“Accordingly, I find that it was the common understanding of the parties in June 2010 that the enhanced testing and remediation of each shipment required by the NCR for that shipment was to be regarded as a result of the relevant NCR. Whether or not Fluor privately took the view that it would have carried out the enhanced testing and remediation in any event is, for the purposes of the construction of the waiver letter, irrelevant.”
“The potential problem with seeing this as a “two-stage” process is that there is an increased risk of falling into error by approaching the two “stages” inconsistently and thereby allowing Fluor to recover in respect of costs and delays which have been settled. There is a significant risk that, when one considers the temporal consequences of the unsettled periods, the temporal consequences of the NCRs are not fully taken into account.”
“For example, the impact of matters like out of roundness or transformers cannot be determined in isolation at a “properly performed” stage: the consequences of the NCRs influenced how these issues were experienced and addressed.”
“. . . A defendant who has, in breach of duty, made it difficult or impossible for a claimant to adduce relevant evidence [as to the consequences of a breach of duty] must run the risk of adverse factual findings.”
“SHL will confirm whether or not the MPs can be installed safely based on final DC Reports.”
“. . . [SHL] shall in no event be obliged to install Oversized Mono Piles or to use its equipment beyond levels acceptable to [SHL]. If [SHL] initially accepts to install Oversized Mono Piles, this will not waive [SHL’s] right to stop the installation of Oversized Mono Piles at any time and at [SHL’s] sole discretion . . . ”
“IGE 02 - within tolerances IGH04 - slightly outside tolerances but considered acceptable by Fluor IGI 06 - slightly outside tolerances but considered acceptable by Fluor”
“Given the above, it may have been possible to complete installation of the MP on or only shortly after24 July 2009 .”
“GGOWL’s issuance of NCRs 006, 008 and 009, and its demands that Fluor change its NDT procedure and retest and repair welds previously tested, had a profound and devastating impact on the Project. Not only did all offshore installation activities relating to the foundation works come to a halt, but even when we ultimately made the decision to cease the retesting and repair effort in Vlissingen, the construction schedule was destroyed. Once we decided to restart the construction phase, we had to remobilize contractors (such as SEPAM) and procure vessels to perform the work, or modify existing vessel contracts to account for the delays. Because offshore work can generally only be performed during certain times of the year due to adverse weather in the North Sea, much of the work that we had planned to perform during the 2009 construction season could not even begin post-October 2009 (e.g. TP installation), or, if it could begin then, it was at a much higher cost to Fluor (e.g. MP installation).”
“Again, this is an example of evidence that bears the ring of firm recollection, not of a reconstruction of events based on carefully selected documents prepared by others. I therefore conclude that what Mr Dekker said in his witness statements in the arbitration reflected Fluor’s view of the position following the issue of the three NCRs. I do not accept the evidence to the contrary that Mr Dekker gave at the trial.”
“At that point (end of July 2009), there was still hope that, when Shipment 3 arrived in Vlissingen, it would not be subjected to an NCR and there would be a supply of TPs on which SEPAM could begin the fit-out works. Ultimately, that proved not to be the case, because shortly after Shipment 3 arrived on August 1st, GGOWL issued NCR 009, which required re-testing and repair of the Shipment 3 MPs and TPs as well. At that point, we were left with little choice but to demobilize SEPAM, except for a skeleton crew, which we utilized to perform miscellaneous support works for the NDT remediation efforts, such as monitoring of temporary power and lighting.”
“18. We proposed to Jumbo that they could take the period from the contractual early start date of 1st July through early August (10 August 2009 mentioned by Jumbo), to use the Javelin vessel for other work . . . The rationale behind this proposal was to eliminate the certain costs for standby time in July and early August, while securing the TP installation vessel in September when we were expecting to have sufficient TPs available and MPs installed . . . 19. When this proposal was developed and negotiated with Jumbo, we still anticipated that TPs would be available, and a sufficient number of MPs installed, to start TP installation on11 August 2009 , the date Jumbo would return from their “away period”
“TP installation commencing in a meaningful way before the departure of the Javelin on19 September 2009 became impossible with the issuance of NCRs 008 and 009. Although Jumbo had offered us the option of extending the Javelin through as late as15 November 2009 (and potentially beyond that date), we had no expectation at the time the offer was made on7 August 2009 that meaningful progress on MP installation would be made by that time, let alone TP installation.”
“Ongoing works on vessel in preparation for TP installation.”
“Jetting modifications to jack up legs completed.”
“General maintenance around The Leviathan.”
“Ballast for simulation trial for TP loadout”
“seafastening of all equipment complete certificate issued by LOC”
“7.3 The extent of the manufacturing fault could not be firmly established by ABB although the faulty transformers were consecutively numbered (ABB ID#9-12), which suggested a defective batch. The repaired transformers (the “first generation transformers”) were returned to Fluor in instalments. They had all been returned by9 November 2009 and thus the need to send them away had no impact on SEPAM’s progress. Because the repaired transformers were returned to Fluor in instalments, by the time SEPAM started fit-out of TPs in mid-October 2009, there were sufficient transformers on site for SEPAM to commence their works without experiencing delay. 7.4 Had the TP works in Vlissingen not been on hold, our decision would likely have been quite different, particularly given that only four transformers were found to have suffered from this particular problem. Since the transformers are all the same, in all likelihood, we would have proceeded with the installation of the remaining transformers in the TPs and the offshore installation of those TPs thereafter. Had any of the transformers showed signs of problems thereafter, or needed to be switched out, we could have made arrangements with ABB to switch out such transformers offshore. Although not ideal, it would have been quite feasible from a technical and construction schedule perspective, and, given that schedule was Fluor’s utmost priority, it is certain Fluor would have elected to do just that rather than holding up TP fit-out and installation.”
