“32. [They] proceeded to destroy the second Pasteurising Tank and procure unnecessarily expensive replacement tanks, instead of implementing the process of hydraulic separation set out above... 33.3 It was not necessary to replace the Tank Heaters in the Pasteurisation Tanks for the reasons set out above… The missing hydraulic separation could have been implemented easily and at minimal cost to limit pressure to the second Pasteurisation Tank, thus avoiding any delay in operation.”
“They could have gone forward and purchased new equipment, but with the safeguard of the hydraulic separation and the heat exchangers” and this has been addressed in the claimant’s Reply.”
“The missing hydraulic separation could have been implemented easily and at minimal cost to limit pressure to the second Pasteurisation Tank, thus avoiding any delay in operation.”