“As this was BN’s first job with Everwarm, I asked for a written contract. This request lead to the issuing of a sub-contract order, dated17 December 2013 . Exhibit LN1/66 attached is a scanned copy of the sub-contract order for RANCHA as provided to me and signed by me.”
“Please supply all necessary labour, small plant and tools required to carry out the External Wall Insulation including the installation of all trims, beads etc. 1. Contract Sum Analysis 2. Everwarm’s Subcontract Terms and Conditions – 5 pages ALL FOR THE AGREED RATE OF£21.50 PER M2 ANTICIPATED DATE OF COMMENCEMENT OF SUB CONTRACT WORKS: As per programme of works PERIOD OF NOTICE TO COMMENCE SUB CONTRACT WORKS: 1 week DURATION OF SUB CONTRACT WORKS: As per programme of works RETENTION: 2.5% DISCOUNT: 0.00% DEFECTS LIABILITY PERIOD: 12 months PAYMENT TERMS: Fortnightly The Site Manager for the project will be To Be Confirmed who can be contacted on To Be Confirmed. Please contact the Site Manager upon receipt of Sub Contract Order. It should be stressed that no Sub-Contract exists until Everwarm receives your signed copy of this Order, thereby indicating your agreement to its terms and conditions. If a signed copy of Order is not returned within 7 days of receipt of same, then it will be deemed that you have accepted its contents and will comply with the terms and conditions…”
“Where the conditions are contained in a document, the document must be of a class which either the party receiving it knows, or which a reasonable man would expect, to contain contractual conditions.”
“It is not necessary that the conditions contained in the standard form document should have been read by the person receiving it, or that he should have been made subjectively aware of their import or effect. The rules which have been laid down by the courts regarding notice in such circumstances are three in number: (1) if the person receiving the document did not know that there was writing or printing on it, he is not bound; (2) if he knew that the writing or printing contained or referred to conditions, he is bound; (3) if the party tendering the document did what was reasonably sufficient to give the other party notice of the conditions, and if the other party knew that there was writing or printing on the document, but did not know it contained conditions, then the conditions will become terms of the contract between them.”
“It is not necessary that the conditions themselves should be set out in the document tendered: they may be incorporated by reference, provided that reasonable notice of them has been given.”
“Q: Now, you say that was because it was the first job you didn’t ask for a written contract in relation to the second job or the third job etc? A: No. Q: And the reason for that was because you were working on the assumption that the same terms would apply, is that right? A: What we discussed, yeah. Definitely, yeah”
“Conditions will not necessarily be incorporated into a contract by reason of the fact that the parties have, on previous occasions, dealt with each other subject to those conditions.”
“These terms and conditions shall be deemed to be incorporated in any contract, agreement or Order between the Company and the Sub-Contractor and shall be in substitution for any other terms and conditions introduced before or after the date of the Order (unless expressly identified and agreed in writing by the Company). Furthermore, any action undertaken by the Sub-Contractor in pursuit of their obligations under this Sub-Contract will be deemed an explicit agreement to these Sub-Contract terms and conditions and cannot be rescinded, altered or amended in any way without mutual agreement by the parties to this Sub-Contract.”
“(a) The dimensions of the external walls subject to the EWI Works would be measured and their total gross area calculated; (b) The dimensions of any large opening, such as a window or door, would be measured and deducted from the figure calculated at (a); and (c) An allowance of 1m² would be added back for each such opening as described at (b) above for the reveals.”
“The Company may at any time whatsoever (including without limitation between Valuation Dates) make an assessment of the aggregate of the value of all work properly performed and all other sums properly incurred in relation to the Sub-Contract Works up to the selected assessment date, calculated in accordance with the Subcontract (“the Assessment”). The Company shall be entitled to deduct from or set off against any payments otherwise due to the Sub-Contractor under the SubContract or any other agreement between the Company and the Sub-Contractor the difference between (1) the Assessment together with the aggregate of any other sums which the Company may be entitled to deduct or claim under the SubContract or otherwise and (2) the aggregate of the sums paid and those established as due to be paid to the Sub-Contractor in relation to the Sub-Contract Works. Furthermore, to the extent that any difference above shows that a sum is due and owing to the Company such difference shall be a debt due and payable by the Sub-Contractor within 7 days, without any right of set-off and/or deduction.”
“Discretionary Assessment Notwithstanding any other provision of the Sub-Contract, the Company may at any time whatsoever (including without limitation between Valuation Dates) make an assessment of the aggregate of the value of all work properly performed and all other sums properly incurred and/or owing in relation to the Sub-Contract Works up to the selected assessment date, and otherwise calculated in accordance with the Subcontract (“the Assessment”). To the extent that any Assessment shows that a sum is due and owing to the Company such difference shall be a debt due and payable by the Sub-Contractor within 7 days, without any right of set-off and/or deduction.”
