". . . If you had met with me as agreed I would have been happy to inform you of this and the compromise we were proposing as the only client to continue to owe the company money. I have been through the file in some detail. One of Mark's [Mr Cotton's] strengths was his attention to detail, and so the file is comprehensive."
"The respondent does not seek to escape its contractual agreement to adjudicate or rewrite the contract, but seeks the postponement of any adjudication proceedings until such time as the Covid-19 lockdown can be sensibly lifted."
"I could not advise my client to even consider agreeing to an extension under 3 months at least but even that may not be enough as some reports are saying that it could take several months if not longer to get this situation under control."
"Interlocutory relief or declaratory relief for the same effect will rarely be granted to interfere with an ongoing adjudication but the court has jurisdiction to grant such relief and will do so in unusual circumstances."