“Based upon a timing of events that this happened, and what was going on on the field from an installation standpoint, it was pretty much a straightforward decision.”
“there would have been a much more in-depth discussion about what do we do with the TPs that have transformers installed in them versus transformers that are still sitting on the ground.”
“If Fluor had been able to proceed with MP and TP installation in the summer of 2009 (i.e. if we were not prevented from doing so by the weld defects), I believe that Fluor management would not have made the decision to send the transformers back to ABB for repair. The reason is simple. By the time the issue was discovered in late August 2009 Fluor would have already installed 2-3 batches of TPs (i.e. 12-18 TPs). ABB’s report was then not received for several weeks after this. Fluor’s priority would have been to maintain the installation programme, even if this meant that it was likely that Fluor would have to swap out the bad transformers offshore at a later date and at an extra cost. The alternative would have been for Fluor to allow the Javelin (the TP installation vessel) to sit idle and pay enormous standby charges, which Fluor was obviously determined to avoid, and Fluor would have sought to recover the replacement costs from ABB in any event. Had we not returned the transformer (sic) to ABB in September 2009, the second transformer issue would never have arisen as this was caused by ABB’s own remedial works.”
“I must therefore leave open for further argument the issue of whether costs of testing or repairing any TPs was required - either expressly or by necessary implication - by any of the three NCRs and, if so, to what extent. This includes the question of whether or not it is open to Fluor to take this point.”
“. . . the examination results have to be re-validated and appropriate weld repairs made to ensure that all welds meet code requirements.”
“In the meantime we have instructed ZPMC to do d-scan only until we know more.”
“NCRs 006, 008 and 009 condemned all the TPs and all the MPs in Shipments 1, 2 and 3, which brought the construction phase of) this Project to a complete halt.”
“the enhanced testing and remediation of MP and TP welds it has been required to perform as a result of the acts and omissions of GGOWL, including, but not limited to, GGOWL’s issuance of NCR 006, 008 and 009 relating to MP welds.”
“. . . the issuance by GGOWL of the NCRs constitutes in the Tribunal’s view an effective direction for the Contractor to comply with its requirements for additional testing and repair about which the Contractor complains. The discussions between the Parties subsequent to NCR 006 made it clear that GGOWL would only accept D scanning at 12 db as adequate to clear the NCR, and that the retest and repair requirements extended to TPs as well as the MPs.”
“Peter, Please find attached our reports covering the visual and NDT inspections carried out in Vlissingen last week. I will use Ian’s NDT report supported by the RTD report as backup to the NCR. Regards Bob”
“Visual Inspection report 1st June 09”, “Monopile Underfill Locations” and “NDT Report Summary 1st June 09”
“Bruce, Please find attached initial documents re further NCR on Monopiles for discussion tomorrow morning 08:30 hrs, an up to date of (sic) NCR log is attached for completeness, you should also note that the power transformer failure is included. Peter”
“the examination results have to be re-validated and appropriate weld repairs made to ensure that all welds meet code requirements.”
“At some stage in June Mr Hardie had a conversation with a Mr Pashley, of GGOWL, to discuss what Fluor had to do in order to have the NCR released. Apart from providing the relevant paperwork in relation to the welds, Mr Pashley made it clear that Fluor would have to scan all the welds using D scanning. Mr Hardie said that it was not practicable to scan unground welds with the probe on the weld cap on account of the irregularity of the surface, but he was told that it could be done using copious amounts of couplant.”
“A. My view is the seed was planted here. I kept pushing back. What disturbed me about it is I had provided some input. In most cases if I provided a reasonable explanation the issue got closed. I think, however, in this case it would not go away. I had numerous discussions, you can see that in my witness statement, with Peter Reilly and others that: we want to re-test in Vlissingen, we want to re-test in Vlissingen. Then as soon as the re-tests occurred in Vlissingen, NCR hit us, so, at a minimum, the manifestation of it was in Vlissingen with the first NCR. Mr Grove: Mr Grove was a member of the Tribunal. So, in your view, it was a disguised direction right from the start? A. That is my view.”
“On5 June 2009 , I was tasked with developing the process to address NCR 006 and get it released. My first step was to find the equipment, facilities and labour needed to carry out this work. I immediately asked our procurement people to look into obtaining additional rollers from Bode Positioners to support the MPs. We had already procured one set of rollers from Bode to support the China NCR works . . .”
“He also would like Martin Hoskins [Hickson, I think he meant] NDT to also work alongside his NDT men and come to some agreement with regards to the best way of identifying the defects and the way to go ahead.”
