“Notwithstanding clause 17 (b) the Subcontractor shall submit his final statement for each Works Order together with full substantiation as required by the Contractor to the Contractor within one month of completion of the Works Order.”
“Labour, plant, and material expense incurred in carrying out the works (excludes overheads and profit). Actual Costs will be established through transparent open book audit on an initial basis and thereafter on an annual basis”. ii) The proposed clause 17.1.4 (e) provided that: “If the actual cumulative cost of treatment and disposal of the above stated material varies positively or negatively from the forecast total … then a pain/gain share shall apply on a 50/50 basis between the parties subject to substantiation and agreement of quantities and Actual Costs.” iii) The proposed clause 17.1.4 (g) provided that: “Audits of Actual Cost will be on a sample basis. Such audits to be carried out at the Contractor’s discretion without notice. If in the Contractor’s opinion there is a significant variation in a sample audit a further detailed audit may be invoked. The findings of such audit may vary the allocation within the pain gain mechanism. ….”
“… by varying the payment regime from the outset of the contract, the parties must have necessarily intended that the final payment regime would be varied in like manner. The consequence of this was that, instead of having individual final accounts for each Works Order, with a separate statement required within one month of completion of that Works Order, the parties must have intended to provide for a single final account process within one month of completion of all the Services ordered pursuant to the Subcontract.”
“That having been said, if “now” means November 2018, the tar instalments (if due) have come to an end. It seems to me that, thereafter, a reasonable period should be allowed for any residual ascertainment of actual cost (with any audit in respect thereof) and implementation of the pain-gain provisions. In that context, I bear in mind that such costs will have been expended before July 2017 and should, by now, be capable of ascertainment. There was no argument about timescale but 29. which the implementation of those provisions must come to an end and be replaced with the requirement for [the Defendant] to provide the final statement.”
“Clarification of the issues underlying the declarations was by no means an easy undertaking. Both in his skeleton argument and orally at the hearing, Mr Hickey suggested that the Court should either give the declarations sought or “such declarations as it considered appropriate for the reasons set out in this Skeleton and as expounded at the oral hearing”
“…pending resolution of the final payment, [the Defendant] is entitled to bring a claim through adjudication in respect of adjustments to amounts notified in respect of previous interim payments. Once (and if) it is accepted that [the Defendant] had a right to apply for such interim payments, both before and even after termination (whether pursuant to an agreement or on a convention basis) it must follow that the amounts so notified could be challenged by way of review.”
“If those sorts of granular or contingent claims are made to the adjudicator in respect of a given application, it will be for him or her to determine the permissibility of that approach in the first instance. If it becomes appropriate to revisit that question in Court, whether on enforcement or by way of a separate Part 8 claim, then the issues about that can be properly ventilated in those proceedings at that time.”