“we can confirm that installation thus far was to a good standard and was in accordance with our assembly guidance. It is important that as the build continues that the batter on the face is maintained as per our design and that the horizontal joints are laced with continuous lacing also any temporary ties should be removed.”
“Anthonyroylance@yahoo.co.uk”
“Anthony Roylance Eur.Ing, A.Roylance, C Eng MICE Chartered Civil Engineer”
“By a contract made partly orally and partly in writing, and to the extent in writing contained in email messages passing between the Claimant and First Defendant commencing in November 2010, the First Defendant in the course of its business agreed to carry out some of the structural engineering design works directly for the Claimant (“Contract”). As part of those works it carried out a redesign of the Gabion Retaining Wall it had previously commenced designing for Renew. It did so because the original design it had produced was not suitable for the actual site conditions. Its contract with the Claimant was to amend the design of the wall and associated features including drainage to produce a functioning retaining wall that was fit for purpose for the site.”
“As I see it the following need to be completed: 1. Design and drawings of the “cut-off” drain being constructed behind the gabion wall – I assume you will need Peak’s input to prove that the drain as installed can cope with the groundwater flows.”