“instructed Doug [Mr Hardie] to provide a copy of the ZPMC NDT procedure to QIS and to make clear to QIS that they were to test in accordance with that procedure . . ..”
“PB Inspection Report No 09IM027 (date 1st June 09) PB used RTD to UT inspect various, cap ground circ. welds, on the MPs: IGH 06, and IGI 04 . . . UT Inspection On Thurs 4 June, six UT operators, from QIS, began scanning the Circ. Welds of IGI 05, which were internally ground on the weld cap . . .”
“i) send David Thomas, Fluor’s level III, UT consultant, to ZPMC to perform a detailed review of all NDE activities associated with the GGOWF Project. vii) Get Sonovation to rapidly scan large volumes of weld, leaving detailed sizing by slower UT”
“From the start, in October 2009, I was directly involved in the negotiation of what became known as the “Early Start Agreement” with Jumbo, which allowed for a Jumbo vessel to return to the Project in March 2010 to commence TP installation. The decision as to which vessel to supply and use was made by Jumbo. Jumbo was pushing to start the installation of TPs as early as possible as they had vessel availability. While we considered bringing on the installation vessel earlier, a number of factors/concerns militated against it: (a) We were concerned that due to the cold weather the grout (used to connect the TP to the MP) would not have enough time to set properly during the weather window which would make the connection between the TP and MP less stable and susceptible to shifting in later or unforeseen adverse weather conditions and put Fluor at risk of having to correct the grout outside the weather window. (b) Also, even if we were able to get some of the TPs installed starting in February, we could not begin IA cable installation until early April 2010 (the date that the IA cable installation vessel was contracted to mobilise). Therefore, it did not seem to us to be reasonable or beneficial to expedite TP installation, only to have the TPs sit idle for two months (or more) before IA cable installation could begin.”
“The handling of MPs and TPs which could not be installed required very large additional storage areas and associated infrastructure (including crawler mats and gravel dykes, laying sand, gravel and specially made concrete supports for TPs). Fluor was forced to contract for additional self-propelled modular transporters (SPMTs) and cranes. The atmospherically-controlled warehouse was too small for the increased demands, and an additional warehouse was procured and air conditioning and atmospheric controls installed. Additional costs were incurred in respect of fork lift trucks and fuel for the additional generators required to provide power for the welding. As the number of subcontractors on site expanded dramatically, Fluor had to contract for additional storage, canteen and sanitary facilities to accommodate them and their materials, housed in a new contractor park. The division of the sums paid to VZT between works to MPs, TPs and site-wide costs (and various sub-categories of costs within those heads) is explained by Mr Ross in his first report.”
“Fluor’s Claim 9 is founded on an express connection between headcount for NDT and repair, and on the individuals who make up the claim. On the assumption that all those individuals are properly allocated to that claim, in my opinion the VBA should achieve a reasonable overall evaluation for that group of individuals.”
“I was informed by Fluor management around August 2008 that we needed a dive vessel to accommodate and support divers to carry out the installation of J-tubes required to enable the IA cables to enter and rise up the MPs before the TPs were placed on top of the MPs. Of course, we also needed the actual divers, and specialist supervision of the divers.”
“The point at which this became impossible was the arrival of defective Shipment 3 TPs in Period E. Effectively; from the moment that this Shipment arrived (1 August 2009 ) the demobilisation became inevitable. On this basis, on a proper analysis, the cost is one attributable to a cause in Period E and crystallised shortly after.”
“At that point (end of July 2009), there was still hope that, when Shipment 3 arrived in Vlissingen, it would not be subjected to an NCR and there would be a supply of TPs on which SEPAM could begin the fit-out works. Ultimately, that proved not to be the case, because shortly after Shipment 3 arrived on August 1st, GGOWL issued NCR 009, which required re-testing and repair of the Shipment 3 MPs and TPs as well. At that point, we were left with little choice but to demobilise SEPAM, except for a skeleton crew . . . ”
“GGOWL’s issuance of NCRs 006, 008 and 009, and its demands that Fluor change its NDT procedure and retest and repair welds previously tested, had a profound and devastating impact on the Project. Not only did all offshore installation activities relating to the foundation works come to a halt, but even when we ultimately made the decision to cease the retesting and repair effort in Vlissingen, the construction schedule was destroyed. Once we decided to restart the construction phase, we had to remobilise contractors (such as SEPAM) and procure vessels to perform the work, or modify existing vessel contracts to account for the delays.”
“Those days were lost because the defects in the TP welds meant that no TP installation vessels were able to complete the first TP String until17 March 2010 .”
“It was obvious to Fluor by mid-August 2009 that there would not be enough MPs actually installed to warrant a possible extension of the charter period of the TP installation vessel and its charter period ended on19 September 2009 . At this point the critical path moved into the TP installation.”
