“Bester’s conduct has been unreasonable at almost every turn. Having started and lost the adjudication before Mr Tolson, it did not pay, did not respond to requests for payment and, when PBS issued proceedings, indicated an intention to defend proceedings although there was no defence to the claim. It raised spurious issues in its Defence which, apparently, it never had any real intention of pursuing. It unreasonably did not consent to judgment and only acknowledged that PBS was entitled to judgment when submitting its skeleton argument for the hearing on13 April 2018 . Bester says that evidence submitted on8 March 2018 ‘was clear in seeking a stay.’ But given Bester’s previous record of non-cooperation, non-payment and non- response, the material fact is that it never consented to judgment, formally or otherwise. In the light of my ruling rejecting the stay of execution, given on13 April 2018 , it is not unfair to characterise Bester’s conduct as adopting every and any device to stave off the evil moment of payment.”
“The Employer [Bester] shall … take over and pay the corresponding part of the Contract Price for the Works, including the Temporary Works, which have been performed up to the termination of the Contract.”
“The respondent submits that the claimant is required to mitigate against its loss by selling on or using the items of plant on some other facility. I disagree; it is the respondent which has caused the claimant to manufacture the plant items which the evidence shows that it has done and which, as Mr Košťál has averred, are now stored at the claimant’s factories in the Czech Republic. When the relevant proportion of the Contract Price has been fully paid over to the claimant the plant belongs to the respondent which is responsible for collecting and disposing of the plant as it sees fit.”
“(a) Fraud or deceit can be raised as a defence in adjudications provided that it is a real defence to whatever the claims are; obviously, it is open to parties in adjudication to argue that the other party’s witnesses are not credible by reason of fraudulent or dishonest behaviour. (b) If fraud is to be raised in an effort to avoid enforcement or to support an application to stay execution of the enforcement judgment, it must be supported by clear and unambiguous evidence and argument. (c) A distinction has to be made between fraudulent behaviour, acts or omissions which were or could have been raised as a defence in the adjudication, and such behaviour, acts or omissions which neither were nor could reasonably have been raised but which emerge afterwards. In the former case, if the behaviour, acts or omissions are in effect adjudicated upon, the decision without more is enforceable. In the latter case, it is possible that it can be raised, but generally not in the former.”
“The policy considerations in respect of the temporary finality of adjudication decisions have been well ventilated elsewhere in many cases. The policy considerations in respect of the approach of the courts to allegations of fraud on enforcement are similar, but also include not allowing parties a ‘second bite of the cherry’ if such allegations could have been raised before the adjudicator. It is also the case that enforcement of decisions is almost always done with a hearing underCPR Part 24 , with argument based upon written evidence, and without actually calling witnesses. If all a party has to do to avoid summary judgment is to raise allegations that have to be resolved with oral evidence, the system of enforcement would become nigh on impossible to manage, and speedy conversion of adjudication decisions into actual payment received would be frustrated. I consider the general direction of all the cases on adjudication enforcement to be in the same direction. Adjudication enforcement proceedings are to be resolved by applications for summary judgment underCPR 24 . It is only in extremely rare cases, which hardly ever arise, that issues that arise on enforcement will themselves be tried. This is because adjudication does not definitively resolve the parties’ rights and obligations under a contract. All it does is result in a decision that has the status of what has been called ‘temporary finality.’”
“In formulating and applying these propositions, courts need to be aware and take into account what goes on construction sites up and down the country. On numerous occasions, contractors and subcontractors and even consultants will submit bills or invoices which are or are believed by the recipient to overstate the entitlement. Whilst there are some ‘cowboy’ and fraudulent builders who prey on the public, it will only rarely be the case that one can presume fraud to have taken place where an invoice or bill is overstated. The claiming party may believe that it is entitled to what it is claiming; there may be a simple and honest mistake in the formulation of the claim; the claim may be based on a speculative but arguable point of law or construction of the contract. In none of these cases can it be said that there was fraud on the part of the claiming party. The Court should be astute and cautious on adjudication enforcement applications in assessing pleas of fraud by the party against whom the adjudication decision has been made. I doubt very much whether there will be any significant number of challenges to enforcement on the basis of fraud.”
“7. Equally Bester seeks to introduce into this Adjudication some obligation on PBS to sell or use the equipment which was substantially bespoke for use on this project and for which Bester was liable to pay. Without prejudice to its rights, PBS has made attempts to sell it or reuse it but without success (see the witness statement of Mr Ondřej Košťál served herewith). The equipment is stored, as Mr Tolson found, and as was evidenced to PBS in early 2017, to Bester’s order and is available to Bester upon payment, as it always was. 8. If/when the plant/equipment can be sold, PBS will give credit to Bester for any value obtained, however PBS denies that it is under any obligation to secure onward sales for the equipment which is substantially bespoke for the Wrexham project and if Bester is able to use it or sell it, upon payment of the Contract value, it is available in storage and at Bester’s disposal. 9. There is no basis to seek to reduce the contract value which attaches to the various items of plant and equipment manufactured for the Contract.”
