“85. The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator’s decision unless it is plain that the question which he had decided was not the question referred to him or the manner in which he had gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of the adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case, which ….. may, indeed, aptly be described as “simply scrabbling around to find some argument, however, tenuous, to resist payment”. 86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator’s reasons and identify points upon which to present a challenge under the labels “excess of jurisdiction” or “breach of natural justice”
“…. I conclude as follows in relation to breaches of natural justice in adjudication cases: (a) it must first be established that the adjudicator failed to apply the rules of natural justice; (b) any breach of the rules must be more than peripheral; they must be material breaches; (c) breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant …..”
“… we may well have comments before a final draft can be circulated so it’s unlikely to be ready for collection tomorrow.”
“I refer to our earlier discussion and confirm that the draft deed which deals with: 1. Revised scope of works – envelope, shell & core and no external works to plots 1&2, 2. Final account for project agreed at 8.6m in full and final settlement, including all contractor and employer claims and counterclaims, and 3. Payment plan (proposed by employer for agreement by contractor, if not agreed contract payment terms remain), is being reviewed by our lawyers whom I have just chased and should have their comments back shortly to send on to you. It appears that we are both pulling in the same direction, but since it must be set out in a deed I’m sure you appreciate that I must run it past our solicitors, allowing them a reasonable time to get back to us. Please confirm that you will remove the items relating to the draft deed of variations from your latest contractor’s report as it is premature and possibly misleading until the finalisation and execution of a variation deed. It would be counter-productive and serve neither of us if the funders and their monitoring surveyor see the report out of context and decide to pull out of the refinancing.”
“17. As JJR has not sensibly abandoned its argument regarding there being an agreement and has produced further witness statement with “supporting” evidence, Rosemary Lodge include a witness statement from Bruce McGlew (Tab A) to explain the nature of the without prejudice discussions between the parties and the fact that no agreement has been reached. This is corroborated by the witness evidence of Iestyn Lewis (Tab B) and Huw Morgan (Tab C).”
“22. The fact that there was a draft Deed of Variation demonstrates that there was no agreement, until such time that it was executed. If an agreement had been reached by discussion at a meeting there would have been no emphasis on following it up with a Deed of Variation. There would be no draft Deed of Variation at all. This would have been explained to JJR when it sought legal advice on the drafting of the deed. 23. The parties are both commercial business who realised the importance of recording the terms of any agreement to be reached in a formal and binding way (with the benefit of legal advice). The parties therefore embarked upon a process of drafting and negotiating a Deed of Variation, which was never finalised or executed. 24. It was plainly the parties’ intention that if there was no executed Deed of Variation, there was no binding agreement to vary the Contract. 25. This is completely in line with the parties’ agreement that “nothing is agreed until everythingis agreed” as outlined in Bruce McGlew’s witness statement at Tab A (as supported by Huw Morgan (Tab C) and Iestyn Lewis (Tab B)). Some of the principles were agreed but others were not, and that is what prevented the execution of the Deed of Variation.”
“I also recollect that we made it clear that our hands were tied by what our funders would sign off on and so we could only really deal with principles. Any terms would need to be run passed (sic) the funders and lawyers. Its (sic) why JJR provided a draft Deed of Variation shortly after the meeting without us prompting: they knew they meeting was the first step in the process of reaching any formal agreement.”
“I have confined by explanations to the essentials only but nevertheless I have carefully considered all the evidence and submissions although not specifically referred to in this Decision.”
“Mr Bruce McGlew did not deny that agreement was reached. He has said in his statement that the figure of£8.6m was discussed and that there were other key terms which needed agreement such as payment terms and that the Claimant [RDL] could not unilaterally agree any terms without having the funders approve them. He has been careful not to deny that agreement was reached as to the figure. He also said that during the meeting Mr Ronayne stated that “nothing is agreed until everything is agreed.”
