“We hereby give you notice of the sum that we consider to be, or to have been, due at the payment due date in respect of the above payment being £X and the basis on which that sum is calculated is attached. The payment will be made on account and subject to final checks.”
“I also question the working hours we dictated (more or less 2 shifts, 12 hours each). Their people work 14 days in a row, 4 days free. Can anybody really work productive such long hours for consecutive 14 days. I dare to doubt… .”
“have you checked against gate records?”
“the issue is, M&W have instructed a Sub-contractor without a heavy financial backing behind them to man up to levels which they cannot maintain without weekly payments.”
“So we decided on Tuesday this week that we pay now every invoice without assessment as is on‐account and do our checks afterwards. I am not at all happy with that solution as we already can foresee following problem: workers at Premier are paid weekly according their timesheets. There are considerable differences between timesheets and their working hours on site. Tim presented them to Premier’s managing director who promised better supervision. We also provide them now with our gate records on a weekly basis. It’s hard to cut their invoices afterwards as they already have paid now their workers before we come back with our assessment. If they do not change (increase) their productive hours on site we will bring Premier in a very uncomfortable situation or we just accept their invoices as they are. … I just can give advice to have at least a close look on their presence at site as we would been forced to cut their invoices if differences between invoiced hours and hours according gate records remain that size we have seen on previous application. And with the on account payment pattern now, we would create a huge problem for them retrospectively or we just accept.”
“D. Because Premier has work both on the site and off site on M&W’s storage facility, Premier will have installed, at their cost, and operating by Monday April 16th a biometrics’ reader outside the M&W gate to scan all employees in in the morning and evening. In addition they will maintain a manual signed timesheet to back up all records. All data collected by the biometrics report shall be provided to M&W for each invoice period. E. Any additional overtime requests above the standard hours above will have to be authorized by the M&W Piping Construction Manager or his delegate. F. Premier will manage all breaks and insure the craft is back to work immediately following any break period. G. Premier Management and Supervisors will be responsible for maintaining quality workmanship, insuring a high productivity for the craft they are supervising and shall maintain discipline among its entire workforce. H. Premier must maintain qualified supervisors and qualified craft. I. Premier shall submit invoices on or before the close of business each Monday following the week worked.”
“Approved But please have now a look on all previous applications and conduct an accurate assessement [sic] on them. We do have gates to use the data for crosschecking the timesheets of our suppliers.”
“… suggest we do our final analysis today utilising our turnstile records prior to sending the letter to give Roy an indication as to where we are on deductions beyond the£96k currently held.”
“Based on discussions held over a number of weeks between both parties please find attached agreed working patterns and basis for invoicing.”
“[w]hilst we agree in principle with the pay basis, we are unable to agree that hours will be checked against your onsite turnstiles.”
“It was previously agreed with Stevan Demase that if we installed the biometrics reader and supplied manual timesheets that these would be the only measure of hours worked. Taking into account the above, we therefore state that we do not trust the data from the turnstiles and will not agree to using that as a measure for hours worked.. We would like to have the pay basis in place as soon as possible, therefore please could we ask that you review your document so that moving forward we can have something we all agree on.”
“Following a consultation with Roy Knight we reiterate that our contract with M&W can only be paid on Biometric clock data and signed timesheets to verify and take account of extra hours agreed. … Any use of turnstile timings is completely unacceptable for the reasons given. Please re-issue the agreement and include a statement that promises Premier Engineering will be paid in full based on the attached letter, and that gate timings will never be taken into consideration again. We have wasted far too much time on this when we should be concentrating on completing the contract.”
“This meeting took place on site, outside of Tim Lakeman's office, it was kept quite informal. The objective of the meeting was to discuss the use of the turnstile gate times, as opposed to timesheets and the biometric clock in system. It was agreed that the turnstiles were unreliable at times and didn't allow for works being done on the other side. It was agreed that we would only count times on Premier's biometric clocking system, and this would be backed up with signed timesheets. No further deductions would be made to invoices and payments would be made in full.”
“Dear Premier Employees, As managing director of Premier Engineering, I offer a total of 3 wks notice as away [sic] of compensate of termination of employment, as of Monday9th July 2018 . Thank you for all your efforts on this contract and I hope you the best in the future. Please stay in contact and if you require a reference in the future, please contact me directly. [Signed] H Warren MD” [Signed] H Warren MD”
“Discussions took place regarding lack of notice given by the Defendant to the Claimant, and as a consequence the short notice given to the men by the Claimant. [The union representative] claimed an extra two weeks’ pay in lieu of notice for the men to placate the protesting labour.Mr Roy Meakin verbally offered to pay£85,000.00 towards the cost of this additional liability.That offer was noted but not accepted by Mr Harry Warren as he believed that the Defendant should be liable for all 3 weeks’ pay. Mr Harry Warren was requested to hand-write a signed a letter explaining the proposal, which was taken to the men on the gate by the Union official. … The proposed additional payment was accepted by the men and all protests ceased immediately and the site returned to work.”
“Equipment retained by Premier”