“BP will be obliged to cease trading from the First Property as a direct consequence of the carrying out of part of the Restaurant Works and the Building Programme anticipates such closure will be for a period of four weeks and Liberty shall pay to BP the sum of£40,000.00 for each week that BP is closed and so in proportion for a period of less than one week during which the First Property remains unopen for trading due directly to the carrying out of the Restaurant Works.”
“If a defendant orders works which delays a contract, then unless there is an extension of time provision which covers it – and here there is not – time is rendered at large and the sort of payment of a sum due as a delay, such as the£40,000 , would not be due.”