“final assessments because the Defendant had failed to produce and issue final accounts to the Claimant”
“A valuation, which the defendant now seeks to bring into the claim, is completely beside the point. The parties agreed in the Sub-Contracts on a straightforward and cost effective valuation mechanism which would give finality and not require the parties to instruct experts and the like to carry out time consuming and expensive valuation reports.”
“as to the manner in which such powers may be exercised, a term which may vary according to the terms of the contract and the context in which the decision-making power is given.”
“An important feature of the above line of authorities is that in each case the discretion did not involve a simple decision whether or not to exercise an absolute contractual right. The discretion involved making an assessment or choosing from a range of options, taking into account the interests of both parties. In any contract under which one party is permitted to exercise such a discretion, there is an implied term. The precise formulation of that term has been variously expressed in the authorities. In essence, however, it is that the relevant party will not exercise its discretion in an arbitrary, capricious or irrational manner. Such a term is extremely difficult to exclude, although I would not say it is utterly impossible to do so. Certainly clause 1.1.5 of the conditions in the present case is not effective to exclude such a term, if it is otherwise to be implied.”
“PAYMENT SHEET – WELLHOUSE PHASE 2 EWI5125 Last Valuation Date: Jan 17 BN rendering claim Everwarm paid Paid Differenc e Gross 154,580 112,515 42,065 Deduct Variations not substantiated -8323 Additional measure not substantiated -36,564 Method of measurement -12,817 96,876 112,515 -15,639 Deduct Retention 3,057 Nett to date 96,876 109,458 Retention released 0 3,057 Total paid inc. retention£109,458 T&T Assessment – monies due to BN Rendering - Deduct Retention 3,057 Nett to date 96,876 109,458 Retention released 0 3,057 Total paid inc. retention£109,458 T&T Assessment – monies due to BN Rendering -£12,582 ”
“Notice of Assessment of Value of Sub-Contract Works We refer to the Sub-Contract between Everwarm Limited and BN Rendering Limited for external wall insulation works (labour only) constituted by our Sub-Contract Order Number [x]. We hereby give you notice that assessments have been carried out on our behalf by Turner & Townsend. We attach a copy of the Payment Sheet prepared by Turner & Townsend which discloses an overpayment by Everwarm Limited in the amount of £[y]. Please arrange to make payment of such balance due and owing to Everwarm Limited within 7 days failing which action will be taken by us to recover such amount as a debt.”
“We refer to the Sub-Contract between Everwarm Limited and BN Rendering Limited for external wall insulation works (labour only) constituted by our Sub-Contract Order Number [x]. We hereby give notice that assessments have been carried out on our behalf by Turner & Townend: • of the value of the Sub-Contract Works under the above SubContract Order; and • of the value of the Sub-Contract Works under the other Subcontracts with your company. We attached for your reference: • a copy of the Payment Sheet prepared by Turner & Townsend which discloses an unpaid value due to your company for the above Sub-Contract Order of £[y]; and • a copy of the Summary Sheet prepared by Turner & Townsend for all the Sub-Contracts with your company which discloses a total overpayment by Everwarm Limited to your company of£416,406 We confirm that the sum of£416,406 disclosed as the due total to Everwarm Limited is set off against the balance otherwise due underSub-Contract Order 5116 and is due and payable by your company. Please arrange to make payment of such balance due and owing to Everwarm Limited within 7 days failing which action will be taken by us to recover such amount as a debt”
“Every construction contract shall - (a) provide an adequate mechanism for determining what payments become due under the contract, and when, and (b) provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.”
“A construction contract shall, in relation to every payment provided for by the contract— (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.” (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.”
“The requirement in subsection (1)(a) to provide an adequate mechanism for determining when payments become due under the contract is not satisfied where a construction contract provides for the date on which a payment becomes due to be determined by reference to the giving to the person to whom the payment is due of a notice which relates to what payments are due under the contract.”
“There is an important distinction between sections 109 to 110A on the one hand and sections 110B to 111 on the other hand. Sections 109, 110 and 110A set out what a contract must say. If the contract does not comply, then the relevant provisions of the Scheme are incorporated into the offending contract. Sections 142. say. Instead those two sections set out, in somewhat convoluted language, what the parties may or must do in certain situations.”
“(1) This section applies as between contracting parties where one of them deals on the other’s written standard terms of business. (2) As against that party, the other cannot by reference to any contract term – (a) when himself in breach of contract, exclude or restrict any liability of his in respect of the breach; or (b) claim to be entitled – (i) to render a contractual performance substantially different from that which was reasonably expected of him, or (ii) in respect of the whole or any part of his contractual obligation, to render no performance at all, except in so far as (in any of the cases mentioned above in this subsection) the contract term satisfies the requirement of reasonableness.” (a) when himself in breach of contract, exclude or restrict any liability of his in respect of the breach; or (b) claim to be entitled – (i) to render a contractual performance substantially different from that which was reasonably expected of him, or (ii) in respect of the whole or any part of his contractual obligation, to render no performance at all, except in so far as (in any of the cases mentioned above in this subsection) the contract term satisfies the requirement of reasonableness.”
