“This section covers the method of managing the payment amount determination, invoicing, and required support information to provide payment to the Subcontractor for the Subcontract Work.”
“Further, it [Symbion] argues that even if there was no pay-if-paid modification, the onus is on the Claimant [Venco] to prove the value of the work it carried out. It says that the Claimant has failed to discharge this burden and therefore no damages should be awarded. By contrast, the Claimant denies that it agreed any pay-if-paid modification. ….. Further the Claimant contends that it had sufficiently proved the value of the works in respect of which it is claiming payment.”
“Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant – … (d) failure by the Tribunal to deal with all the issues that were put to it. …”
“(g)(i) There must be a “failure by the tribunal to deal” with all of the “issues” that were “put” to it. (ii) There is a distinction to be drawn between “issues” on the one hand and “arguments”, “points”, “lines of reasoning” or “steps” in an argument, although it can be difficult to decide quite where the line demarking issues from arguments falls. However, the authorities demonstrate a consistent concern that this question is approached so as to maintain a “high threshold” that has been said to be required for establishing a serious irregularity […]. (iii) While there is no expressed statutory requirement that the Section 68(2)(d) issue must be “essential”, “key” or “crucial”, a matter will constitute an “issue” where the whole of the applicant's claim could have depended upon how it was resolved, such that “fairness demanded” that the question be dealt with […]. (iv) However, there will be a failure to deal with an “issue” where the determination of that “issue” is essential to the decision reached in the award […]. An essential issue arises in this context where the decision cannot be justified as a particular key issue has not been decided which is critical to the result and there has not been a decision on all the issues necessary to resolve the dispute or disputes […]. (v) The issue must have been put to the tribunal as an issue and in the same terms as is complained about in the Section 68(2) application […]. (vi) If the tribunal has dealt with the issue in any way, Section 68(2)(d) is inapplicable and that is the end of the enquiry […]; it does not matter for the purposes of Section 68(2)(d) that the tribunal has dealt with it well, badly or indifferently. (vii) It matters not that the tribunal might have done things differently or expressed its conclusions on the essential issues at greater length […]. (viii) A failure to provide any or any sufficient reasons for the decision is not the same as failing to deal with an issue […]. A failure by a tribunal to set out each step by which they reach its conclusion or deal with each point made by a party is not a failure to deal with an issue that was put to it […]. (ix) There is not a failure to deal with an issue where arbitrators have misdirected themselves on the facts or drew from the primary facts unjustified inferences […]. The fact that the reasoning is wrong does not as such ground a complaint under Section 68(2)(d) […]. (x) A tribunal does not fail to deal with issues if it does not answer every question that qualifies as an “issue”
“[Venco’s] Statement of Claim assumes that the value of its work is conclusively established by its invoices..... the value of the work performed by [Venco] was subject to continuing re-evaluation by Symbion until the end of the project. As such, it is [Venco’s] burden to prove the value of its works and its invoices are not conclusive evidence.” (ii) Whatever Venco had said, therefore, does not appear to have been an assertion of conclusivity. This was at best what Symbion assumed Venco was saying and Symbion’s response was focussed on the point that Venco still had the burden of proving the value of its works. (iii) In its pre-hearing Responsive Memorial, Venco argued that “even if Symbion had grounds to challenge [Venco’s] invoices at the time, which [Venco] denies, Symbion’s chance to challenge [Venco’s] invoices is long past under the terms of the Subcontract.”
“(1) The Tribunal failed to deal with Symbion’s argument regarding the express provisions of the Subcontract as to the evidential value of the documents relied on by Venco. (2) The Tribunal failed to deal with Symbion’s submission regarding Venco’s obligation to submit “supporting documents showing in detail in a form approved by [Symbion] the value of all work done in accordance with the [Subcontract]” when seeking final payment.”
“There can be no reasonable argument that the issues sought be precluded are (sic) the same issues as in the prior arbitration. Specifically …. these issues include: • the payment procedures and the right to ongoing reassessment of the value of work until the end of the project…. • the oral modification of the BOP Subcontract to provide that Symbion was not required to pay its subcontractors until after receiving payment from [the JV] …. • Symbion’s payment of invoices that [Venco] claims were unpaid as of January and April 2009; • Symbion’s performance of its duties under the BOP Subcontract”
“So we, the arbitration panel, agree that there are not perfect parallels between what was being litigated in the prior arbitration and this one. Different contract, different facts, different agreements, different scopes of work. All that is going to have to be taken into account.”
“Symbion’s final defence was that there was binding, or in the alternative, highly persuasive evidence before the Tribunal that the work (including procurement) for which Venco sought payment in this Arbitration had not been performed or was of a value far less than claimed by Venco in the Arbitration.”
“In particular, there was binding, or in the alternative, highly persuasive authority before the Tribunal within the Prior Award that Venco’s evidence pertaining to the value of the work performed was, under the terms of the Venco Subcontract, insufficient.”
“HIGHLY CONFIDENTIAL: NOT TO BE USED IN THE ARBITRATION”
“40 … At the one end is the arbitration itself and at the other an order following a reasoned judgment under section 68. In between is the hearing under section 68. An order will normally give very limited information … even a section 68 hearing is likely to cover only limited aspects of the subject matter of the original arbitration … A reasoned judgment under section 68 will in likelihood disclose very much less about the subject matter of the arbitration than will have been covered during the section 68 hearing itself. Moreover, judges framing judgments are accustomed to concentrate on essentials, to avoid where possible unnecessary disclosure of sensitive material and in some cases to anonymise. … 41. When weighing the factors, a judge has to consider primarily the interest of the parties in the litigation before him or in other pending or imminent proceedings. … The concerns or fears of other parties cannot be a dominant consideration. Nor can there be any serious risk of their being deterred from arbitrating in England, if the court weighs the relevant factors appropriately. If, in the absence of other good reason for publication the court withholds publication where a party before it would suffer some real prejudice from publication or where the publication would disclose matters by the confidentiality of which one or both parties have set significant store, but publishes its judgments in other cases, businessmen can be confident that their privacy and confidentiality in arbitration will, where appropriate, be preserved. The limited but necessary interface between arbitration and the public court system means that more cannot be expected. There can be no question of withholding publication of reasoned judgments on a blanket basis of a generalised, and in my view, unfounded, concern that their publication would upset the confidence of the business community in English arbitration.”