“13. COMPLETION DATES 13.1 The CONTRACTOR shall comply with the following dates fulfilling with all the conditions established in this Contract STEEL STRUCTURE END OF ERECTION DATE BUILDING Unit 1 Unit 2 TURBINE HALL01/02/2014 01/03/2014 ELECTRICAL MODULES10/03/2014 10/04/2014 FEED WATER28/02/2014 03/03/2014 OTC11/01/2014 15/02/2014 HRSG ENCLOSURE17/07/2014 16/08/2014 PLATFORMS09/04/2014 08/05/2014 ”
“With reference to the revised delivery schedule noted below we confirm that we can achieve these dates subject to the following parameters been achieved by the Design/Construction Team; 1. All Design Information [Full Construction Drawings with Design Loads] issued to us by 19th August for the following elements - • Turbine Building 1 [Connection details for Internal Platforms to Main Frame also required to insure details are incorporated into Main Frame] • Electrical Module 1 • OTC 1 2. All Design information [Full Construction Drawings with Design Loads] issued to us by 2nd September for the following elements - • Turbine Building 2 [Connection details as noted in item 1 above also required] • Electrical Module 2 • OTC 2 • Feedwater 1 • Platforms l & 2. 3. All Design information [Full Construction Drawings with Design Loads] issued to us by 9th September for the following elements - • Feedwater 2 4. All Design information [Full Construction Drawings with Design Loads] issued to us by6th January 2014 for the following elements - • HRSG Enclosure l • HRSG Enclosure 2” • Turbine Building 1 [Connection details for Internal Platforms to Main Frame also required to insure details are incorporated into Main Frame] • Electrical Module 1 • OTC 1 • Turbine Building 2 [Connection details as noted in item 1 above also required] • Electrical Module 2 • OTC 2 • Feedwater 1 • Platforms l & 2. • Feedwater 2 • HRSG Enclosure l • HRSG Enclosure 2”
“The CONTRACTOR may only request changes to the Completion Dates when the following circumstances occur: (i) a cause of Force Majeure that affects any Completion Dates or (ii) suspension of the Contract by order of the BUYER or (iii) any act of prevention or default of the BUYER, or (iv) deferment of the giving of possession of the Site or any part thereof as needed to perform the Scope and provided that CONTRACTOR has fulfilled all the conditions required for such access, or (v) modifications to the Scope pursuant to clause 12, or (vi) any strike at the Site, other than strikes of CONTRACTOR’s personnel and/or subcontractors, that directly impacts performance of CONTRACTOR’s Scope or(vii) in case of CONTRACTOR’s suspension In accordance to clause 15.6 or (viii) in the other cases expressly established in this Contract.”
“In my opinion, SUK could not reasonably have completed the steel structure works in the Units any earlier than the identified Complete Steel Structure Erection date in the table below [the table set out at paragraph 46 above] taking into account all of the circumstances that it encountered including the access issues caused by DF, the increased scope, the change circumstances in respect of the site logistics and the variation works required by DF.”
“…so peculiar, so unexpected, and so different from what any person reckoned or calculated upon, that it is not within the contract at all; then, it appears to me, one of two courses might have been open to him; he might have said: I entirely refuse to go on with the contract…or he might have said, I will go on with this, but this is not the kind of extra work contemplated by the contract, and if I do it, I must be paid a quantum meruit for it.”