“I refer to my previous correspondence concerning the above contract. In line with the terms of the contract the retention held against our works, as detailed in the attached invoice is now due. I would be grateful if you could arrange for payment of this retention immediately.”
“110A Payment notices: contractual requirements (1) A construction contract shall, in relation to every payment provided for by the contract— (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date. (2) A notice complies with this subsection if it specifies— (a) in a case where the notice is given by the payer— (i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated; (b) in a case where the notice is given by a specified person— (i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated. (3) A notice complies with this subsection if it specifies— (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated. (4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero. (5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply. (6) In this and the following sections, in relation to any payment provided for by a construction contract— “payee” means the person to whom the payment is due; “payer” means the person from whom the payment is due; “payment due date” means the date provided for by the contract as the date on which the payment is due; “specified person” means a person specified in or determined in accordance with the provisions of the contract. (a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or (b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date. (a) in a case where the notice is given by the payer— (i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated; (b) in a case where the notice is given by a specified person— (i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated. (a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and (b) the basis on which that sum is calculated. “payee” means the person to whom the payment is due; “payer” means the person from whom the payment is due; “payment due date” means the date provided for by the contract as the date on which the payment is due; “specified person” means a person specified in or determined in accordance with the provisions of the contract. 110B Payment notices: payee's notice in default of payer's notice (1) This section applies in a case where, in relation to any payment provided for by a construction contract— (a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2)not later than five days after the payment due date, but (b) notice is not given as so required. (2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3)at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given. (3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given. (4) If— (a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of— (i) the sum that the payee considers will become due on the payment due date in respect of the payment, and (ii) the basis on which that sum is calculated, and (b) the payee gives such notification in accordance with the contract, that notification is to be regarded as a notice complying with section 110A(3)given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection). 111 Requirement to pay notified sum (1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment. (2) For the purposes of this section, the “notified sum” in relation to any payment provided for by a construction contract means— (a) in a case where a notice complying with section 110A(2)has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice; (b) in a case where a notice complying withsection 110A(3)has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice; (c) in a case where a notice complying with section 110A(3)has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice. (3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum. (4) A notice under subsection (3) must specify— (a) the sum that the payer considers to be due on the date the notice is served, and (b) the basis on which that sum is calculated. It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero. (5) A notice under subsection (3)— (a) must be given not later than the prescribed period before the final date for payment, and (b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined. (6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a). (7) In subsection (5), “prescribed period” means— (a) such period as the parties may agree, or (b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts…..”
“The final payment payable under a relevant construction contract, namely the payment of an amount equal to the difference (if any) between: (a) the contract price; and (b) the aggregate of any instalment or stage or periodic payments which have become due under the contract, shall become due on – (a) the contract price; and (b) the aggregate of any instalment or stage or periodic payments which have become due under the contract, (i) the expiry of 30 days following completion of the work; or (ii) the making of a claim by the payee, whichever is the later.”
“4.11 The Company may deduct from any interim payment due to the SubContractor a sum equivalent to 5% (or such other amount as may be identified in the Order) of each such payment by way of retention. 4.12 No earlier than six months after the completion of the Sub-Contract works (or such other period as may be identified in the Order) the Sub- Contractor may make a written request for release of one half of the retention. The due date for payment of such amount shall be the date or receipt by the Company of the written request and payment thereafter will be dealt with in accordance with clause 4.3.4 to 4.3.12. The Company may, at its discretion release these monies earlier. 4.13 No earlier than twenty four months after the completion of the SubContract works (or other such period as may be identified In the Order) and subject to the agreement of the Company that any defects in the SubContract Works have been completed to their satisfaction and In accordance with clause 2.7, the Sub-Contractor shall make a written request for release of the second half of the retention. The due date for payment of such amount shall be the date or receipt by the Company of the written request and payment thereafter will be dealt with in accordance with clauses 4.3.4 to 4.3.12. The Company may, at its discretion, release these monies earlier.”
“By our calculation, the total sum of our client’s overpayments exceed the total sum of the sums due to your clients on the sites listed above. In light of the above, our client does not accept your client’s position as set out in your letter of15 April 2019 and accordingly our client will not be making payment of any sums at this stage for the reasons set out above.” 240.Curiously, the letter ends: “This letter is without prejudice to and under reservations of our client’s rights and pleads and neither the letter (nor any copy of it) nor its contents may be produced, exhibited, referred to or founded upon in any court action or in any other proceedings except (a) with our client’s express written consent or (b) at our client’s instance.”