“Please can you send me the information requested at the meeting and in 2 previous emails as we are unable to work out the costs you are claiming for the lower columns [which formed part of the additional work]. We still require the original day sheets as you have previously sent copies plus the operatives need to be named on the Assesmont day work spreadsheet”
“Can you also provide the qualifications for all the operatives you claim were on site as over half of the sheets you have sent which we do not accept have a number of operatives only”
“... the defendant must be able to demonstrate that: (a) there is a short and self-contained issue which arose in the adjudication and which the defendant continues to contest; (b) that issue requires no oral evidence, or any other elaboration beyond that which is capable of being provided during the interlocutory hearing set aside for the enforcement; (c) the issue is one which, on a summary judgment application, it would be unconscionable for the court to ignore”
“What that means in practice is, for example, that the adjudicator’s construction of a contract clause is beyond any rational justification, or that the adjudicator’s calculation of the relevant time periods is obviously wrong, or that the adjudicator’s categorisation of a document as, say, a payment notice when, on any view, it was not capable of being described as such a document [was wrong]. In a disputed case, anything less would be contrary to the principles set out in Macob, Bouygues and Carillion”. “19. It is axiomatic that such an issue could still only be considered by the court on enforcement if the consequences of the issue raised by the defendant were clear-cut.”
“20….(a) Fraud or deceit can be raised as a defence in adjudications provided that it is a real defence to whatever the claims are; obviously, it is open to parties in adjudication to argue that the other party’s witnesses are not credible by reason of fraudulent or dishonest behaviour. (b) If fraud is to be raised in an effort to avoid enforcement or to support an application to stay execution of the enforcement judgment, it must be supported by clear and unambiguous evidence and argument. (c) A distinction has to be made between fraudulent behaviour, acts or omissions which were or could have been raised as a defence in the adjudication and such behaviour, acts or omissions which neither were nor could reasonably have been raised but which emerge afterwards. In the former case, if the behaviour, acts or omissions are in effect adjudicated upon, the decision without more is enforceable. In the latter case, it is possible that it can be raised but generally not in the former. (d) Addressing this latter case, one needs to differentiate between fraud which directly impacts upon the subject matter of the decision and that which is independent of it.”
“The policy considerations in respect of the temporary finality of adjudication decisions have been well ventilated elsewhere in many cases. The policy considerations in respect of the approach of the courts to allegations of fraud on enforcement are similar, but also include not allowing parties ‘a second bite of the cherry’ if such allegations could have been raised before the adjudicator”
“In an application to stay the execution of summary judgment arising out of an Adjudicator’s decision, the Court must exercise its discretion under Order 47 ... ... with considerations a) and b) firmly in mind. (d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial ... may constitute special circumstances…rendering it appropriate to grant a stay”
“Accordingly, in my judgment, a further principle should be added to those in the Wimbledon Construction Company 2000 Limited case and I expressed myself in these terms in the first draft judgment. I expressed in that draft that in my judgment, the principles set out in the Wimbledon Construction Company 2000 Limited case should have added to them a further one”
“Three times Assesmont (other ops on a course should be on site at 12) half day” and then after that a number and the abbreviation “ops”
“As discussed, I have been reliably informed by members of Assesmont Limited’s team past and present that it was Dave Sams’ intention to exploit the works at Apollo House in the belief that Creative Steel Solutions Limited has carried out all the works”
“As you may be aware, Dave Sams and Scott Harvey have some past history and although I have no proof, I have been reliably informed that there was a clandestine relationship there and some reward offered to Scott Harvey for the work/info given and backup. It has been relayed to them that it was his intention to vastly inflate his costs in the belief that it was to be deducted from our account. Steve Pearce, who works for me, asked him what he was up to when he was investigation [sic] parts of the structure on site that were not part of his works or works you had asked him to provide an opinion on, when confronted his comment was ‘It’s between Me & Jason’”
“If the summary judgment is granted but Brookvex is subsequently successful on the valuation of works and sums are due in return to Brookvex (which I do not accept) the Court can be satisfied that Assesmont will be able to pay such sums which would at the most be around£60,000 ”