“It may be considered surprising that both Mr McGlew and Mr Lewis could recollect and state the exact words which they say were used by Mr Ronayne at a meeting held approximately six months prior to providing their witness statements, which suggests that these two witnesses collaborated when writing their statements. Mr Neylon in a subsequent Witness Statement has denied that such a statement was made, but I find that that part of the evidence is irrelevant anyway. Both of the Claimant’s witnesses had said that the statement was made during the meeting, and therefore it is not inconsistent with the Respondent’s allegation that by the end of the meeting everything was agreed.”
“My Findings as to the Agreement 22. I have considered all the evidence including that of the four witnesses whoattended the meeting on30th May 2018 and particularly the evidence of the Respondent’s witnesses that was denied by the Claimant’s witnesses, the subsequent conduct of the Parties in having the fit-out of plots 1 &2 carried out by others, and the email from Mr McGlew of6th June 2018 , repeated above, which confirmed at paragraph no. 2 that the final account was agreed at£8.6M in full and final settlement, including all Contractor and Employer’s claims and counterclaims, and I conclude that the agreement was made as alleged by the Respondent. 23. The Claimant has relied on the fact that the Deed of Variation was not executed but I find that that is irrelevant. It is quite usual for parties who have made a binding oral agreement to record that agreement in writing, and if as is the case here the Deed was not finally executed that does not detract from the legal standing and binding nature of the oral agreement. 24. In fact it would appear that the Deed of Variation was agreed with the exception of the Payment Terms as confirmed in the email from Mr Neylon to Mr McGlew of28th August 2018 as repeated below. Email from Tom Neylon to Bruce McGlew –28th August 2018 12.55 “Bruce As discussed this morning on the phone the only outstanding item on the deed is the payment terms as you have stated you “cannot agree these with the financiers until PC has been achieved”
“So far so good: it is relatively easy to see why a deliberate failure to consider an issue (particularly a defence) which the adjudicator should have considered might well amount to a breach of natural justice. But the Scottish case of Whyte and Mackay Ltd v Blyth and Blyth Consulting Engineers Ltd. took the matter considerably further. There, the adjudicator failed to consider a submission raised by the defenders to the effect that, even if they had advised that piling work was necessary, the employer would not have taken that advice. The judge found that the adjudicator had addressed the question of causation but for whatever reason, did not mention the defenders’ submission on the issue that the pursuers would not have paid for the piling work in any event. It appears, therefore that the adjudicator’s error was inadvertent; it certainly did not appear deliberate. Lord Malcolm concluded that this was a very significant omission in the adjudicator’s decision and reasoning and his failure to deal with what was potentially a complete answer to the claim amounted to a breach of natural justice. Whilst this decision is perfectly understandable on its own facts, it might be regarded as something of an inroad into the general principle that an adjudicator can make errors or law and fact without affecting the validity of his decision. ….. It is respectfully submitted that, at least on this aspect of the case, Whyte and MacKay should be regarded as a case on its own facts, in particular because the point raised by the defenders was so important, and the adjudicator’s failure to deal with it was so complete that, in those unusual circumstances, a breach of natural justice was made out. ….”
“47. …. [The adjudicator] was not obliged to set out in extenso his response to every last element of Modus’ case; nor was be obliged to give detailed reasons for every part of his conclusion. 48. Further, for the reasons I have already indicated, the Adjudicator took all of these matters into account. I have already referred to paragraph 8 of his decision [in the present case paragraph 7] … That makes plain that the Adjudicator considered every point raised by the parties, whether or not he had dealt with these points expressly in his decision. There is nothing to suggest that the adjudicator did not do what he said he had done in paragraph 8 of his decision ….. It seems to me that the adjudicator took into account all the relevant points, including this secondary argument.”
“If an adjudicator declines to consider evidence which, on his analysis of the facts or the law is irrelevant, that is neither (a) a breach of the rules of natural justice nor (b) a failure to consider relevant material which undermines his decision on Wednesbury grounds or for breach of paragraph 17 of the Scheme. If the adjudicator’s analysis of the facts or the law was erroneous, it may follow that he ought to have considered the evidence in question. The possibility is inherent in the adjudication system. It is not a ground for refusing to enforce the adjudicator’s decision …..”