“… You are to proceed in strict accordance with the following terms and conditions on the understanding that as soon as the formal documents are drawn up you will enter into a contract with Mr & Mrs Russell. This shall be in the form of the JCT Standard Building Contract without Quantities 2005 and such amendments as referred to in item 6 of this letter. In any event, it is understood that such terms and conditions become fully operational upon your commencing works. 1. Contract Sum -£2,098,643.02 . The contract sum includes a client contingency of£50,000 . 2. Contract Period – 48 weeks 3. Date of Site Possession –8th July 2010 4. Date of Contract Commencement –12 July 2010 5. Date for Completion –10th June 2011 6. Contract Documents - The Contract Documents will comprise the following: JCT Standard Building Contract without quantities 2005 and such amendments as referred to in Employer’s Requirements dated November 2009. 6. Contract Documents (cont’d) Contract drawings – as detailed in the Employer’s Requirements dated November 2009 and the tender correspondence detailed below. Tender correspondence as detailed in the attached schedule. 7. Warranties If warranties are required to be entered into, they will be substantially in the form as referred to in the Employer’s Requirements dated November 2009. 8. Contract Conditions Your tender is deemed to be inclusive of all works, terms and conditions as described, drawn and contained within the above documents. Subject to your acceptance of, and compliance with the above, unless and until a formal contract is prepared and executed, this letter, together with your acceptance thereof, shall be deemed to constitute a formal contract between you and Mr & Mrs Russell to carry out the works as described in the aforesaid documents and this letter. ….”
“generally co-ordinate and control the project from cost planning and programming through the setting of a rigorous suite of full contract documentation. This covers the contract administration through the coordination of issue of completion paperwork…. At cost planning stage we highlight alternatives so that informed decisions can be made to optimise choices. At tender stage we prepare a comprehensive set of tender documents to achieve the best competitive tenders from contracts as well as advising the most appropriate contract method etc. to ensure the best result in terms of cost/time/quality. During the post contract period we monitor all aspects of the scheme and report regularly so that any changes can be fully appraised and the scheme can be properly controlled to avoid cost and time overrun… We read this role as releasing the administrative burden from the entire team rather than creating another tier of bureaucracy … Our philosophy is to “make it happen” – we offer a comprehensive service that dovetails with our clients and helps push schemes forward.”
“The burden is on the Claimants to prove that PSP’s advice about the tender and the management of the tender process in the circumstances at the material time fell below the standard of a reasonably competent quantity surveyor, project manager, and contract administrator, causing them to suffer the loss claimed.”
“By reason of the premature appointment of Ibex, the Russells have had to spend significantly more than they ought to have done to complete the Project. For the avoidance of doubt, the Russells accept that PSP is not responsible for each and every overspend on the project, but only for those losses that were caused by PSP. Accordingly, in order to give PSP the benefit of the doubt where appropriate, the Russells have adjusted the Ibex tender to ascertain what would have been a reasonable price for carrying out the Project and only claim the loss incurred in excess of that sum.”
“…establishing causation in construction related professional negligence claims against design professionals such as quantity surveyors and project managers is notoriously difficult precisely because of the difficulty in showing how things would have turned out differently even if the professional had not acted negligently.”
“…demonstrate on the balance of probabilities that the project, if properly run by [the QS], would have resulted in a lower outturn, and what that would have been. The obvious starting point is to consider [the contractor’s] final account of£8.109M , identify the principal reasons for the principal cost increases, and demonstrate why [the QS] bears responsibility for some or all of them.”
“110 THE TENDER DRAWINGS: as listed in appendix B of the Employer’s requirements 120 THE CONTRACT DRAWINGS: will be the same as the Tender drawings.”
“It follows therefore that PSP should have noted and raised this emerging responsibility gap and taken steps to either: a Amend the consultant’s scope of work to make up the design responsibility or b Revert to Ibex to increase the Ibex design contributed c To have arranged a coordinated combination of a and b.”
“Prelims Section A11 calls for the contractor to take on a number of design & drawing responsibilities. Please note that we cannot accept & have not allowed for these. Please see revised Preliminaries issued under Tender Query Response 4.”
