“we have only allowed for the bearing piles shown on drawings 300 and 301 and not made any further assessment of the other piling requirements as we did in our previous budget estimate.”
“1.0 DESCRIPTION OF THE PROJECT The construction of a 60m single storey industrial unit comprising of a two storey office block and a 10m deep tunnel together with foundations to accommodate a Vertical Helical Alignment Machine, together with a new access road, bases for 2no.36m carousels and a carousel F together with specialist foundations housing machine rails. 1.1 Scope of Subcontract Works Subcontract Works include the design, supply, installation and supervision of the CFA Piling Works. 1.5.2 Subcontract Programme Area Commencement Duration Vham Building perimeter 11/6/12 3 wks Vham Building - Internal 20/8/12 3 wks The above dates are based on the earliest commencement date of11th June 2012 1.5.5 Approximate Start Date Van Elle works are to commence between 11th and25th June 2012 5.7 Account Settlement Final Account is to be submitted by Van Elle within 1 month of completion of the subcontract works together with all necessary supporting documentation. 7.19 Mansell advised that due to the Vham tunnel construction running through the building the intended programme was to commence on the building footprint then move onto the internal piles as far as possible. This is dependant on the working space required to construct the tunnel. The remainder of the piles within the building would have to be completed once the tunnel is constructed and the area backfilled. John Blyth advised that rather than let the piling rig leave site and then have to pay to remobilise it was Mansell preference to rework the programme to try and keep the rig working by carrying out the piling to the carousel bases and the machine rails. These areas have not yet been fully designed or costed Mansell/Shadbolts are to focus on the North Carousel and the machine rails at the North end of the building and forward details of these to Van Elle for costing. The initial thoughts were that the loadings would be generally the same as the building for which we already have rates per pile. R.Harm confirmed that the order was being placed on the building only and that if we are to work in the external areas this will be treat as variations and instructed accordingly.”
“… You were going to sort out a limited order/LOI so we could confirm rig and start ordering materials, what is current position…”
“…Please find attached bill of quantity for 36 m Carousel. I have left the mobilisation in but this can be omitted if the piling just carries on from one section to the next with one rig. I’ve included for de-bonding foam up to 1 m…”
“No binding contract will result from this email until an officer, on behalf of the company, signs a written document.”
“To install 450 mm dia and 600 mm dia CFA Board piles to a maximum depth of 22.0 mm. The piling is to commence on the North Carousel on 450 mm dia augers, pile quantity 99 no. The follow-on sequence is to be determined by pile availability on the remaining building. Equipment required (Phase 1) Soilmec SF50 piling rig…”
“Newcaflex Development 1. We have been instructed to start work on Newcaflex Development.. by our employer Duco Ltd under a letter dated1st May 2012 . 2. It is anticipated that the Main Contract willbe placed using JCT Design and Build Contract 2011, as amended by the Schedule of Modifications agreed between ourselves and our Client 3. It is our intention to place a formal sub-contract with yon to carry out the design, supply, installation and supervision of the CFA Piling Works. 4. The results of our negotiations to date are comprised in the following documents and understandings. In this letter we will refer to them as the “ Proposed Sub-Contract”… 4.2. Sub-Contract Management Plan [ie the 15 May Meeting Note] 4.3. Mansell Sub-Contract Conditions, which will be the JCT Design and Build Sub-Contract 2011, incorporating Mansell Amendments… 4.5 Van Elle Limited schedule of numbered documents [which is appended to the LOI] 4,6. Van Elle Limited Contract Analysis [This is the 20 March Quotation] 4.7 Programme of works as detailed with Van Elle Limited – summary of works 3000357 CFA Piling. 4.8 The Mansell Safety, Quality & Environmental Policy Statements… 5. ln the event of any discrepancy arising, the documents: listed above shall be reviewed and applied in that order of priority, 6. You have indicated that, in order to meet the above timetable, you must commence design and mobilisation now and that you are not happy to do this without formal commitment from us. Accordingly, we are issuing this enabling works contract to you. 7. This letter is not intended to bring the Proposed Sub-Contract into effect but does create a legal contract between us to the extent set out below. 8. We confirm that we will pay you in accordance with the Proposed Sub-Contract for all work properly (and not prematurely) carried out by you in relation to the above items of work which you agree to commence and carry out in accordance with the Proposed Sub-Contract including the placing of orders for materials etc. Where the Proposed Sub-Contract does not contain relevant prices we will pay you a fair and reasonable sum in respect of the items in question. 13. Under no circumstances will be liable under this enabling works contract to pay you more than£363,600 exclusive of VAT in total and this sum is subject to set-off in respect of your breach of contract causing us loss under the Main Contract. 16. If and when the Proposed Sub-Contract is executed, its terms and conditions shall supersede this enabling works contract and govern any of your completed work respectively…”
“The number of piles are going to change as the design develops which is why he has based it on this and as the piles are installed we will invoice against the rates shown. The Carousel piles are at the same rate as the 450 mm diameter piles shown on the bill. There are 99 No so the 204 No shown on the bill more than covers… 6 and 7 are outlining reasons for the LOI… .13 means we will have to monitor how works are progressing and if.-Contract is not issued get a further letter upping the£363k if the value of the work starts to approach this figure… Once the design is complete I can price again to get the figure clearer.”
