“the aggregate price for the work as summarised in the statement of work and as calculated and subject to the terms and conditions of schedule 1(“the commercial terms”).”
“the agreed total cost of£339,600 as assigned by the service provider to the work to be completed to deliver the product to the customer, in accordance with the statement of work in effect and of same date to this agreement.”
“the accrued value of the discounts derived from the application of the discount percentage to the total net of taxes, of each commercial invoice submitted by the service provider to the customer over the term of this agreement.”
“the percentage of approximately forty one percent agreed between the parties that shall be applied in the calculation of the cumulative discount; calculated as the maximum cumulative discount divided by the contract value, as both exist at the date of this agreement.”
“this agreement will continue in effect until the date of completion or if earlier, until that date that either the purchaser or the company terminate the software development agreement under the terms of that agreement, whereupon this agreement will terminate automatically, the consideration shall be calculated pursuant across 3.2 and completion will take place within 10 working days of such date pursuant to clause 4.”
“…GCV has not fulfilled its obligations to deliver the completed works by the contracted date or at all. Such software that has been released or made available [but not delivered since it is not accepted] is incomplete, defective and does not perform materially and substantially in accordance with the requirements of the contract specification or SOW. Software that has been made available is not fit for submission to the integration and interoperability testing by the Customer [part of the acceptance testing following GCV’s alpha testing and beta testing and Acceptance certification process] prescribed by SDA clauses 7 and 8 and is not accepted. Such software that has been released or made available to TL on various dates that has been subjected to Functional Testing by TL is not ready for service as defined by the contract and clearly must have failed any reasonable alpha testing process carried out by GCV if any at all.”
“GCV is therefore in material breach of contract as regards the Software Development Agreement and has repeatedly failed in the past to remedy breaches identified to it or which were obvious. By this letter, Transparently is exercising its rights to terminate the Software Development Agreement … … TL will also seek damages under SDA clause 18.8 and at common law … and other relief including delivery up of the software and all related documentation for the software [and each version released to TL] as it has been developed to date including all software change and configuration control records and test specifications and test results from tests carried out by GCV to date. … GCV is required to and should now comply promptly with its obligations under SDA clause 18.10 and 18.13. This includes all provision of all materials, access codes and any other information to enable TL to secure, control and make use of the software hosting platforms used for this project. GCV is required to and should now deliver up to TL the source code [all versions developed including any versions not yet released] and any related software development items immediately…”
“By notice dated25 October 2021 Transparently purported to terminate the SDA under its terms and on the basis of a repudiatory breach claiming that the CEPA was automatically terminated. Our client does not accept that a material breach of the SDA had arisen but waives its right to raise issue with the notice of termination and accepts that the SDA has been terminated. Alternatively, our client treats your notice of termination as itself constituting a breach of the SDA and/or a repudiatory breach, such that the SDA hereby stands terminated. Under clause 18.12 of the SDA termination of the SDA triggers a completion pursuant to the terms of the CEPA. … Clause 4.2 of the CEPA compels Transparently to accept our client’s application for the allotment and issue of shares to it and to provide a deed of adherence for our client to sign, which, for the avoidance of doubt, our client provides an engrossed copy of with this letter. Our client stands ready to comply with clause 18.13 of the SDA upon completion pursuant to the CEPA and to deliver the product, including all software, source code(s) and work in progress as well as assigning all IP rights to Transparently and granting any necessary licences to the work.”
“the agreed discount being equal to£139,570 or to a lesser amount only as agreed in and pursuant to clause 3.2”