“In respect of [PBS’s] a Contractor's termination under clause 16.2 of the Subcontract conditions, the Contractor is obliged to hand over Contractor’s Documents, Plant, Materials and other work, for which the contractor has received payment, and work in progress up to the date of termination (clause 16.3). On the basis that no payment has been made in respect of the Equipment, although it has been undertaken in accordance with the Contract and offered to Bester upon terms that it is paid for, PBS has no further obligation to Bester in relation to the plant and equipment other than to keep it safely stored/protected, for which it is entitled also to be paid. Upon payment by Bester, the plant and equipment can be made available to Bester. Bester is liable to pay for the equipment such as was procured at termination, it does not have the right to refuse to pay and insist that PBS takes the risk on an onward sale or disposal for the contract value on the open market. If and to the extent that PBS is able to dispose of any of the equipment, then it will give credit for any sums received.”
“As the witness statement of Mr Ondřej Košťál explains, PBS has tried to find buyers for the equipment but has failed thus far to conclude a contract for the sale of any of the equipment or realise any cash payment in respect of the same.”
“23. Following termination of the PBS/Bester Contract, in order to try and mitigate the losses incurred, PBS B started to look for a project in which to use the equipment. In 2018 it was decided to use the grate for the Olsztyn project. In May 2018 the purchase price and storage costs were fully paid to Detroit Stoker and in the summer 2018 the grate was transported to the Czech Republic and subsequently to Poland in late September 2018. 24. I referred to these matters in my witness statement in the adjudication at paragraphs 11-15. The payment for the sale of the grate for use in the Olsztyn project has not yet been determined as it is wrapped up in the overall account for the project. This piece of equipment is therefore now no longer available to provide to Bester.”
“It is because of Bester’s probable insolvency and potential for it to be wound up in the near future that I am not happy to provide any credit for equipment sold or used elsewhere against the sum awarded by Mr Judkins in the second adjudication.”
“Since the bulk of the supply has already been produced, these costs have been calculated by the supplier on the CA. 16,441,000.0-Kč. At the meeting with the representation of the FY Lodge Cottrell, it was agreed that PBS would purchase a part of the equipment usable for the boiler and its use in another project. The supplier shall retain unnecessary parts of the Nakontrahované supply for PBS … The resulting price of buying part of the technology and thus the termination contract is ca. 13,050,000.0- Kč.” 37.4 Commenting favourably on the saving of over 7,000,000 CZK, Petr Kádner said, in an e-mail copied to Mr Košťál, that he was in favour of the deal. He added: “I believe that the boiler uplacírujeme somewhere”
“I believe that the boiler was being modified for re-use somewhere.” 37.5 While PBS has not disclosed the terms of any final settlement, it appears probable that some such deal was done. Indeed, an e-mail exchange between Mr Novotný and Lodge Cottrell in April 2018 was disclosed in which the parties made arrangements for the fabric filter to be shipped to PBS’s order and Mr Novotný expressed his appreciation that they had been able to resolve “a difficult situation with the Wrexham project in a way that was acceptable to both our companies.”
“The decision on the tank is from our point of view linked to the Olsztyn (Poland) project. The contract should be signed within about two weeks. Then it would be very likely that Yara was the supplier of SNCR for this project as well and we could achieve a comfortable solution for both parties.”
“19. After some negotiation, Yara agreed to use some of the manufactured material elsewhere and only charge PBS B for the equipment that could not be used. A mechanism was agreed in which this amount was paid to Yara on the basis of the invoice already issued to PBS B and the difference was the subject of a credit note from Yara. 20. Yara offered to purchase the tank for its raw material value and PBS E negotiated with Yara for use of the tank in the Olsztyn project in Poland. Yara offered to provide a tank for the Olsztyn project using the material from the Wrexham tank. The manufactured tank was thereafter deconstructed and a new tank built for the use by PBS E in the Olsztyn project. PBS E paid the full value for that tank to PBS B. 21. The SNCR was not a necessary boiler component for construction, and the boiler would be fully operation without SNCR for uncontaminated biofuels and in countries with free emission standards, other than in EU countries. Therefore, the absence of the SNCR was not material to the state of completion of the boiler.”
“It is clear that there may be some slight variation in what equipment is available to hand over to Bester should it eventually make payment of its debt to PBS, however PBS is not seeking to recover anything more than it is due.”
“Once it is proved that a false statement was made which is ‘material’ in the sense that it was likely to induce the contract, and that the representee entered the contract, it is a fair inference of fact (though not an inference of law) that he was influenced by the statement, and the inference is particularly strong where the misrepresentation was fraudulent.”
“First and foremost, in a case where fraudulent material misrepresentations have been deliberately made with a view … improperly to influence the outcome of the negotiation of the contract in favour of the maker and his principal, by an experienced player in the relevant market, there is the most powerful inference that the fraudsman achieved his objective, at least to the limited extent required by law, namely that the fraud was actively in the mind of the recipient when the contract came to be made.”
“If a claimant applies for summary judgment before a defendant against whom the application is made has filed a defence, that defendant need not file a defence before the hearing.”