“We, The Korea Development Bank, with all the relevant details, have knowledge of subcontracts number [then it is given]..dated 20 November between TRS (the contractor) and Sungchang (the sub-contractor) for the execution of electromechanical works. We hereby guarantee, irrevocably and unconditionally undertake to pay to the beneficiary any or all sums up to the aggregate maximum amount of SAR 40.505.563[it is about£8 million , I think, which is referred to as the guarantee amount]…equivalent to the amount of the advance payment made by the contractor to the sub-contractor as security for the faithful observance of the obligations arising out of the mentioned subcontract. The guaranteed amount will be paid to the beneficiary within five business days after receipt of your first written simple demand signed by the beneficiary duly authorised officer indicating that the sub-contractor has failed to fulfil any of the conditions of the subcontract and the beneficiary has wired the sub-contractor, as advance payment, an amount equal or larger than the demanded amount date the date of remittance without restriction and notwithstanding any objection of the sub-contractor. It is a condition for any claim and payment under this guarantee to be made that the funds paid as advance payments subject to the terms of the subcontract must have been received by the sub-contractor on its account number 042-117994-03 held with HSBC.”
“However, according to the documents furnished by you, a certain portion of the advance payment was received by the sub-contractor on its bank account held with the Saudi British Bank. We are therefore of the conclusion that the condition under the guarantee is not satisfied and therefore the Bank is not obliged to honour the demand.”
“For the most part, the correct approach to construction of the Bonds, as in the case of any contract, was not in dispute. The principles have been discussed in many cases, notably of course, as Lord Neuberger MR… those cases show that the ultimate aim of interpreting a provision in a contract, especially a commercial contract, is to determine what the parties meant by the language used, which involves ascertaining what a reasonable person would have understood the parties to have meant…the relevant reasonable person is one who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.”
“The language used by the parties will often have more than one potential meaning. I would accept the submission made on behalf of the appellants that the exercise of construction is essentially one unitary exercise in which the court must consider the language used and ascertain what a reasonable person, that is a person who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract, would have understood the parties to have meant. In doing so, the court must have regard to all the relevant surrounding circumstances. If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other.”
“Where the parties have used unambiguous language, the court must apply it…The underlying result…”
“The court may correct an obvious misnomer as a matter of interpretation”
“It seems to me that the doctrine of misnomer is of uncertain width. It is clearly a doctrine of construction, but it is not plain to what extent it permits the reference to extrinsic evidence. Davies v Elsby Brothers Ltd would suggest that where there are two possible entities, the rule is a strict one: unless one can say from the four corners of the document that the parties must have intended to refer to one rather than the other entity, then the doctrine does not apply. If, however, there is only one possible entity, then it is possible to use extrinsic evidence to identify a misdescribed party. It is arguable that Nittan v Solent Steel falls into this latter category. Moreover, the cases, as does common sense, suggest that a case of mere misnomer is not easily (query if ever?) concluded to be such without the mistake being explicable.” 43 Lewison states that even if that view is correct, the Court would be able to take into account the same evidence of the background as would be admissible for the purpose of interpreting the contract, including any relevant course of dealing between the parties: “In the end the question is one of interpretation of the contract in question, and therefore the material available and the techniques used in contractual interpretation ought to apply even where the allegation is one of misnomer.”
“A demand under the guarantee shall be supported by such other documents as the guarantee specifies and, in any event, by a statement by the beneficiary indicating in what respect that applicant is in breach of its obligations under the underlying relationship. This statement may be in the demand or in a separate signed document accompanying the demand.”
“Although Article 14H is mandatory in form, it nevertheless creates a problem of legal analysis, as does it predecessor. If the buyer instructs his bank and the bank agrees to issue a credit containing a non-documentary condition, why should not the parties’ apparent specific intentions override the UCP. This would be the usual consequence of an inconsistency between a specifically negotiated term in the contract and standard terms and conditions incorporated by reference.”
“It should nonetheless be noted that other provisions of the UCP,” and he gives two examples, “can similarly override other specifically negotiated terms of the credit and to this extent the terms of the UCP600 are unusual standard terms and conditions incorporated by reference”
“A guarantor is liable to the beneficiary only in accordance with first the terms and conditions of the guarantee and, second, with these rules, so far as consistent with those terms and conditions, up to the guarantee amount.”
“When the guarantor rejects a demand it shall give a single notice to that effect to the presenter of the demand. The notice shall state that the guarantor was rejecting the demand and each discrepancy for which the guarantor rejects the demand.”
“The notice required shall be sent without delay, but not later than the close of the fifth business day following the day of presentation.” “The notice required shall be sent without delay, but not later than the close of the fifth business day following the day of presentation.”