“HZI gives ICL notice pursuant to Clause 43.1(h) and/or 43.1(q) of the Conditions of Contract (“Conditions”), that HZI hereby forthwith terminates the employment of ICL under Clause 43.1 of the Contract. For the avoidance of doubt, HZI does not exercise its discretion to provide a 7 day period for rectification under Clause 43.1A of the Conditions.”
“HZI is entitled to and hereby does terminate the employment of ICL under the Contract on all or any of the grounds set out in this notice. Such termination is without prejudice to any other rights or remedies which HZI may possess under the Contract or at law. … In the meantime, all of HZI’s rights and remedies remain fully reserved.”
“This letter constitutes notice that ICL exercises its common law right to accept HZI’s repudiation of the Contract and accordingly treats the Contract as terminated.”
“It was a condition precedent to HZI having the right to terminate pursuant to Sub-Clauses 43.1(h) and 43.1(q) that HZI first issue a notice pursuant to Sub-Clause 43.1A and allow ICL a seven day period in which to commence and diligently pursue the rectification of the default that was the subject of that notice.”
“[10] The court’s task is to ascertain the objective meaning of the language which the parties have chosen to express their agreement. It has long been accepted that this is not a literalist exercise focused solely on a parsing of the wording of the particular clause but that the court must consider the contract as a whole and, depending on the nature, formality and quality of drafting of the contract, give more or less weight to elements of the wider context in reaching its view as to its objective meaning. … [11] …. Interpretation is, as Lord Clarke stated in Rainy Sky (at [21)], a unitary exercise; where there are rival meanings, the court can give weight to the implications of rival constructions by reaching a view as to which construction is more consistent with business common sense, But, in striking a balance between the indications given by the language and the implications of the competing constructions the court must consider the quality of the drafting of the clause … and it must be alive to the possibility that one side may have agreed to something which with hindsight did not serve his interest …. Similarly, the court must not lose sight of the possibility that a provision may be a negotiated compromise or that the negotiators were not able to agree more precise terms. [12] This unitary exercise involves an iterative process by which each suggested interpretation is checked against the provisions of the contract and its commercial consequences are investigated …. … [13] Textualism and contextualism are not conflicting paradigms in a battle for exclusive occupation of the field of contractual interpretation. Rather, the lawyers and the judge, when interpreting any contract, can use them as tools to ascertain the objective meaning of the language which the parties have chosen to express their agreement The extent to which each tool will assist the court in its task will vary according to the circumstances of the particular agreement or agreements. Some agreement may be successfully interpreted principally by textual analysis, for example because of their sophistication or complexity and because they have been negotiated and prepared with the assistance of skilled professionals. The correct interpretation of other contracts may be achieved by a greater emphasis on the factual matrix, for example, because of their informality, brevity or the absence of skilled professional assistance. But negotiators of complex formal contracts may often not achieve a logical and coherent text because of, for example, the conflicting aims of the parties, failure of communication, differing drafting practices or deadlines which require the parties to compromise in order to reach agreement. There may often therefore be provisions in a detailed professionally drawn contract which lack clarity and the lawyer or judge in interpreting such provisions may be particularly helped by considering the factual matrix and the purpose of similar provisions in contracts of the same type. The iterative process …. assists the lawyer or judge to ascertain the objective meaning of disputed provisions.”
“(d) the Contractor may not make an application for an Interim Payment Application for a Milestone Payment before all preceding Milestone Events … have been achieved.” “(g) the Contractor may make an Interim Payment Application only once per month at the end of the respective month.”
“Subject to Sub-Clause 39.1, upon completion of each Milestone Event the Contractor may in respect of each completed Milestone Event make an Interim Payment Application to the Purchaser’s Representative supported by complete and detailed documentary evidence …..”
“If a DD [Delay Damages] Milestone is also a Milestone Event and the Purchaser in its absolute discretion has permitted the Contractor to make an Interim Payment Application before the Milestone Event is completed, such permission shall be no prejudice to the Purchaser rights under this Clause 15 and shall not constitute a waiver of the Purchaser’s entitlement to Liquidated Damages for Delay for failure to achieve the DD Milestone.” (ii) Clause 16B.8: “Without prejudice to Sub-Clause 16B.7, the Purchaser may at any time (whether before or after the Time for Completion) in its absolute discretion grant an extension of time in respect of any Relevant Milestone. The Purchaser is not required to exercise its discretion under this Sub-Clause 16B.8 for the benefit of the Contractor.” (iii) Clause 17.3: “The Purchaser shall …. evaluate the proposed Contractor Variation, in good faith, taking into account all relevant issues including whether ….. but the Purchaser may at its absolute discretion accept or reject the Contractor Variation.” (iv) Clause 39.19: “…. If a Milestone Event is also a DD Milestone and the Purchaser in its absolute discretion has waived his right to Liquidated Damages for Delay for failure to achieve the DD Milestone, such waiver shall not entitle the Contractor to apply for an [sic] Payment Notice for the respective Milestone until all conditions stated in Sub-Clauses 39.1 and 39.2 are fulfilled.”