“01 The tender drawings are design drawings only and must not be considered as working drawings. 02 The Building Services Contractor shall be responsible for preparing all working detail and fabrication drawings for the proper execution of the works. Note that the Contract may adopt the design drawings for this purpose, providing that the drawings become the responsibility of the contractor and are overstamped as such. The Contractor shall also add any relevant details such as required by this specification. 03 The Building Services Contractor(s) shall be responsible for the following final design elements:- Cable, conduits and trunking route Ceiling rose locations Luminaire connection details Fire alarm panel internal wiring Support of all plant and equipment All builderswork associated with the services installation …”
“So as I say there’s an element, even when you have … full employer’s design where the contractor is involved even though the contractor will say, “We have no design responsibility”, there are elements that they are involved in, and that’s normal.” (ii) When Mr Greenwell was cross-examined on this issue, he accepted that what the contractor was to undertake was not “design”
“VDC explained that further to their contract drawing, they would expect the M&E contractor to provide a set of working drawing (sic) to coordinate the services for (sic) approval by VDC. VDC confirmed that they retain the design responsibility for the M&E packages.” (iv) Mr Greenwell accepted both that Ibex had been clear that they took no design responsibility and that Vector had confirmed that they retained all design responsibility and further that the responsibility for design co-ordination lay with the design team and in particular CLA. (v) Further, Mr Greenwell had not realised that there were, in the tender drawings, 29 builderswork drawings provided by Vector. (vi) This was, therefore, again an instance where there was no “responsibility gap” and no evidence that anyone had ever thought differently. Against that background, it was again unsurprising that Mr Greenwell was not able to proffer a single example where the alleged gap had caused a problem. Some of Mr Greenwell’s responses in cross-examination on this issue are instructive. As part of this answer about the Lutron system, he said this: “So in this particular case, the responsibility or co-ordination, which we’re saying is all down to the M&E contractor, is also for the AV system as well, and …. this is part of my challenge with trying to work out what it was that caused the problems we saw on this project, was that the issues, as a succession of issues, were grey at best and sometimes contradictory, and this is a very good example.”
“So it doesn’t strike me as being particularly unusual where the designer for the windows is the architect taking elements of design advice from a fabricator”
“This significant delay has come about due to the fact that you have chosen to control the procurement of the window package through the Contract Instruction process, the manufacture of the windows has been delayed due to a significant number of changes made by the Architect in the drawing production and approval process and the final delay has been due to the Employer not accepting the standard Formes Alutek finish resulting in the enhanced specification instructed under Contract Instruction no. 90.”
“Since there appears to be a significant amount of obfuscation here it may help if I briefly set out what we regard as the issue. At issue is the finish of the frames – their suitability and fitness for purpose. Formes are the window sub-contractor – that is not in dispute. They have produced extrusions which are anodised correctly. What they have not done is produce a window frame which has an acceptable finish on its adjacent sections. Your e-mail confirms that such a requirements can be met and indeed you have ascribed the costs of circa£3,000 to meeting that requirement. To suggest that in a multi-million pound high end one off house the client should accept window frames which are patently and irrefutably non-matching (in an individual frame rather than one to another) but [when] that standard could have been achieved so easily is astonishing.”
“… This is after the tenders have been received. As we went through all of the tenders, every contractor to a greater or lesser extent has priced the landscaping and Charter in fact being the one who have, if you like, taken a different view from the other three by providing a provisional sum for everything. They had the opportunity during the tendering period to ask questions if they weren’t clear. But each of them took a slightly different approach but other than Charter generally the same approach of putting in a mixture of prices for individual items plus provisional sums.”
“A: One would assume that in the six months between January and July that PSP and the Russells did actually talk to one another about what design development was going on and what adjustments would have to be made. Q: You make that assumption and obviously it’s a matter of fact for the judge in due course? A: Yes Q: Assume they weren’t told that that provisional sums were going up outside of the pool, they should have been told shouldn’t they? A: If you make that assumption, then, you know, yes, you could say that. I think it’s an assumption that would probably not be borne out in practice.”
“This is a similar issue to others: the Russells will say that it is necessary for a Tender Sum Analysis to be clear in order that one knows that is covered, and how to value variations in due course. The item also includes the desirability (on the Russells’ case) for a schedule of rates ….. The point of principle that divides the experts is whether or not, as a reasonably competent quantity surveyor, PSP should have taken more steps to protect the Russells from inadequacies in the pricing that could lead to uncertainty and therefore claims to variations.”
“I do not consider that PSP carried out a sufficient review of the ambitious programme submitted by Ibex. The lack of a detailed programme review and reporting of this is a failing by PSP.”
“So we did interrogate the programme, we did so over the full 6 month period.”
“In theory these dates do not pose any problem, however, the difficulty is agreeing the design with the clients. Frankly, judging from yesterday’s meeting I would doubt that this is possible. Hours seem to pass in agonizing over the minutiae of every detail and progress is only made negatively. We are damned if we provide too much information (we’ve gone too far) and damned if we do not provide a holistic view (how can I decide without the whole picture). The exterior of the building went through a similar phase, with endless sketches and explanations. ….”
“In the case of either option, the Russells do now have their house and so the question is why PSP must pay for the overrun. The reason is that by issuing the letter of intent in the way that they did, PSP locked the Russells into a contract that they could no longer fix (eg. by amending the design). In other words, the extra cost would have been avoided: the Russells would still have had a house, but it would have been for the price (and specification they chose) rather than with an overspend of over£1 million ).”