“4.2 The way the Project was originally resourced in China - shown in the organisation chart dated24 September 2008 - reflected the intention that Fluor would monitor ZPMC’s work at a high level. Accordingly, Fluor initially planned for a team of 12 personnel in total, comprising a welding engineer, a project coordinator and a team of inspectors from SQS, reporting to Jason Estabrook, the SQS Manager. In particular, ZPMC was responsible for quality control (“QC”) and Fluor would carry out quality assurance (“QA”) “spot checks”. 4.3 In the event, there were numerous and ongoing issues with the quality of ZPMC’s work so that it became necessary for Fluor to increase its QA team. Fluor progressively ramped up until, at its peak, the QA team numbered 132 inspectors from SQS (see the organisation chart dated19 September 2009 ).”
“In response to the discovery of defects in the welds in the MPs and TPs in Vlissingen, it was also necessary for Fluor to commit significant internal and subcontracted resources to undertake further NDT, as well as additional QA supervision/coordination, in respect of weld activities in Shanghai.”
“As must be apparent to ZPMC, the further NDT carried out on Shipments 4 to 8 included particularly D scans on welds. ZPMC carried out D scans, and Fluor incurred expense in overseeing that, because it had become apparent to ZPMC and to Fluor that E scans were insufficient to detect transfers defects in welds.”
“Indirect and/or consequential damages, or whatever the cause may be shall be explicitly excluded from this Purchase Order.”
“What is the recoverable quantum of (a) the historical costs and (b) the future monitoring and testing costs? GGOWL’s case is that it is entitled to (a) the historical costs of£19,868,927.61 plus€546,224.58 ; and (b) the costs of the proposed monitoring and testing regime at a cost of£44,233,706 (net present value) as damages by reason of: (a) Fluor’s breach of contract in manufacturing the structures with weld defects; (b) Fluor’s breach of contract in failing to repair the defects discovered in Vlissingen or to produce ECAs to justify non-repair; (c) Fluor’s breach of contract in installing the structures offshore in October 2009 in a defective state; (d) Fluor’s breach of contract in prohibiting GGOWL from carrying out further testing of the structures from August 2009 onwards; (e) Fluor’s breach of contract in failing to carry out offshore inspection and testing of the structures as instructed by GGOWL or to agree to joint testing.”
“That [the payment into court] has to be taken into account in some way seems to me to be beyond doubt and it is, of course, always open to a plaintiff who wishes to accept a payment in or thinks that its acceptance may cause him some embarrassment in the matter of apportionment to request an amendment of the notice of payment in to apportion the sum paid among the causes of action in respect of which it is paid. In the ordinary way that would, I think solve any difficulty, though I would like to reserve the position - which of course does not arise here - where there may be grounds for asserting that the apportionment is collusive or not made bona fide. Where, however, the party who has to bring the money into account himself provides no material to show how any apportionment should be made (or, as in this case, invites the judge to deal with it in a particular way) the judge has to do his best with what material he has, and the only material he had in this case was the claims themselves. What he had to ascertain was what the plaintiffs had lost, and to what extent that loss had been mitigated or satisfied by what had been received. There was really no other reliable way of doing this except by assessing the true value of the plaintiff’s claim against [the contractor], and comparing it with the£30,000 received.”
“Unless the claim is of sufficient strength reasonably to justify a settlement and the amount paid in settlement is reasonable having regard to the strength of the claim, it cannot be shown that the loss has been caused by the relevant eventuality or breach of contract. That is not to say that unless it can be shown that the claim is likely to succeed it will be impossible to establish that it was reasonable to settle it. There may be many claims which appear to be intrinsically weak but which, common prudence suggests should be settled in order to avoid the uncertainties and expenses of litigation. Even the successful defence of a claim in complex litigation is likely to involve substantial irrecoverable costs. It is thus an every day event for shipowners or their P&I clubs to settle cargo damage claims based on allegations of bad stowage or unseaworthiness for well under 50% of the claim when the alternative explanation of the damage is the inherent condition of the goods or some other cause for which owners are not liable. Unless it appears on the evidence that the claim is so weak that no reasonable owner or club would take it sufficiently seriously to negotiate any settlement involving payment, it cannot be said that the loss attributable to a reasonable settlement was not caused by the breach by reason of which the goods are in a damaged condition.”
“Where a settlement agreement does allocate sums to particular claims or causes of action, that will not necessarily be conclusive. The court will look behind the form or words used in a global settlement to ascertain the underlying position and to ensure that third parties’ rights are not unjustly affected.”
“GGOWL last offer 1. GGOWL to pay£41.6M for outstanding milestone payments (inclusive of interest) plus£1.5M for agreed VOs. 2. Fluor to provide an Extended Warranty in the form of an extension to GGOWL’s rights under the BOP Contract. 3. Fluor to pay£21M for inspection and monitoring costs (to be paid as incurred, on a 75/25 basis as between Fluor and GGOWL, capped at£28M at 2013 prices) 4. Fluor to complete the remediation of the Transformers, Tekmar Seals and Met Mast Defects plus other undisputed Defects and snagging 5. Fluor to pay GGOWL£30.35M to settle GGOWL claims for: legal costs (10.85), Siemens claims (7.0), other project claims (2.5) and historic Weld Dispute costs (10.0) 6. GGOWL to pay Fluor£9.75M to settle Fluor claims for: Harwich (2.95), Adverse weather (1.8) and other Project claims (5.0) Fluor last offer 1. GGOWL to pay£41.6M for outstanding milestone payments (inclusive of interest) plus£1.5M for agreed VOs. 2. Fluor to provide an Extended Warranty in the form of an extension to GGOWL’s rights under the BOP Contract. 3. Fluor to reimburse GGOWL up to 100% of any inspection and monitoring costs incurred up to a cap of£28M on the occurrence of any valid claim under the Extended Warranty. 4. The parties walk-away on their Project Claims. 5. Fluor to rectify the Transformers, Tekmar Seals and Met Mast defects and GGOWL to complete the balance of defects and snagging in return for a payment from Fluor of£10M .”
