“the combination of Hardware and Software working together to deliver the function and performance specified in the Contractor Undertakings. Any part of the System may be separately identified as a Sub-system.”
“the services to be provided under this Contract, including but not limited to the Implementation and Scanning Services and the Support Service.”
“The Contractor shall meet the Contractor Undertakings contained in schedule A, and shall fulfil all its obligations under the Contract in accordance with the timetable in schedule E in consideration of payment by the Authority of the Contract Charges.”
“The Contractor shall perform its delivery and installation obligations under the Contract according to the timetable contained in schedule E …”
“The Authority shall pay the Contractor the Contract Charges, and shall perform its responsibilities under the Contract including, but not limited to, those specified in schedule D (Authority’s responsibilities), in compliance with the Contractual Dates set out in schedule E.”
“the charges as set out in schedule G.”
“The Authority shall pay the Contractor the Contract Charges, as applicable, and any other valid charges that may become due, according to the payment schedule contained in schedule G.”
“Any actual or anticipated material delay or failure by either party shall be notified to the Project Board and managed in accordance with the recommendations of the Project Board. Both parties shall use all reasonable endeavours to mitigate the impact of such delay regardless of cause.”
“Subject to clause 3.1.3, delay or failure solely caused by the Contractor to meet any Contractual Dates contained in the timetable in schedule E, shall be subject to the provisions of clause 8.3 (delays).”
“If the Contractor fails to meet any Contractual Date specified in the timetable contained in schedule E, both parties shall use all reasonable endeavours to mitigate the impact of such delay, and as required under the provisions of clause 3.1, it shall be liable to: (a) reimburse the Authority for all proven losses, costs, damages and expenses incurred by the Authority by reason of such delay.”
“Clarification “(a) The provisions of sub-clause 8.3.1(a) above shall apply to delay by the Contractor in meeting any Contractual Dates, notwithstanding the previous application of such provisions to delay or failure by the Contractor to meet any other Contractual Dates. (b) The Authority acknowledges that the Contractor’s ability to meet its obligations under the Contract according to the timetable in schedule E may depend on the Authority likewise meeting its obligations, including those specified in schedule D. Consequently, insofar as the Contractor is prevented from fulfilling any of its obligations as a direct result of a delay solely caused by the Authority it shall not be liable to the Authority for such failure and sub-clauses 3.1.3 and 3.2.1 shall apply.” “(a) The provisions of sub-clause 8.3.1(a) above shall apply to delay by the Contractor in meeting any Contractual Dates, notwithstanding the previous application of such provisions to delay or failure by the Contractor to meet any other Contractual Dates. (b) The Authority acknowledges that the Contractor’s ability to meet its obligations under the Contract according to the timetable in schedule E may depend on the Authority likewise meeting its obligations, including those specified in schedule D. Consequently, insofar as the Contractor is prevented from fulfilling any of its obligations as a direct result of a delay solely caused by the Authority it shall not be liable to the Authority for such failure and sub-clauses 3.1.3 and 3.2.1 shall apply.”
“Except as otherwise expressly provided by the Contract, all remedies available to the Contractor or the Authority for breach of the Contract are cumulative and may be exercised concurrently or separately. The exercise of any one remedy shall not be deemed an election of such remedy to the exclusion of other remedies.”
“Either the Authority or the Contractor may at any time by notice in writing to the other party terminate the Contract as from the date of service of such notice whenever any of the following events occurs: 10.2.1 there is a breach by the other party of any provision hereof which expressly entitles the non-breaching party to terminate the Contract; or 10.2.2 the other party commits a material breach of any of its obligations hereunder which is not capable of remedy or, if capable of remedy, is not remedied within thirty (30) days or such reasonable time (agreed between the parties at the time), after receipt of written notice from the non-breaching party of its intention to terminate.”
“If the System, any part of it, any Deliverable, Service or Task has failed to meet its required acceptance criteria specified in schedule F in all material respects by the Acceptance Completion Date specified in relation to it, if any, the Contractor shall, unless the provisions of clause 3.2 apply, be deemed to be in Default, thereon, without prejudice to any other remedies available to the Authority, it shall be entitled, in respect of and as appropriate to such failure, to: … (d) terminate the Contract under the provisions of clause 10.2.1 provided only that: (i) such failure is in respect of acceptance of the System or Service; … In the event of termination in accordance with this sub-clause 23.4.1(d), the provisions of 11.3 shall apply.”
“If so specified in the Contractor Undertakings, the Authority shall be entitled to performance remedies specified in schedule A, if any are specified therein, in place of, in addition to or in combination with the provisions of clause 25.3 in which case, such remedies shall be applied without prejudice to any other rights and remedies available to the Authority and, where applicable, shall be in addition to the financial limitations set out in clause 8.”
“If, notwithstanding any corrective actions taken in accordance with sub-clause 25.3 or performance remedies applied in accordance with clause 25.4, the Contractor persistently fails, in any material respect, to meet any Service Level, such failure shall be considered to be a material breach of the Contractor’s obligations and shall entitle the Authority to terminate the Contract in accordance with the provisions of clause 10.2. Neither party shall be prevented from determining that any other breach of the Contract constitutes a material breach.”
“Rights and obligations of the parties which have accrued or which shall accrue shall survive termination of the Contract insofar as survival shall be construed from the relevant clauses in the context of such termination ...”
“The termination of the Contract as provided for in this clause 11 shall not prejudice or affect any right of action or remedy which shall have accrued or shall thereafter accrue to the Contractor or the Authority.”
“… the liability of either party for Defaults shall be limited as stated below: (a) the liability of either party under the Contract for any one Default resulting in direct loss of or damage to tangible property of the other party or any series of connected Defaults resulting in or contributing to the loss of or damage to the tangible property of the other party shall not exceed the figure set out in schedule G; (b) the aggregate liability of either party under the Contract for all Defaults, other than those governed by sub-clause 8.1.2 (a) above, shall not exceed the amount stated in schedule G to be the limit of such liability.”
“any breach of the obligations of either party (including but not limited to fundamental breach or breach of a fundamental term) …”
“Paragraph 9.1 The aggregate liability of the Contractor in accordance with sub-clause 8.1.2 paragraph (a) shall not exceed the sum of two million pounds. “Paragraph 9.2 The aggregate liability of the Contractor in accordance with sub-clause 8.1.2 paragraph (b) shall not exceed: 9.2.1 for any claim arising in the first 12 months of the term of the Contract, the Total Contract Price as set out in section 1.1; or 9.2.2 for claims arising after the first 12 months of the Contract, the total Contract Charges paid in the 12 months prior to the date of that claim.”