“We acknowledge receipt of your letter of intent dated1 June 2012 accepting our quotation 120216 Rev A dated20 March 2012 and confirm the provisional start date of the week commencing11th June 2012 . Your letter dated1 June 2012 will serve as an interim agreement and neither party will be bound by the including sub-contract until such time as it is executed by each party.… Please ensure that our record sheets are agreed and signed on site as this document will form the basis of the remeasure for the final account with the terms of our contract… Please note, your order is accepted on behalf of Van Elle Ltd in accordance with the Terms and Conditions of our quotation dated (see overleaf)…”
“Andy has just sent me a copy of the Pile layout and loads for the 36 meter Carousel (North Carousel) is this the one we are starting on. The design and price we have given is based on 99 No piles with loads of 750kN compression and 50kN lateral loads.… The drawing shows 95 No piles of which only 19 No have loads of 750kN or less… The rig is programmed to arrive tomorrow and there will be only a small number of piles that can be installed at up to 750kN compression and 50kN lateral…”
“Following receipt of revised pile loads yesterday for the Carousel please find attached revised calculations and pile schedule… We are carrying out settlement calculations but would anticipate a settlement of up to 5 mm at working load. Please confirm that this is acceptable prior to the works commencing today.”
“Piling works carried out at the above site in accordance with our quotation 120216 VHAM Visit 2 dated2 October 2012 and your email dated3 October 2012 …”
“The main reason for Van Elle not being in a position previously to definitively advise on availability is that current projects which were uncertain in duration have been expanded in scope and are therefore demanding resources until the end of December… In addition, due to both the scope contained in the original sub contract, which included a contract sum of£393,600 [this should be£363,600 ] with Van Elle having exceeded this already (£396k ) and the alteration to access, rig requirements and logistics, it is also required to offer further costings for these works… Please can you advise on Mansell reaction to the above anticipated availability and I will continue to finalise costing and designs.”
“the provision of all necessary services in order to undertake and complete the design, supply and installation of the CFA Piling Works inclusive of all necessary supervision, all in accordance with the following:” (3) The Price is stated to be£363,600 ; (4) The “Works” (i.e. the Main Contract works) are described as: “The design and construction of a metal clad steel framed new build VHAM building, complete with overhead crane, mechanical and electrical services, together with associated external works.” (5) The “Sub-Contract Works” are described as: “The provision of all necessary services and supervision to undertake the design, supply and installation of the CFA Piling Works.” (6) The “Sub-Contract Sum” is then stated to be£363,600 exclusive of VAT; (7) Underneath the section just referred to and on the same page, appear 3 manuscript notes as follows: “* ORIGINAL SUB- CONTRACT SUM TO BE CONSIDERED IN ADDITION TO ALL FURTHER WORKS UNDERTAKEN * DURATION OF WORKS TO BE ASSESSED IN RELATION TO ALL FURTHER WORKS UNDERTAKEN * AS PER ORIGINAL ORDER ACCEPTANCE DATED 11.06.12 NO ALLOWANCE WAS MADE FOR LAD’S” (8) Condition 4 stated that the Sub-Contract Works would be carried out in accordance with the provisions of this Deed, the Sub-Contract Conditions which were expressly incorporated and the numbered documents listed in Appendix 1 which were also expressly incorporated; (9) Under Condition 8, the documents referred to in the Sub-Contract included: “1. The provision of this Deed 2. Mansell’s Safety, quality and environmental Policy Statement… 4. Sub- contract the Pre-contract Meeting Minutes/subcontract Management Plan [i.e. the 15 May meeting Note]…” (10) At Appendix 1, the sub-contract works were described as: “CFA Piling (“the Sub-Contract Works”)… As part of metal clad in steel framed new build Vham building complete with overhead crane, mechanical and electrical services, together with associated external works (“the Main Contract Works”)…” (11) Article 3A described the “Sub-Contract Sum and Final Sub-Contract Sum” as£363,600 exclusive of VAT; (12) Part 5.1 under the heading “Program”, said that the period required for the preparation of all necessary drawings etc was detailed within document 4 CM-AG-02-10 Management Plan dated15 May 2012 . Part 5.6 stated that the period required for the carrying out of the Sub-Contract Works was 6 weeks. There was then a further manuscript addition from VE which stated: “FOR ORIGINAL ORDER VALUE AND SCOPE”; (13) By part 17, the Numbered Documents were identified. The list is the same as that in the LOI save that a new final item 43 was added described as the “Van Elle Enabling Order 1. 6.12” which is the LOI; that list is repeated at the end of the Sub-Contract but here, 75. against item 6 “contract sum build up ref 30/00357 van Elle”
“+ FOLLOW-ON BILLS OF QUANTITIES” finally, against Item 43, VE added in manuscript: “WARRANTY TO BE REVIEWED/NEGOTIATED SEPARATELY”
“A shared common subjective understanding of parties as to the meaning of a term, the issue of construction, is potentially admissible to the issue the court has to consider of what the proper construction of the term is. But…if X on its face is X, then no amount of what party A says to party B… or what party A thought internally or what party B thought internally can turn X into Y.”
“As such from my point of view I was comfortable that the North Carousel Piling Works were already covered by the VE quotation dated28 May 2012 and did not form part of the works covered under the LOI.”