“4. Fluor will pay GGOWL the sum of£26 million in full satisfaction of all GGOWL’s claims, including but not limited to, the legal fees, Siemens Delay Claim, Historic Costs, Esbjerg Claim, WTG Storage, etc 5. GGOWL will assume responsibility for completion of all work remaining on the Project, including but not limited to, warranty claims and snagging matters and Fluor shall have no further responsibility [or] liability for such work. 6. . . . 7. . . . 8. The parties will cooperate in the structuring of the final settlement agreement so as to satisfy their respective internal accounting, tax, and other requirements. 9. Except as provided herein, neither party will have any obligation whatsoever . . .”
“… in full and final settlement of the following: .1 all legal costs incurred by GGOWL in relation to the Claims and the Proceedings; .2 [the Siemens claims]; .3 all costs incurred in relation to [the disputed defects and snagging items set out in Schedule [ ] of this agreement; .4 [all historic costs]”
“.1 the Fluor claim for delay for the Harwich work stoppage . . . .2 [adverse weather] .3 [other Project claims].” .4 [all historic costs]” .2 [adverse weather] .3 [other Project claims].”
“1. DEFINITIONS … “Claims” means (in each case whether past, present, future, known and/or unknown, but subject to clauses 3.4 and 12.1) all and any actions, causes of action, claims, liabilities, obligations, claims for costs or expenses (including but not limited to legal fees and disbursements), damages, losses and demands of whatever nature which relate to and/or arise out of the Project and/or out of the Proceedings; … “Proceedings” means the legal action commenced by Fluor against GGOWL under claim number 111822 in the LCIA and the counterclaim brought by GGOWL against Fluor under claim number 111822 also in the LCIA; “Project” means the project for the design, construction and operation of the Greater Gabbard Offshore Wind Farm; … 3. SETTLEMENT 3.1 The parties agree to settle the Claims and Proceedings and any further obligations and/or liabilities arising in relation to the BOP Contract and the Project, on a full and final basis on the terms of: 3.1.1 this agreement; and 3.1.2 the Extended Warranty Deed. … 5. PAYMENTS DUE FROM GGOWL TO FLUOR 5.1 GGOWL shall pay Fluor (collectively the “GGOWL Payments”): 5.1.1 the sum of£41,600,000 (forty one million, six hundred thousand pounds) including interest but excluding VAT (the “Milestone Payment Sum”); and 5.1.2 the sum of£1,050,000 (one million and fifty thousand pounds) including interest but excluding VAT (the “Variation Order Sum”) and; 5.1.3 the sum of£3,009,198 (three million, nine thousand and one hundred and ninety eight pounds) being the VAT payable on the sums in sub-clauses 5.1.1 to 5.1.2 (inclusive) above 5.2 GGOWL shall make the GGOWL Payments subject to and in accordance with clause 7 of this agreement. 6. FLUOR PAYMENT 6.1 Fluor shall pay GGOWL the sum of£32,325,000 (thirty two million, three hundred and twenty five thousand pounds) (the “Counter Claim Damages”). 6.2 Fluor will pay the Counter Claim Damages subject to and in accordance with clause 7 of this agreement. 7. PAYMENT ARRANGEMENTS 7.1 The parties acknowledge and agree that within 60 days of this agreement: 7.1.1 GGOWL is due to pay to Fluor the GGOWL Payments … 7.1.2 Fluor is due to pay to GGOWL the Counter Claim Damages … 7.2 The payments in clause 7.1 can be set off against each other, such that the only payment to be made within 60 days of this agreement is the payment by GGOWL to Fluor of£10,325,000 … plus VAT of£3,009,198 …. (the “Net Payment”). … 8. COMPLETION OF OUTSTANDING WORKS AND DEFECTS 8.1 GGOWL shall following the date of this agreement assume responsibility for the Works (as defined in the BOP Contract) and for completion of any outstanding works relating to the BOP Contract (the “Outstanding Works”) and for the remedying of any outstanding defects in the Works (as defined in the BOP Contract) (the “Outstanding Defects”) and for the completion and continuing operation of any obligations owed to Competent Authorities with jurisdiction or authority in relation to the Project. … 9. EXTENDED WARRANTY Upon the date of this agreement the parties shall each deliver to the other the Extended Warranty Deed, fully executed and unconditionally released. … 11. WITHDRAWAL OF THE PROCEEDINGS 11.1 The parties acknowledge the decisions, awards and findings of the Tribunal on all matters decided by the Tribunal in relation to the Proceedings. The parties shall not in any future claim or proceedings seek to re-open or challenge any decisions, awards or findings of the Tribunal in relation to the Proceedings. 11.2 The parties agree within 14 (fourteen) days of the date of this agreement to issue a letter to the Tribunal appointed in relation to the Proceedings confirming that the Tribunal is released from its appointment, and that no further award will be made by the Tribunal in relation to the Proceedings. 11.3 Each party agrees to pay 50% (fifty per cent) of any outstanding fees and expenses of the Tribunal, the LCIA, IDRC and other costs of the Proceedings such as transcription costs, that are not covered by the payments on account of the Tribunal’s fees and expenses that have already been made to the LCIA. The parties agree that will be no order as [to] costs in relation to the Proceedings. 