“Proman have now received approval that the costs quoted by Sitol were accepted and it is our employer’s intention (the Finegolds) to enter into an NEC contract with you based on the following:”
“All financial matters must be forwarded to Proman. All approved payments will be sent by Proman by electronic transfer.”
“Following a number of conversations and emails with David Muir, we agreed that Proman would carry out all of the works which were required to complete the project, appointing specialist contractors to undertake those works,” which would have to read subcontractors. “In exchange, I paid Proman a fixed lump sum in respect of its overhead and profit, referred to as a “fee”, as well as the cost of the work carried out on site.”
“Please find the revised budgets following our discussions. I have kept the wow factor to the ground floor pool area and master bedroom, simplified all the other areas. I will issue you with a schedule of all savings.”
“The work will be undertaken by Proman UK, acting as your project managers, and for this I have reduced all previous budgets by 10 per cent and then shown our fee of 10 per cent for this service.”
“We are very excited to work with you. We have agreed a maximum budget of£3.1 million . Anything less than that we will split. Also, you and your team’s fees are fixed so that if the budget is completed in less time you will still get all of it, and if it overruns we do not pay any more.”
“Yes. That is the basis of our agreement. Many thanks. We can speak later.”
“Here are the insurance cover documents for employer’s and public liability and professional indemnity which cover all our fee work.”
“Our contractors all risk policy is currently being updated with specific details of your project. I have had to complete a further risk profile with them last Friday because of the intended basement works.”
“Preparation work, site establishment, preliminaries and project management as per the attached valuation.”
“Please make the payment to PM UK so we can them paid.”
“Although I do not deny that Sitol appears to have been provided with a contractual document, I did not agree to it, never entered into it, not aware of it until Sitol provided a copy. I had not hear of Sitol until long after the alleged contract had been gone into.”
“Regardless of understanding of our agreement, the contractor still required payment for work done, which does not include any of our fees which I sent you this morning.”
“Your current liabilities for contractors and supplies are in the region of£925,000 , leaving us with£75,000 in fees, which is a massive shortfall.”
“I am not agreed. I originally agreed£3.1 million . Last week I reluctantly agreed£4 million (inaudible). I was very clear. Why would I agree more? It is not acceptable. You surely cannot have agreed to pay out£1.4 to£1.7 million without my prior approval?”
“As per our gentleman’s agreement, find our VAT invoice for the next set of progress payments which need to be paid to the contractors.”
“As discussed, the last payment needs to be roughly 200k, so that will leave you with 100k to call on between now, so please manage your deals and cashflow accordingly.”
“A party may refer a dispute to the adjudicator if the party notified the other party of the dispute within four weeks of becoming aware of it.”
“We do not intend to rehearse our client’s position as in 19 February letter. Mr Finegold’s position remains that a contractual relationship between you does not exist. The only contractual relationship our client has entered into is with Proman. They are not obliged to make any payment to you. It is a prerequisite of any contract that parties had an intention to create legal relations. In circumstances where Mr Finegold had not heard of Sitol Limited (inaudible) carrying out the works and has not seen or signed a contract with you, we cannot see how you can maintain that you have a valid claim. As set out in our 19 February letter, your contractual relationship in respect of the works is with Proman. Proman is responsible for payment of the outstanding sum. We respectfully repeat our suggestion you direct all requests for payment to the liquidators.”
“You refer to a contract, but you have not provided copies of the contract. You have failed to provide any evidence to support your assertion that a contractual relationship exists between you and Mr Finegold. The onus on you is to demonstrate your entitlement. If you disagree with our client’s position, we invite you to provide evidence or any other legal basis for your claim. In the absence of this, your claim is without merit.”
“To the extent you intend to continue to seek to recover the outstanding sums from Mr Finegold, we respectfully suggest you seek independent legal advice in relation to your position.”