“Each case depends on the terms of the contract under which the determination is made, both as to what it is the expert has to decide, and as to how far his decision is binding on the parties. In each case it is necessary to examine the determination, in order to see whether it lies within the scope of the expert’s authority. If it does not, then it has no effect as between the parties.”
“27. However, although the parties must adhere to the agreement which they have made, I do not consider that the approach to an expert determination clause should be the same as that which is now taken to an arbitration clause. The rationale for the approach in the Fiona Trust case is that parties should normally be taken, as sensible businessmen, to have chosen one forum for the resolution of their disputes. As arbitration will usually be an alternative to court for the resolution of all disputes between the parties, it would not accord with the presumed intention of sensible businessmen to draw fine distinctions between similar phrases to allow a part of the dispute to be outside the arbitration and allocated to the court. 28. In contradistinction expert determination clauses generally presuppose that the parties intended certain types of dispute to be resolved by expert determination and other types by the court (or if there is an arbitration clause by arbitrators). The rationale of the Fiona Trust case does not therefore apply, as the parties have agreed to two types of dispute resolution for disputes which might arise under the agreement… The simple question is whether the dispute which has arisen between the parties is within the jurisdiction of the expert conferred by the expert determination clause or is not within it and is therefore within the jurisdiction of the English court. It is a question of construction with no presumption either way.”
“36.1 Where this Contract provides for a dispute to be referred to an expert, any Party may serve notice on the other Party of its intention to refer the dispute to the Chartered Institute of Arbitrators (or such other expert as may be agreed between the Parties) (the "Expert") acting as an independent expert. 36.2 The Expert shall be independent of the Parties and will not act as an arbitrator. The Expert shall decide the dispute referred to him taking due and proper account of any submissions of the Parties (if any, to be provided to the Expert within five (5) Working Days of the appointment of the Expert) and will issue his decision within seven (7) Working Days following the date of his appointment. 36.3 Each Party shall co-operate with the other Party and the Expert in the investigation of the dispute and shall provide at its own expense any information, documents, records or access as the Expert reasonably requires to make his determination. 36.4 The Expert's determination shall be in writing and shall be binding on the Parties, except in the case of fraud or manifest error, unless and until agreed by the Parties or by the final determination of the dispute by a court or judge thereof. Each Party shall bear its own costs in relation to the reference to the Expert, provided that the Expert shall be entitled to determine how his fees shall be shared between the Parties.”
“The Technical Adviser shall, within ten (10) Working Days from Commissioning, by providing a minimum of two (2) days prior written notice to the Contractor, inspect the Works for the purpose of preparing the list to be agreed as the Punch List. Subject to notice being received by the Technical Adviser pursuant to clause 7.1, within five (5) Working Days from such inspection, the Technical Adviser shall issue to the Employer and the Contractor such list. In the event that the Technical Adviser does not inspect the Works or issue the list to the Employer and the Contractor within the required periods, the Contractor shall be entitled to issue such list to the Employer and the Technical Adviser. If within ten (10) Working Days from the issue of the list by the Technical Adviser or the Contractor (as applicable), the Parties are unable to agree the Punch List or any part of the Punch List, the matter may be referred to the Expert pursuant to clause 36.”
“In the event the Contractor fails to pass the Provisional Acceptance Tests (including any repeats thereof under clause 8.4) within one hundred and eighty (180) days of Works Completion, then the Employer shall be entitled, at its sole option and discretion, to: (a) require the Contractor to carry out further make good works and to carry out a further repeat of the Provisional Acceptance Tests in which case this clause 8.5 shall continue to apply until such time as the Provisional Acceptance Tests have been passed to the satisfaction of the Employer; or (b) seek to agree with the Contractor a reasonable reduction in the Contract Price (including, where a portion of the Contract Price has already been paid by the Employer, a pro rata reimbursement of a part of the Contract Price, which shall be payable by the Contractor as a debt). If the Employer and the Contractor are unable to agree a reduction or reimbursement of the Contract Price then the Employer shall at its option be entitled to refer the matter to determination by an Expert pursuant to clause 36. … .” (a) require the Contractor to carry out further make good works and to carry out a further repeat of the Provisional Acceptance Tests in which case this clause 8.5 shall continue to apply until such time as the Provisional Acceptance Tests have been passed to the satisfaction of the Employer; or (b) seek to agree with the Contractor a reasonable reduction in the Contract Price (including, where a portion of the Contract Price has already been paid by the Employer, a pro rata reimbursement of a part of the Contract Price, which shall be payable by the Contractor as a debt). If the Employer and the Contractor are unable to agree a reduction or reimbursement of the Contract Price then the Employer shall at its option be entitled to refer the matter to determination by an Expert pursuant to clause 36. … .”