12. RELEASE 12.1 In consideration of the terms and conditions of this agreement and the terms of the Extended Warranty Deed, the parties agree to waive and unconditionally and forever release each other, their parents, subsidiaries, affiliates and associate companies (included but not limited to their respective directors, officers, employees, agents, successors, assigns and heirs) from the Claims, from the Proceedings and from any further obligations and/or liabilities arising in relation to the BOP Contract and the Project, but any such waiver and release does not take away the rights of the parties to enforce (i) the obligations set out in this agreement (ii) the obligations and warranties set out in the Extended Warranty Deed and (iii) the indemnities set out in clause 17.1 of the BOP Contract.” … “Claims” means (in each case whether past, present, future, known and/or unknown, but subject to clauses 3.4 and 12.1) all and any actions, causes of action, claims, liabilities, obligations, claims for costs or expenses (including but not limited to legal fees and disbursements), damages, losses and demands of whatever nature which relate to and/or arise out of the Project and/or out of the Proceedings; … “Proceedings” means the legal action commenced by Fluor against GGOWL under claim number 111822 in the LCIA and the counterclaim brought by GGOWL against Fluor under claim number 111822 also in the LCIA; “Project” means the project for the design, construction and operation of the Greater Gabbard Offshore Wind Farm; 3.1 The parties agree to settle the Claims and Proceedings and any further obligations and/or liabilities arising in relation to the BOP Contract and the Project, on a full and final basis on the terms of: 3.1.1 this agreement; and 3.1.2 the Extended Warranty Deed. 5.1 GGOWL shall pay Fluor (collectively the “GGOWL Payments”): 5.1.1 the sum of£41,600,000 (forty one million, six hundred thousand pounds) including interest but excluding VAT (the “Milestone Payment Sum”); and 5.1.2 the sum of£1,050,000 (one million and fifty thousand pounds) including interest but excluding VAT (the “Variation Order Sum”) and; 5.1.3 the sum of£3,009,198 (three million, nine thousand and one hundred and ninety eight pounds) being the VAT payable on the sums in sub-clauses 5.1.1 to 5.1.2 (inclusive) above 5.2 GGOWL shall make the GGOWL Payments subject to and in accordance with clause 7 of this agreement. 6.1 Fluor shall pay GGOWL the sum of£32,325,000 (thirty two million, three hundred and twenty five thousand pounds) (the “Counter Claim Damages”). 6.2 Fluor will pay the Counter Claim Damages subject to and in accordance with clause 7 of this agreement. 7.1 The parties acknowledge and agree that within 60 days of this agreement: 7.1.1 GGOWL is due to pay to Fluor the GGOWL Payments … 7.1.2 Fluor is due to pay to GGOWL the Counter Claim Damages … 7.2 The payments in clause 7.1 can be set off against each other, such that the only payment to be made within 60 days of this agreement is the payment by GGOWL to Fluor of£10,325,000 … plus VAT of£3,009,198 …. (the “Net Payment”). 8.1 GGOWL shall following the date of this agreement assume responsibility for the Works (as defined in the BOP Contract) and for completion of any outstanding works relating to the BOP Contract (the “Outstanding Works”) and for the remedying of any outstanding defects in the Works (as defined in the BOP Contract) (the “Outstanding Defects”) and for the completion and continuing operation of any obligations owed to Competent Authorities with jurisdiction or authority in relation to the Project. Upon the date of this agreement the parties shall each deliver to the other the Extended Warranty Deed, fully executed and unconditionally released. 11.1 The parties acknowledge the decisions, awards and findings of the Tribunal on all matters decided by the Tribunal in relation to the Proceedings. The parties shall not in any future claim or proceedings seek to re-open or challenge any decisions, awards or findings of the Tribunal in relation to the Proceedings. 11.2 The parties agree within 14 (fourteen) days of the date of this agreement to issue a letter to the Tribunal appointed in relation to the Proceedings confirming that the Tribunal is released from its appointment, and that no further award will be made by the Tribunal in relation to the Proceedings. 11.3 Each party agrees to pay 50% (fifty per cent) of any outstanding fees and expenses of the Tribunal, the LCIA, IDRC and other costs of the Proceedings such as transcription costs, that are not covered by the payments on account of the Tribunal’s fees and expenses that have already been made to the LCIA. The parties agree that will be no order as [to] costs in relation to the Proceedings. 12.1 In consideration of the terms and conditions of this agreement and the terms of the Extended Warranty Deed, the parties agree to waive and unconditionally and forever release each other, their parents, subsidiaries, affiliates and associate companies (included but not limited to their respective directors, officers, employees, agents, successors, assigns and heirs) from the Claims, from the Proceedings and from any further obligations and/or liabilities arising in relation to the BOP Contract and the Project, but any such waiver and release does not take away the rights of the parties to enforce (i) the obligations set out in this agreement (ii) the obligations and warranties set out in the Extended Warranty Deed and (iii) the indemnities set out in clause 17.1 of the BOP Contract.”
