“All reasonably foreseeable losses, costs, damages, expenses and liabilities reasonably and properly incurred by the Buyer (including all rents that would otherwise be receivable from NCP, but excluding VAT if and to the extent that such VAT can be recovered by the Seller or the Buyer) which are either agreed or determined to be as a consequence of any breach by the Seller of its obligations in and other provisions of the NCP Compensation Deed and/or the NCP Option Agreement and/or as a consequence of the failure by NCP to complete a lease in the Agreed Form pursuant to the NCP Option Agreement.”
“BCC’s failures to resolve the defects in the Car Park have meant that NCP has not entered into the New Lease, and Grand Central has therefore not received the rents from NCP to which it would otherwise have been entitled. To date, BCC has paid certain sums in respect of these lost rents, but this has undercompensated Grand Central and further sums remain unpaid.”
“These NCP Losses have arisen as a consequence of NCP not completing the New Lease pursuant to the NCP Option Agreement and/or of BCC’s breaches of the NCP Option Agreement set out in Section H below.”
“…on a proper construction of Clause 33.1.2 and the definition of ‘NCP Losses’ in the SPA, BCC is only liable to indemnify Grand Central under Clause 33.1.2 in respect of lost rent if it is agreed or determined that the loss of rent was reasonably foreseeable and has been reasonably and properly incurred [as] a consequence of (1) any breach by BCC of the NCP Compensation Deed and/or the NCP Option Agreement and/or (2) NCP’s refusal in accordance with the terms of the NCP Option Agreement (i.e. lawfully) to enter into the New Lease.”
“Except that NCP was not entitled to refuse to enter into the New Lease, paragraph 9 is admitted. NCP purported to terminate the NCP Option Agreement by notice of30 April 2020 on the basis that the New Lease was not completed by10 April 2017 , which it alleged entitled it to terminate under Clause 24.2 of the NCP Option Agreement. By a further notice of1 May 2020 , NCP purported to terminate on two further grounds, namely that (1) there were allegedly fewer than 316 spaces suitable for commercial use at the Car Park, which entitled it to terminate under Clause 21.4 of the NCP Option Agreement and (2) there were allegedly unremedied defects in the Car Park. However: 9.1 NCP was not entitled to terminate under Clause 24.2 because the failure to enter into the New Lease was due to its own ‘act, omission or delay’ in that it had refused to enter into the New Lease. 9.2 NCP was not entitled to terminate under Clause 21.4 because the Car Park has more than 390 spaces (as Grand Central pleads at paragraph 100). 9.3 The existence of alleged defects in the Car Park was not a ground entitling NCP to refuse to enter into the New Lease or to terminate the NCP Option Agreement. 10. In the premises, NCP’s failure to enter into the New Lease was a breach of Clause 4.5 of the NCP Option Agreement, and its purported termination by letters of30 April 2020 and/or1 May 2020 were repudiatory breaches that were accepted by BCC on29 May 2020 . Further or alternatively, NCP committed a repudiatory breach of the NCP Option Agreement when it entered into the Management Agreement, which was accepted by BCC on29 May 2020 .”
“On a proper construction of Clause 33.1.2 and the definition of ‘NCP Losses’ in the SPA, BCC is only liable to indemnify Grand Central under Clause 33.1.2 in respect of lost rent if it is agreed or determined that the loss of rent was reasonably foreseeable and has been reasonably and properly incurred a consequence of (1) any breach by BCC of the NCP Compensation Deed and/or the NCP Option Agreement and/or (2) a lawful refusal by NCP to enter into the New Lease.”
“Further, in breach of Clause 33.2, Grand Central encouraged the making of an NCP Claim by NCP, which means that BCC is not liable to Grand Central under the indemnity in Clause 33.1.”
“BCC’s construction seeking to limit the indemnity at Clause 33.1.2 of the SPA in respect of losses caused by NCP’s failure to enter into the New Lease to circumstances in which this failure was lawful is wrong. (2) Neither Clause 33.1.2 nor the definition of ‘NCP Losses’ contain any wording that suggests that BCC’s liability to indemnify Grand Central is so limited; the material part of the definition merely provides that losses must be ‘a consequence of the failure by NCP to complete a lease in the Agreed Form...’ Any failure, whether lawful or unlawful, applies. (3) Accordingly, BCC is liable to indemnify Grand Central in respect of reasonably foreseeable losses that have been reasonably and properly incurred as a consequence of (1) any breach by BCC of the NCP Compensation Deed and/or the NCP Option Agreement or (2) any failure by NCP to enter into the New Lease.”
“Clause 33.8, together with Clauses 33.4 and 33.9 [of the SPA], are relevant to the proper construction of ‘NCP Losses’.”
“On a proper construction of the definition of ‘NCP Losses’ as referred to in clause 33.1.2 of the SPA, does the last part of the definition include only a lawful failure by NCP to complete a lease in the agreed form pursuant to the NCP Option Agreement as alleged by BCC at paragraphs 16 and 59.1 of its Defence?”
“In my judgment the right approach to preliminary issues should be as follows. (a) Only issues which are decisive or potentially decisive should be identified. (b) The questions should usually be questions of law. (c) They should be decided on the basis of a schedule of agreed or assumed facts. (d) They should be triable without significant delay, making full allowance for the implications of a possible appeal. (e) Any order should be made by the court following a case management conference.”
“... there is always a risk that an order directing a preliminary issue will lead to unnecessary expense and delay if a decision on that issue will not be decisive of the litigation either way (because, for example, there are other bases of claim independent of it; Woodland Trust v Essex CC[2013] UKSC 66 ; [2014] A.C. 537 at [2]).”
“I suggest that determination of these matters will therefore not be overly complex – it will be a matter of (i) construing the NCP Option Agreement to determine precisely in what circumstances NCP was entitled to refuse to enter into the New Lease/terminate the NCP Option Agreement, (ii) establishing whether, on the facts, any of those grounds arose and (iii) determining whether NCP’s actions were therefore lawful or not.”