“Sections; range of liquidated damages for each Section”
“Practical Completion”: a stage of completeness of the Works or a Section which allows the Property to be occupied or used and in which: (a) there are no apparent deficiencies or defects and no incomplete items of work which would or could: (i) compromise the health and safety of persons entering and/or occupying the Property; (ii) given their cumulative number and/or nature, have more than a trivial impact on the beneficial occupation and use of the Property for the intended purpose, by reason of their rectification or completion; and/or (iii) in relation to the work necessary to remedy them will cause interference or disruption to the beneficial use or occupation of the Property; (b) the Site has been substantially cleared of all temporary buildings, builders’ plant and equipment, unused materials and rubbish and cleaned; (c) any other stipulations or requirements which the Contract Documents indicate are to be complied with before Practical Completion have been complied with to the reasonable satisfaction of the Employer. (d) the relevant Statutory Requirements have been complied with and any necessary consents or approvals obtained; (e) all parts of the Works or services in a Section are fully functioning, and safe access to the Section (and associated plant areas required to operate the Section) through or around any other uncompleted sections can be secured on behalf of the Employer or any Tenant (including their contractors, sub-contractors, consultants, sub-consultants, suppliers and agents) in accordance with the access provisions set out in the relevant section of the Employer’s Requirements; (f) full testing and commissioning of the services installations has been completed satisfactorily and/or such testing or commissioning has included: 1. Complete testing and proving of all systems and equipment with the provision of all certification to the Employer; 2. Regulation of all air and 3. Completion of the Building Management System and Controls as follows: (i) All equipment in position with all wiring complete and satisfactorily tested (ii) Point to point testing complete and satisfactorily certified; (iii) All sensors calibrated and satisfactorily certified; (iv) Functioning testing (software debugging) – fully complete, tested and satisfactorily certified; (v) BMS Supervisor and Graphics – fully complete, tested and satisfactorily certified; (vi) Fine tuning of control loops – substantially complete; and provided always that where the Contract Documents expressly state that the commissioning, testing and/or adjustment of any mechanical or electrical services installations forming part of the Works is to be completed before Practical Completion of the Works is to be regarded for the purposes of this Contract as achieved, then the Works shall not be considered to have achieved Practical Completion for the purposes of this Contract until such commissioning testing and/or adjustment is completed as the Contract Documents require and the relevant certificates issued. Property is defined as: ““Property”: the property comprised of the completed Works.”
““Works”: the works briefly described in the First Recital, as more particularly shown, described or referred to in the Contract Documents, including any changes made to those works in accordance with this Contract.”
“Practical Completion 2.27 When Practical Completion of the Works or a Section is achieved and the Contractor has sufficiently complied with clause 2.37 and 3.16.5, then: 1. in the case of the Works, the Employer shall forthwith issue a statement to that effect (‘the Practical Completion Statement’) and the Employer shall from such date be entitled to enter and take possession of the completed Works with effect from such date; 2. in the case of a Section, he shall forthwith issue a statement of Practical Completion of that Section (a ‘Section Completion Statement’); and Practical Completion of the Works of the Section shall be deemed for all the purposes of this Contract to have taken place on the date stated in that statement.”
“SECTIONAL COMPLETION 1.10 There will be a requirement for Sectional Completion, of various areas of the building as defined within Volume 4, to facilitate the installation of equipment. The Tender is to advise as part of the Tender return the dates on which these areas will be complete. The Contractor’s attention is directed to the requirements associated with the provision of these Sectional Completions…” ii) At paragraph 54 of Section A13 Description of the Works it is provided as follows: “SECTIONS OF THE SITE FOR COMPLETION AND HANDOVERS The Contractor is attention is drawn to the requirements of Sectional Completion, early access and coordination included in Volume 4….”
“160 PARTIAL POSSESSION / SECTIONAL COMPLETION BY EMPLOYER Practical Completion (Section and final) and Handover Procedures The Employer intends to achieve a completely defect-free (at the discretion of the Employer) and fully documented Completion of each section of the project which, on handover, will not require any further attention from the Contractor, other than to rectify faults that might occur or become manifest after Practical Completion of the section and the Practical Completion of the whole of the project…. Section(s) of the Works shall be handed over in accordance with the outline programme and the Sectional Completions as set out in Clause A13 and Volume 4 of the Employer’s Requirements…. Requirements for Practical Completion of a Section For Practical Completion of a Sectional [sic] the whole of the works in that Section are to be completed and cleaned, with all services in a Section being fully functional and with safe and secure access/egress to the defined Sectional Area through or around other uncompleted Sections/areas of the works.”
“27. I decide that Balfour Beatty are entitled to the declaration that they seek in this adjudication. I accept Balfour Beatty’s assertion that the ordinary and natural meaning of the words used in the definition of Practical Completion means that it is not possible to achieve Practical Completion of any Section in isolation from the other Sections ……………”
“28. Given the above definition, the only time of which the property comprised of the completed National Automotive Innovation Centre could be occupied and used is when all Sections have achieved Practical Completion. Clearly for the development to be complete requires all four Sections of the Works to achieve Practical Completion. In view of this clear definition it is not possible to achieve Practical Completion of any Section in isolation from the other Sections. I do not consider that it is possible (and or appropriate) to read anything else into the words that have been used. 31. ………….. “The words used in the definition of Practical Completion therefore stipulates that an individual Section only achieves Practical Completion at a stage of completeness which allows the completed Works to be occupied and used. By referring to the completed Works I consider this indicates that all Sections must achieve Practical Completion for any Section to meet the definition of Practical Completion included in the Contract. This definition on the face of it may seem illogical however the words used by the parties are clear and unambiguous. Other than applying this literal interpretation I am unable to determine any alternative definition of Practical Completion from the words used by the parties.”