“And no doubt if other numbers hadn’t been right, then the extended warranty just by itself wouldn’t have been acceptable [to GGOWL] because it had to be supported by other payments or settlements across the board. Is that right? A My lord, you hit it right on the head. The reason why the amounts seemed to go up in terms of cash was because they were not satisfied with the amounts contingent in the warranty.”
“Q So Fluor’s position was that it only wanted a mediation if there was a complete global settlement of all outstanding issues, correct? A A global settlement is what I desired as well. Q This would include all of its possible claims? A If we could sweep up and offer our claims and their claims as well as the litigation risk and put a price on it that was acceptable to GGOWL, that would be a good settlement.”
“Because of the occasions, circumstances and developments that occurred in the middle of April.”
“A There is a process under which it was increased to 32 million, which is the important ingredient that is missing from the April 9th communication. Q What is that ingredient? A There was a recognition, a realisation, some time in the middle of April, that what was contemplated with respect to the warranty was much different, if not completely different, by Gabbard and Fluor. We had to have the warranty with issues of trigger and breadth such that it would not be valued currently or it might trigger a loss. Gabbard’s position was that there was going to be an easy access to the 28 million by virtue of an easier trigger, and that it would be extrapolated across the entire . . . Q Yes, the extrapolation issue. A . . . 32 if one [MP] failed. So that was a sea change some time in the middle of April. Q What has that to do with increasing the offer from 25 (sic) to 32 million? A Once we got a more limited warranty negotiated, GGOWL wanted an increased amount of money upfront, and that is when the particularisation that you have shown me in the April 9th communication broke down and it became just dollars being traded.”
“Over the course of those four years, Fluor engaged the team of external experts identified in section 5 below. Those experts were primarily engaged to support Fluor’s efforts to obtain satisfactory ECAs to justify installing the structures with unrepaired defects and, later, in defending the counterclaim.”
“Fluor continued with the ECA work long after taking the decision to ignore the NCRs because it had (1) to defend its decision to install against GGOWL’s allegations regarding structural integrity (which eventually evolved into its counterclaim) and (2) to protect its reputation in the market, particularly with regard to having decided to install a product with known defects.”
“502 Acceptance of defects exceeding the given limits may be granted based on fracture mechanics testing and appropriate calculations. If this approach is considered, the inherent inaccuracy of the NDT methods shall be considered when the critical defect size is determined.”
“In my view, this evidence clearly establishes that, as a result of the cracking that had been found in the piles at Vlissingen, the only reasonable option available to Fluor was to carry out an investigation into the true condition of the piles and to establish the extent (if any) to which this might affect their performance in service.”
“As a result of the presence of this cracking the MPs and TPs on delivery at Vlissingen were not fit for the purpose of being installed forthwith without either further examination, testing and repair or a satisfactory Engineering Critical Assessment indicating that repairs were not necessary and that the MPs and TPs would, from a structural point of view, perform satisfactorily in service for 25 years.”
“There can be no doubt that by this time ZPMC’s welding, as Respondent well knows, was directly at issue between the parties. Respondent had already rejected Shipment #1 on3 June 2009 due to welding issues, causing Claimant to seek damages that, at that time, it contemplated recovering against ZPMC through the legal process. To that end, Claimant then directed first TWI, and later Jan Ibsoe, to perform certain tasks and prepare reports to be utilised for the dominant purpose of substantiating the legal claims that Claimant was then contemplating asserting against ZPMC, which claims were later re-directed to Respondent as a result of Fluor’s determination that the Employer Required NDT and Remediation and the NCRs issued by Respondent were without justification . . .”
“In addition, it must be noted that this issue and the other set forth by Claimant (i.e. the relevance and admissibility of all weld NDT data) are still in dispute solely because Respondent wrongly refuses to acknowledge that the issue of the structural integrity of the foundation works is and always has been at issue in this case as it is presently pleaded.”
“In general terms the purpose of an ECA is to seek to establish whether indications/defects jeopardise the structural integrity or design life of a structure. This was in fact the purpose or at the very least one purpose of the ECAs undertaken by Fluor as can be seen from the contemporaneous correspondence and Fluor’s Amended Statement of Case . . .”