“The calculation of loss must of course involve comparing what the plaintiff would have lost as a result of making the loan with what his position would have been if he had not made it. If for example the lender would have lost the same money on some other transaction, then the valuer’s negligence has caused him no loss. The distinction between the “no transaction” and “successful transaction” cases is of course quite irrelevant to the scope of the duty of care. In either case the valuer is responsible for the loss suffered by the lender in consequence of having lent upon an inaccurate valuation. When it comes to calculating the lender’s loss, however, the distinction has a certain pragmatic truth. I say this only because in practice the alternative transaction which a defendant is most likely to be able to establish is that the lender would have lent a lesser amount to the same borrower on the same security. If this was not the case, it will not ordinarily be easy for the valuer to prove what else the lender would have done with his money. But in principle there is no reason why the valuer should not be entitled to prove that the lender has suffered no loss because he would have used his some money on some altogether different but equally disastrous venture. …”
“By the time the Project is finished in early 2015, removing the costs of the lower ground floor and pool area, the total construction costs are likely to be in the region of£4.3 million . PSP should have known that a more realistic tender would be between£2.2 -2.4 million and advised the Claimants of this in the Tender Report. If the Claimants had received the correct advice in respect of the true cost and duration of the eventual build and decided to proceed with the project in that form (which would not necessarily have been the case) they would have elected to proceed with a contractor whose costs were in the realistic region of£2.2 -2.4 million. The additional cost incurred in respect of construction work due to negligence advice from PSP is therefore approximately£1.6 million (being the difference between what the Claimant would have paid if advised correctly and what they have actually paid).”
“CONTRACT GUARANTEE BOND Allow for providing a bond for the due performance of the Contract to the Value of 10% of the Contract Sum and incorporating agreed amendments, from an approved Bank/ Insurance Company or similar institution. The bond must be in place before any money is paid under this contract.” (ii) The draft form of bond was a default bond (using the terminology of a guarantee) and not an on demand bond. By clause 1, the Guarantor guarantees the due and punctual performance of the Contractor’s obligations and: “… shall in the event of a proven breach of the Contract by the Contractor (which definition shall include insolvency or other events listed in Contract Clauses) ….. satisfy and discharge the damages costs and expenses sustained by the Employer as established and ascertained pursuant to and in accordance with the provisions of the Contract.” (iii) Clause 2 set out the maximum amount of the bond. (iv) Clause 3 provided: “Any event of insolvency as set out in clause 8.5 of the Contract shall be deemed to be a proven default upon which the Guarantor shall satisfy and discharge the established and ascertained damages caused to the Employer up to the Bond Amount.”
“PSP in the CSA assessed the drainage at£42,790.10 but did not carry this forward to the Valuation Summary. No CAI was issued for the revisions to the drainage.”
“Defective works were known whilst Ibex was still on Site. After Ibex departed Site, further defects were identified but the extent was not fully evident until the tender for further works was prepared by Cameron Black.”
“Following this, a fixed monthly fee was agreed for the four months between September and December 2011: this enabled us to continue our works in attending site, responding to contractor RFIs, and trying to close down remaining design issues. ….. I have already documented all deficiencies in Ibex’s work that I have observed in the course of my regular site inspections that took place while Ibex were proceeding with the construction work. I will be happy to make a further inspection and specific report for the purposes of assessing any damage or latent defects that have occurred over the last three months …..”
“It was around this time [May 2009] that I agreed with Peter Stone that he would interim invoice me for£5k per month on a cash flow basis pending a final agreement as to his fee. However, we also agreed that these payments would not exceed 5% of the contract sum, or whatever other percentage we subsequently agreed. The 5% was a figure which [was] in my head as a maximum because Peter Stone had previously advised that he would do the work of project manager and quantity surveyor for 3.8%. I had been advised by David Copsey [TDM] that 4% to 5% was a reasonable range for the services that Peter Stone was providing. When invoices came in from PSP I did not think much about these and simply paid them. This was because I trusted PSP to police their own fees …”
“If our fee at 5% is applied to the total value of the project that will in part pay for our professional time in some of the areas mentioned above, The easiest way to deal with the prolongation would be to pay our monthly fee of£5,000 for the period of the project ….. In summary our suggestion is that our 5% fee is based on the project value which would naturally “update” the original fee but we agree a fee of£5,000 per month for the extended period. The original fee would have ended in June so there should be a fee of£5k per month from July onwards. On that basis I suggest we invoice£25,000 for the period July-November.”
“If at any time the Client requires the Consultant to perform any services which are not identified as Basic Services in the services listed in the Schedule (“Additional Services”), the Client pays the Consultant for such additional Services at the rates set out in the Appointment Particulars unless otherwise agreed. If the Client requires Additional Services, the Consultant informs the Client of the likely additional fee to be charged ….” (ii) Clause 7.1 provides: “Payment of the Fee, any additional fee payable for Additional Services and the Reimbursable Expenses is due on receipt by the Client of a VAT invoice from the Consultant. Invoices are submitted on each instalment date or on completion of each activity or work stage set out in the Appointment Particulars ……………..”