in repudiatory breach. RYC is therefore entitled to the relief sought by RYC in this adjudication, subject only to the second issue. The second issue is that MC-L contends that if MC-L failed to operate the clause 8 provisions correctly, its termination letter received on1 December 2021 may be justified as constituting the acceptance of a repudiatory breach by RYC. RYC’s position is that that is not so as a matter of fact and law, without it being necessary to investigate whether there was in fact any repudiatory breach; 2.3 repudiatory breach and the substance of MC-L’s contention that RYC was in repudiatory breach (which is not within the scope of the adjudication but is in any event denied);’
‘Can the purported Notice of Default of 11 November constitute acceptance of Repudiatory Breach’
‘As explained below, the termination was valid as the exercise of the contractual right under Condition 8.4. In any event MCL is entitled in law to justify that that [sic] termination, as an accepted repudiation at common law. Where, as here, the rights consequent upon each method of termination are the same, the same notice (even if expressed to be given under the contractual mechanism) will be capable of operating to terminate both in the exercise of the contractual right, and as an acceptance of a repudiatory breach.’
‘52. Applying the test as set out in Vannin, it is my view and I so find that the reasonable recipient of the letter dated11 November 2021 from Smithers Purslow would have understood, as expressly stated by the letter itself, that it was a notice given in accordance with clause 8.4 of the Contract (Termination by Employer) and no more. 53. As noted above, I have not been directed to any formal acceptance of what MCL now alleges to be RYC’s repudiatory breaches (other than as now advanced in the submissions in this adjudication). … 57. Therefore, in respect of MCL’s reservation as to my having jurisdiction, I consider that nothing has been brought to my attention that would lawfully deprive me of jurisdiction to decide this dispute. 58. In respect of RYC’s request for me to provide my non-binding views on MCL’s ‘substantive case as to alleged repudiatory breach’
‘86. Given my decision as to the extent of my jurisdiction I cannot and do not make any findings as to the grounds upon which MCL claim to support the allegation of repudiatory breach on the part of RYC. However, that leaves open the issue as to whether MCL’s purported termination of RYC’s employment under the Contract is to be equated to acceptance of (what is alleged to be) RYC’s repudiatory breaches? 87. I have noted above paragraph 6-121 of Keating, the relevant part states: It may, however, depend on the order in which the alternatives are effected. An acceptance of repudiation followed in the alternative by a contractual determination expressed to be without prejudice to the acceptance of repudiation might achieve the contractual determination if there was held to have been no repudiation to accept ... 88. It seems to be as a matter of principle that if an ineffective acceptance of repudiation followed in the alternative by a contractual determination can provide a lawful acceptance, then (in the absence of any authority being provided by the parties or found by me) it seems reasonable and logical that an ineffective contractual determination followed by acceptance of repudiation can also provided a lawful acceptance, but subject to “... words or conduct which [properly] amount to a renunciation”: paragraph 27-049 of Chitty. 89. Paragraph 27-050 of Chitty states: The renunciation must be “made quite plain”. In particular, where there is a genuine dispute as to the construction of a contract, the courts may be unwilling to hold that an expression of an intention by one party to carry out the contract only in accordance with his own erroneous interpretation of it amounts to a breach which entitles the other party to terminate performance of the contract; and the same is true of a genuine mistake of fact or law. Even the giving of notice of rescission, or the commencement of proceedings by one party claiming rescission of the contract, does not necessarily amount to a breach which entitles the other party to terminate further performance of the contract, since such action may be taken in order to determine the respective rights of the parties, and so not evince an intention to abandon the contract. On the other hand, it is, generally, no defence for a party who is alleged to have committed a breach which entitles the other party to terminate the contract to show that he acted in good faith. The courts have struggled to reconcile the latter proposition with their reluctance to conclude that a party who has acted in good faith but was mistaken has thereby committed a breach which entitles the other party to terminate the contract. [He then quotes from RYC’s emails of 9 November and letter of11 November 2021 ] … 92. I do not read RYC’s e-mail dated 9 November and letter of11 November 2021 as exhibiting an absolute refusal to continue with the Works and in many respects the correspondence shows that in circumstances where RYC considered it is entitled to extensions of time9 (and possibly payment for loss and expense) it cannot be said that RYC was not trying to adhere to the Contract. 93. Accordingly, I find that even if MCL was entitled to determine the contract by reliance on the invalid contractual termination letter dated11 November 2021 , it cannot be said, in my view, that RYC was in repudiatory breach on the ground relied on by MCL at paragraph 71 of its Response. (3) Was MCL’s action of taking / re-taking possession of the site on1 December 2021 an act of repudiation? 94. As noted on the chronology above, with the CA’s letter dated30 November 2021 (but sent by e-mail and hand delivered to RYC on1 December 2021 ) the CA’s accompanying e-mail confirmed that: ‘The client has arranged for security to take possession of the site, please do not attempt to gain access without prior arrangement. We can organise a convenient time over the coming days for tools and belongings to be collected and a meeting to discuss the final account.’ 95. The clear intent of the CA’s e-mail noted above was to bar RYC from the site, thus rendering impossible any further performance by RYC.’
‘i) A referring party is entitled to define the dispute to be referred to adjudication by its notice of adjudication. In so defining it, the referring party is entitled to confine the dispute referred to specific parts of a wider dispute, such as the valuation of particular elements of work forming part of an application for interim payment. ii) A responding party is not entitled to widen the scope of the adjudication by adding further disputes arising out of the underlying contract (without the consent of the other party). It is, of course, open to a responding party to commence separate adjudication proceedings in respect of other disputed matters. iii) A responding party is entitled to raise any defences it considers properly arguable to rebut the claim made by the referring party. By so doing, the responding party is not widening the scope of the adjudication; it is engaging with and responding to the issues within the scope of the adjudication. iv) Where the referring party seeks a declaration as to the valuation of specific elements of the works, it is not open to the responding party to seek a declaration as to the valuation of other elements of the works. v) However, where the referring party seeks payment in respect of specific elements of the works, the responding party is entitled to rely on all available defences, including the valuation of other elements of the works, to establish that the referring party is not entitled to the payment claimed. vi) It is a matter for the adjudicator to decide whether any defences put forward amount to a valid defence to the claim in law and on the facts. vii) If the adjudicator asks the relevant question, it is irrelevant whether the answer arrived at is right or wrong. The decision will be enforced. viii) If the adjudicator fails to consider whether the matters relied on by the responding party amount to a valid defence to the claim in law and on the facts, that may amount to a breach of the rules of natural justice. ix) Not every failure to consider relevant points will amount to a breach of natural justice. The breach must be material and a finding of breach will only be made in plain and obvious cases. x) If there is a breach of the rules of natural justice and such breach is material, the decision will not be enforced.’
‘did MCL successfully terminate the contract at common law?’