“A dispute has arisen between the parties to the sub-contract concerning the failure of the Responding Party to pay the sum of£84,760.04 to the Referring Party pursuant to the following invoices issued by the Referring Party and less interim payments made by the Responding Party in the sum of£38,068.72 .”
“At clauses 13.2, 13.4, 13.6 and 14.4 of the sub-contract, pre-conditions of Northern’s ability to deduct or set off any sum for remedial works?” (ii) At paragraph 41 of the Decision the Adjudicator found that: “Clause 14.4 imposes strict obligations on Northern prior to recovery of costs incurred from Synergy in respect of alleged defects which occurred during the defects period”
“The issues are as follows…are clauses 13.2, 13.4, 13.6 and 14.4 of the Sub-contract, pre-conditions of Northern’s ability to deduct or set-off any sum for remedial works?”
“I therefore make my DECISION … Issue 2 A clause 14.4 notice is a pre-condition to deduction or set-off any sum for remedial works during the defects liability period”
“The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the Adjudicator’s Decision unless it is plain that the question which he has decided was not the question referred to him or the matter in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the Decision of an Adjudicator. The court should give no encouragement to the approach adopted by DML in the present case; which (contrary to DML outline submissions to which we have referred in paragraph 66 of this Judgment) may, indeed aptly be described as “simply scrabbling around to find some argument, however tenuous, to resist payment”
“12. It is trite law that adjudication is a speedy process designed only to provide what is called “interim finality” on construction disputes. Parliament intended that the parties should be given a quick answer, and that quick answer should be binding on the parties until the dispute, whatever it may be, is resolved finally either by litigation or arbitration. It has been said in a case concerning what is called a statutory scheme, namely the statutory instrument entitled theScheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) by Chadwick LJ in Carillion Construction Limited v. Devonport Royal Dockyard Limited[2006] BLR 15 , paragraph 86 that the “need to have the right answer has been subordinated to the need to have the answer quickly”