“For the purposes of this Agreement, Project Co Events of Default means any of the following events or circumstances: … Service Failure Points (i) Project Co being awarded a total of 8593 or more Service Failure Points in any 6 month rolling period…”
“On the occurrence of a Project Co Event of Default, or within a reasonable time after the Trust becomes aware of the same, and while the same is subsisting, the Trust may: … (c) In the case of any Project Co Event of Default referred to in clause 44.1(i) (Service Failure Points), if Project Co is awarded 4297 or more further (Service Failure Points) in the following 3 month period, terminate this Agreement in its entirety by notice in writing having immediate effect.”
“Subject only to paragraph 3.2, the Trust may serve notice terminating the Project Agreement at any time if it is entitled to do so under the terms of the Project Agreement.”
“the Trust shall not terminate or serve notice terminating the Project Agreement in respect of a Project Co Event of Default without giving to [BOS]: 3.2.1 at least the Required Period of prior written notice (a “Termination Notice”) stating: (a) that a Project Co Event of Default has occurred and the proposed Termination Date; and (b) the grounds for termination in reasonable detail, and 3.2.2 not later than the date falling 20 Business Days after the date of a Termination Notice a notice containing details of any amount owed by Project Co to the Trust, and any other liabilities or obligations of Project Co of which the Trust is aware (having made proper enquiry) which are: (a) accrued and outstanding at the time of the Termination Notice; and/or (b) which will fall due on or prior to the end of the Required Period, under the Project Agreement.” (a) that a Project Co Event of Default has occurred and the proposed Termination Date; and (b) the grounds for termination in reasonable detail, and (a) accrued and outstanding at the time of the Termination Notice; and/or (b) which will fall due on or prior to the end of the Required Period, under the Project Agreement.”
“… the period starting on the date of a Termination Notice and … (b) following the Payment Commencement Date, ending 60 Business Days later.”
“We write in accordance with the requirements of clause 3.2.1 of the Funders Direct Agreement to notify you in writing: (a) that Project Co Events of Default have occurred under clause 44.1(i) of the Project Agreement; (b) that the requirements set out in clause 44.3 (c) of the Project Agreement have also been satisfied, meaning that the Trust is entitled, in accordance with clause 44.3 (c) of the Project Agreement, to terminate the Project Agreement in its entirety with immediate effect; (c) that the Trust proposes to terminate the Project Agreement on25 August 2017 . As required by clause 3.2.1 (b) of the Funders Direct Agreement, the grounds given giving rise to the Trust’s right(s) to terminate are set out below.”
“Subject to the provisions of clause 3 of the Funders Direct Agreement (which is attached at schedule 6 of the Project Agreement), the Trust is now entitled under clause 44.3(c) of the Project Agreement to serve a notice on Project Co terminating the Project Agreement with immediate effect. The Trust is also entitled and obliged (pursuant to the said clause 3 of the Funders Direct Agreement) to serve notice on the Agent of its intention to do so which, as we have explained above, is the purpose of this correspondence.”
“We write in accordance with the requirements of clause 3.2.2 of the Funders Direct Agreement to notify you in writing of details of any amount owed by Project Co to the Trust, and any other liabilities or obligations of Project Co of which the Trust is aware (having made proper enquiry) which are: (a) accrued and outstanding at the time of the Termination Notice; and/or (b) which will fall due or prior [to] the end of the Required Period, under the Project Agreement. In fulfilment of the above obligations, I attach a table identifying all known heads of claim together with a supporting narrative…”
‘Details of amounts due’
‘any other liabilities and obligations which are accrued and outstanding at the date of the Termination Notice (1 June 2017 )’
‘any other liabilities and obligations which will fall due on or prior to the end of the Required Period (25 August 2017 )’
“The Trust shall not terminate … the Project Agreement … without giving … a notice …”
“details of any amount owed by Project Co to the Trust, and any other liabilities or obligations of Project Co …”
“of which the Trust is aware (having made proper enquiry)”
“which are: (a) accrued and outstanding at the time of the Termination Notice; and/or (b) which will fall due on or prior to the end of the Required Period, under the Project Agreement.”