“23.5 In the event that the Contract is terminated by the Contractor in accordance with clause 23.2, the Contractor's sole remedy for such termination shall be to recover: (a) any amounts properly due under this Contract to the Contractor up until the date of termination; and (b) the reasonable losses incurred by the Contractor as a result of the early termination of any agreement which it has been entered into in connection with this Contract, provided that the Contractor can demonstrate that such reasonable losses are payments to be made by the Contractor to any counterparty to such agreement under the express provisions of such agreement; and (c) if such termination arises prior to due date for payment of the milestone pursuant to 11.4, an amount equal to: (i) the then relevant Contract Price; less (without double counting); (ii) any amounts properly due under this Contract to the Contractor up until the date of termination and which have been paid to the Contractor in accordance with this Contract and the estimated costs to complete the Works (as agreed between the Parties or (a) any amounts properly due under this Contract to the Contractor up until the date of termination; and (b) the reasonable losses incurred by the Contractor as a result of the early termination of any agreement which it has been entered into in connection with this Contract, provided that the Contractor can demonstrate that such reasonable losses are payments to be made by the Contractor to any counterparty to such agreement under the express provisions of such agreement; and (c) if such termination arises prior to due date for payment of the milestone pursuant to 11.4, an amount equal to: (i) the then relevant Contract Price; less (without double counting); (ii) any amounts properly due under this Contract to the Contractor up until the date of termination and which have been paid to the Contractor in accordance with this Contract and the estimated costs to complete the Works (as agreed between the Parties or 37. in any case, not to exceed the then relevant Contract Price.”
“The dispute process If you fail to pay the sums claimed above, our client intends to proceed with a formal claim against you. The contract sets out the processes for resolving disputes at Clauses 36 and 37. Clause 36 sets out a process for expert determination. Clause 13.8 states that, if the parties cannot agree a reimbursement to cover the costs of the defects, the dispute shall be resolved by expert determination under clause 36. Alternatively, Clause 37 states that either party may refer a dispute to adjudication for determination. Our client has the option of either having this dispute dealt with by expert determination or by adjudication. Our client's preferred option would be adjudication. Please would you confirm that you agree that this dispute should be resolved by adjudication and that you accept the adjudication provisions in Clause 37 apply to this dispute. Summary There are defects with the work that you undertook on this site. Our client has already invited you to rectify these defects but you have failed to do so. Our client therefore now seeks from you reimbursement of the costs that they will incur to rectify the defects as a debt and/or damages. If you fail to pay the sums set out above within the next 7 days then our client will consider a dispute to have crystallised and will refer the dispute to an expert or adjudicator to be resolved. In relation to the dispute process, we invite you to agree that the adjudication provisions set out in Clause 37 apply to this dispute. Alternatively, our client reserves the right to have the dispute dealt with by expert determination instead.”
“In light of the above, we consider that a dispute has crystallised and we confirm that we are now instructed to proceed immediately with a referral of this dispute to expert determination. Should you wish to avoid a referral being made for expert determination you should take the following steps immediately: a) Pay the sum of£1,713,674.60 ; or b) Confirm that you agree for this dispute to be resolved by adjudication. ”
“The dispute 11. This dispute relates to DPL’s failure to agree the sum payable to [EEL] to rectify defects with the work undertaken by DPL. Full details of the dispute are set out in the Submission document. 12. DPL have refused to rectify defects and have refused to reimburse EE for the costs that EE will now incur to rectify the defects. The Contract 13. The relevant provisions related to defects are set out in Clause 13 of the Contract, in particular the following: [the submission then set out clauses 13.7 and 13.8 of the Contract] … 15. The defects that are complained of within this dispute are defects to the Photovoltaic System. 16. DPL has refused to rectify the defects complained of. 17. [EEL] will therefore have to arrange for the necessary remedial work to be carried out by others. [EEL] have notified DPL of the cost that will be incurred to rectify the defects and they have requested that DPL agree this cost and reimburse this sum to them. 18. Clause 13.7(a) states that [EEL] are entitled to claim the cost of this remedial work from DPL as a debt. 19. Clause 13.7(b) states that the amount to be reimbursed to [EEL] for having to engage other[s] The “s” is missing in the original to carry out the work should be agreed with DPL. 20. Clause 13.8 states that where the amount of reimbursement pursuant to Clause 13.7(b) cannot be agreed then it shall be resolved in accordance with Clause 36 (ie. Expert determination). … 25. The dispute that [EEL] have referred to expert determination is for an assessment of what sum should be reimbursed to them as a result of DPL’s failure to rectify the defects in the Photovoltaic System. Insofar as it is necessary to determine what defects exist in order to value the cost of rectifying such defects then this forms part and parcel of the dispute that has been referred. 26.
“[EEL] seeks the following redress against DPL: 1. That DPL should pay to [EEL] the sum of£1,708,474.60 or such other sum that I consider appropriate; …”
“7. As noted by EE, and upon my reading of the dispute that has been referred, this dispute is in relation as to whether EE should be reimbursed for the cost of remedying defects that they say DPL has failed to rectify and, if so, how much should be paid. I also note that Clause 13.8 of the Contract states “the Employer and the Contractor are unable to agree a reduction or reimbursement of the Contract Price as required by clause 13.7(b) then this shall be resolved by the Parties in accordance with clause 36.”
“I NOW DECIDE AND DECLARE THAT: - [DPL] shall forthwith pay to [EEL] the sum of£1,708,474.00 ” [DPL] shall forthwith pay to [EEL] the sum of£1,708,474.00 ”