“8. Standard Life’s Part A losses are particularised in Section G and Annex 7. Standard Life limits its Part A claim to£20,141,515 or such other sum the court shall determine. Namely: the difference between what ought to have been advised for outturn construction costs plus construction contingency (£105,872,515 ) less what was advised in fact (£85,731,000 ). This is an ‘information case’ for which the First to Third Defendants are jointly and severally liable for the consequences of their advice being wrong or their failure to advise as they ought. … 86. Standard Life claims from the First to Third Defendants, jointly and severally, its losses on the Development from August 2008 to date. These losses are£128,417,518 or such other sum as the Court shall determine. 87. See Annex 7 for further particulars of the losses. 88. Standard Life limits its Part A claims to£20,141,515 . Paragraph 8 is repeated.”
“1. But for the breach of the Part A Defendants’ obligations, Standard Life would not have proceeded with the Development. Standard Life would not have entered into the Building Contract on26 August 2008 . It would not have executed the Written Order to Commence Works on16 September 2008 . 2. Standard Life’s losses are calculated by way of a basic comparison between: (1) the position Standard Life would have been in had it not proceeded with the Development; and (2) its actual position. 3. Standard Life’s actual position is that it incurred£146,419,486 of construction costs. 4. The calculation of the position Standard Life would have been in had it decided not to proceed with the Development is set out below. (1) Standard Life would not have incurred£146,419,486 in construction costs. (2) Deducted from this figure are costs incurred by Standard Life for which the Part A Defendants were not responsible: (a) the cost of Standard Life introducing John Lewis as an anchor tenant (£8,698,287 ); (b) the cost of tenant variations (£2,423,681 ); and (3) A further deduction is made to allow for certain irrecoverable sums incurred by Standard Life prior to August 2008. Prior to August 2008, Standard Life incurred total expenditure of approximately£15,000,000 . Standard Life estimates that, of this sum, it would have been able to recover approximately£8,120,000 in proceeds from sale of land. The loss of the aborted Development would, therefore, have been approximately£6,880,000 . (4) Standard Life would not have incurred a loss elsewhere with the construction costs which would not in fact have been expended on the Development. 5. The basic comparison, therefore, is£146,419,486 less sums for which the Part A Defendants would not have been responsible in any event (£11,121,968 ) less irrecoverable costs of£6,880,000 . That totals£128,417,518 , or such other sum as the Court may find. 6. Standard Life limits its Part A claim, as pleaded in paragraph 8 of the POC. That is£20,141,515 or such other sum as the Court may find, calculated as follows: (1) the sum which ought to have been advised for outturn construction costs –£100,591,463 (as calculated in Annex 6); plus (2) the sum which ought to have been allowed for construction contingency at 5.25% –£5,281,052 ; namely£105,872,515 less (3)£85,731,000 . On29 July 2008 , Gleeds advised in Financial Report No.7£83,640,000 for outturn construction costs, not including construction contingency, and excluding fees and VAT. This advice was repeated by Gleeds on4 September 2008 in Financial Report No.8. In its Appraisal of14 August 2008 , Shearer included a construction contingency of 2.5%.£83.64m plus 2.5% construction contingency, excluding fees, was£85,731,000 .” (1) the position Standard Life would have been in had it not proceeded with the Development; and (2) its actual position. (1) Standard Life would not have incurred£146,419,486 in construction costs. (2) Deducted from this figure are costs incurred by Standard Life for which the Part A Defendants were not responsible: (a) the cost of Standard Life introducing John Lewis as an anchor tenant (£8,698,287 ); (b) the cost of tenant variations (£2,423,681 ); and (3) A further deduction is made to allow for certain irrecoverable sums incurred by Standard Life prior to August 2008. Prior to August 2008, Standard Life incurred total expenditure of approximately£15,000,000 . Standard Life estimates that, of this sum, it would have been able to recover approximately£8,120,000 in proceeds from sale of land. The loss of the aborted Development would, therefore, have been approximately£6,880,000 . (4) Standard Life would not have incurred a loss elsewhere with the construction costs which would not in fact have been expended on the Development. (1) the sum which ought to have been advised for outturn construction costs –£100,591,463 (as calculated in Annex 6); plus (2) the sum which ought to have been allowed for construction contingency at 5.25% –£5,281,052 ; namely£105,872,515 less (3)£85,731,000 . On29 July 2008 , Gleeds advised in Financial Report No.7£83,640,000 for outturn construction costs, not including construction contingency, and excluding fees and VAT. This advice was repeated by Gleeds on4 September 2008 in Financial Report No.8. In its Appraisal of14 August 2008 , Shearer included a construction contingency of 2.5%.£83.64m plus 2.5% construction contingency, excluding fees, was£85,731,000 .”
“No deduction in the basic comparison is required for the value of the completed Development. (a) Gleeds pleads no particularised case in law or in fact for the assertion. (b) There is no benefit to deduct. Even if there were, it was not caused in fact and in law by Gleeds’ breaches of duty. Even if it were, or in any event, it is collateral to the losses sustained by reason of the information, advice and performance particularly as to outturn construction cost for which Gleeds is liable being negligently wrong. In any event, the value of the Development has decreased. On Gleeds’ logic, that increases the losses. Standard Life does not seek recovery of the same, for the same reasons above.”
“If Standard Life establishes breach and causation against B4 (which is denied) the quantum of the claim is ill-conceived. Standard Life's claim has been calculated by applying a cap to its alleged total losses on the Development. However, Standard Life has not (as it should): (a) excluded losses with other causes, including the Part B claim; and (b) accounted for the benefits it has derived from the Development, including continued beneficial ownership.”
“Paragraph 12(g) asserts that Standard Life’s losses should deduct: (a) “losses with other cases”, including Part B; and (b) account for “the benefits it has derived”. (a) As to any deductions to sums it in fact recovers pursuant to its claims in Part B and Section E2 of Part C POC, see Response 3(c) to Gleeds’ RFI of23 February 2020 . (b) No deduction in the basic comparison is required for the value of the completed Development. (c) Buro 4 pleads no particularised case in law or in fact for the assertion. (d) There is no benefit to deduct. Even if there were, it was not caused in fact and in law by Buro 4’s breaches of duty. Even if it were, or in any event, it is collateral to the losses sustained by reason of the information, advice and performance particularly as to outturn construction cost, for which Buro 4 is liable, being negligently wrong. In any event, the value of the Development has decreased. On Buro 4’s logic, that increases the losses. Standard Life does not seek recovery of the same, for the same reasons above.”
“Shearer asserts in paragraph 3(b) of its Appendix 2 that Standard Life “must give credit for the value of the completed Development”
“What different action would the claimant have taken if provided with reasonably accurate information?”
“Typically in the case of a negligent valuation of an intended loan security, the basic comparison called for is between (a) the amount of money lent by the plaintiff, which he would still have had in the absence of the loan transaction, plus interest at a proper rate, and (b) the value of the rights acquired, namely the borrowers covenant and the true value of the overvalued property.”
“The court may strike out a statement of case if it appears to the court: … (a) that the statement of case discloses no reasonable grounds for bringing or defending the claim …”