“To that end, the claimant then directed first TWI, and later Jan Ibsoe to perform certain tasks and prepare reports to be utilised for the dominant purpose of substantiating the legal claims that the claimant was then contemplating against ZPMC . . . Regardless of the fact that the Claimant’s litigation against ZPMC did not ultimately materialise and Fluor instead pursued arbitration against Gabbard, the fact remains that the draft reports now being sought by the respondent were prepared in contemplation of litigation and are accordingly subject to the protections of the litigation privilege . . . The Welding Institute’s role changed such that by mid-June 2009, as detailed above, it was actively engaged in providing the claimant with technical substantiation for its then contemplated claims against ZPMC. Additionally, the Respondent’s characterisation of TWI and Ibsoe as “technical advisers” rather than “experts” is both incorrect and immaterial. The critical point is at the time they prepared their reports, regardless of the label the respondent ascribed to them, such reports were prepared for the dominant purpose of substantiating claimant’s legal claims which at first contemplated by ZPMC but were later re-directed to Gabbard once Fluor determined that the NCRs were not justified.”
“A Structural integrity was not necessary to prove Fluor’s case against GGOWL in the arbitration. What happened is there was a notice of counterclaim in July, I believe it is 2011, and later a notice of a counterclaim not specified, and then finally a counterclaim. And I do recall a great concern about getting ambushed in the arbitration because all of the allegations of the counterclaim had been made right before the arbitration on the claim. There were two problems, I guess. One is ambush and the other is splitting a case in the arbitration and having the counterclaim go later. Q But it was part of its case, Fluor’s case, in support of the claim, that the work of testing and repair was not technically necessary because the MPs and TPs were structurally sound without being repaired. Do you remember that? A No.”
"If the Court concludes that the documents that came into existence after1 October 2009 were created for the dominant purpose of pursuing litigation against GGOWL, does this mean that no costs are recoverable at all in respect of the relevant reports and legal assistance or, alternatively, is Fluor entitled to recover only a proportion. If the latter, what is the appropriate approach?"
“Subject to Clauses 8.7 (Rate of Progress) and 17.4 (Limitation of Liability), if the Contractor fails to comply with clause 8.2 (Time for Infrastructure Commissioning) and/or Clause 8.3 (Time for WTG Foundation Works Commissioning), the Contractor shall be liable for and shall pay every 10 Business Days or allow on demand liquidated damages to the Employer: (i) in respect of the Phase 1 Infrastructure Works, at the rate of 900 Pounds Sterling per MW per day in respect of the aggregate of the Rated Power Output of each WTG, in relation to which a WTG Foundation Works Commissioning Certificate should have been issued according to the Construction Programme, to the extent that power from each such WTG cannot be exported due to a failure by the Contractor to commission the Phase 1 Infrastructure Works by the Phase 1 Target Infrastructure Commissioning Date, on each day from the Phase 1 Target Infrastructure Commissioning Date up to and including the Phase 1 Infrastructure Commissioning Date; (ii) at the rate of . . . in relation to which the WTG Foundation Works Commissioning Certificates have not been issued, for each day from the Phase 1 Target WTG Foundation Works Commissioning Date up to and including the Phase 1 WTG Foundation Works Commissioning Date; (iii) in respect of the Phase 2 Infrastructure Works, at the rate of . . . in relation to which a WTG Foundation Works Commissioning Certificate should have been issued according to the Construction Programme, to the extent that power from each such WTG cannot be exported due to a failure by the Contractor to commission the Phase 2 Infrastructure Works by the Phase 2 Target Infrastructure Commissioning Date, on each day from the Phase 2 Target Infrastructure Commissioning Date up to and including the Phase 2 Infrastructure Commissioning Date; and (iv) at the rate of . . . in relation to which WTG Foundation Works Commissioning Certificates have not been issued, for each day from the Phase 2 Target WTG Foundation Works Commissioning Date up to and including the Phase 2 WTG Foundation Works Commissioning Date, provided that no liquidated damages shall be payable by the Contractor to the Employer under Clause 8.8.1 (ii) and 8.8.1 (iv) in respect of any WTG following the issue of a WTG Foundation Works Commissioning Certificate in relation to that utility.”
“29.2.1 GGOWL was entitled to levy LDs under Clause 8.8 of the BoP Contract [2.2/442]. Insofar as it wished to do so, it was required to give notice as soon as reasonably practicable and not later than 21 days after becoming aware of the event or circumstance giving rise to the claim (see Clause 2.4.2 at [2.2/406]). 29.2.2. GGOWL did elect to levy LDs, and provided notice of its claim by correspondence within the trial bundle. The letter relevant to this claim was dated23 July 2010 and is contained in the trial bundle at [18.13A/5087]. It notified Fluor that GGOWL was levying LDs in respect of the Phase 1 Foundation Milestone (i.e. that which Fluor alleges was delayed by ZPMC's breaches) from the date that the milestone had been missed (1 May 2010 ) onwards to the date of the letter (a total of 84 days). The LDs levied in respect of this milestone were notified in the sum of£14,259,483 . 29.2.3. ZPMC is correct that LDs accrued against the Phase 1 Infrastructure Milestone prior to this (¶33 of its most recent note) but neglects to mention that GGOWL did not seek to levy them from the point that the Phase 1 [Infrastructure] Milestone was missed and instead levied LDs in respect of the Phase 1 Foundations Milestone. At the time that it did so, only£12,696,912 of LDs had been levied (i.e. only c25% of the cap was exhausted). 29.2.4. So the actual position is that GGOWL did in fact levy LDs against Fluor in respect of the very milestone to which ZPMC caused delay.”