"Further to the letter of 17 May when we asked Oak to submit its final subcontract application within the next 4 weeks, we have had had no response....in accordance with clause 4.6.3, we enclose our calculation of Oak Dry Ltd.’s final subcontract sum"
"6. Regarding the possible Conditions of sub-Contract, the LOI states the intention is that the JCT 2011 Design & Build Sub-Contract will apply. To an extent ODL and OD proceeded on the basis that the JCT 2011 Design & Build Sub-Contract Conditions applied during the delivery of the Sub-Contract Works occasionally referring to the conditions albeit absent of reliance on any completed Sub-Contract Particulars. 7. The sub-contract sum was subsequently adjusted to£11,244,901.90 under Site Instruction No, 10 dated 22July 2016. 8, However, the JCT 2011 Design & Build Sub-Contract was never executed and the woks proceeded with no regulated terms and conditions. Adjudication Provisions 9' There were no Contract Particulars executed and no regulated terms and conditions and therefore ODL's option for adjudication falls to be regulated under part 1 of theSchedule to The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (England) Regulations 2011. The Dispute 10' Although a formal contract was never executed the Parties acted as though clause 4.9, 4.10, 4.13, 4.19 and 4.20 of the intended sub-contract (JCT 2011 Design and Build Sub-Contract, applied for the purposes of Interim payments."
"244. The Letter of Intent states the intention that the 2011 JCT Design and Build Subcontract will apply. 245. It is clear the parties proceeded on the basis that the 2011 JCT Design and Build Subcontract Condition applied, referring to the Conditions albeit absent any completed subcontract particulars. 246. I further agree with OD Developments that whilst parties did not complete the Subcontract Particulars, there was nothing further to be agreed and hence a contact was formed. 247. I therefore agree with the Parties that the Conditions of the JCT Design and Build Subcontract are incorporated and apply."
“There were no Contract Particulars executed and no regulated terms and conditions and therefore ODL's option for adjudication falls to be regulated under Part 1 of the Schedule to The scheme for construction contracts (England and Wales) Regulations 1998.”
‘This Letter of Intent is based on your knowledge and acceptance of the JCT contracts stated’