“1. On the assumption that EMCOR is entitled to an extension of time pursuant to clause 11.3 of the EMCOR Sub-Contract (as amended) by fixing such revised or further revised period or periods for the completion of its Sub-Contract Works, does the EMCOR Sub-Contract (as amended) require: (a) that such revised or further revised periods are added contiguously to the end of the current period, so as to provide an aggregate period within which EMCOR’s Sub-Contract Works should be completed (as contended for by EMCOR); or (b) that such revised or further period or periods are fixed in which EMCOR can undertake its Sub-Contract Works, which are not necessarily contiguous but which reflect the period for which EMCOR has in fact been delayed and is entitled to an extension of time (as contended for by CCL). 2. At paragraphs 3 and 5 of Appendix 2 to CCL’s Particulars of Claim, CCL claims loss and damage from EMCOR and AECOM for delay which includes a claim for the “Liquidated and Ascertained Damages levied by the Employer against CCL” for the period between29 January 2011 and22 July 2011 (“the LADs”). On a proper construction of: (i) the Building Contract (as amended); (ii) the Supplemental Agreement; (iii) the Further Supplemental Agreement: (a) was CCL’s liability to Rolls for liquidated and ascertained damages for the period between29 January 2011 to22 July 2011 extinguished by the Further Supplemental Agreement (as alleged by EMCOR and AECOM but denied by CCL); and (b) if so, does that mean that: (i) EMCOR has no liability to CCL in respect of any sums which it paid to Rolls under the Further Supplemental Agreement in respect of the period 29 January to11 March 2011 ; or alternatively has no liability to CCL for sums purportedly paid to Rolls as LADs under the Building Contract (as alleged by EMCOR but denied by CCL); (ii) AECOM has no liability to CCL for sums purportedly paid to Rolls as LADs under the Building Contract (as alleged by AECOM but denied by CCL).” (a) that such revised or further revised periods are added contiguously to the end of the current period, so as to provide an aggregate period within which EMCOR’s Sub-Contract Works should be completed (as contended for by EMCOR); or (b) that such revised or further period or periods are fixed in which EMCOR can undertake its Sub-Contract Works, which are not necessarily contiguous but which reflect the period for which EMCOR has in fact been delayed and is entitled to an extension of time (as contended for by CCL). (a) was CCL’s liability to Rolls for liquidated and ascertained damages for the period between29 January 2011 to22 July 2011 extinguished by the Further Supplemental Agreement (as alleged by EMCOR and AECOM but denied by CCL); and (i) EMCOR has no liability to CCL in respect of any sums which it paid to Rolls under the Further Supplemental Agreement in respect of the period 29 January to11 March 2011 ; or alternatively has no liability to CCL for sums purportedly paid to Rolls as LADs under the Building Contract (as alleged by EMCOR but denied by CCL); (ii) AECOM has no liability to CCL for sums purportedly paid to Rolls as LADs under the Building Contract (as alleged by AECOM but denied by CCL).”
“The parties acknowledge that the revised Contract Sum has been calculated and agreed by the parties having taken into account all provisional sums, Changes, loss and/or expenses and any other deductions and/or additions referred to in clause 30.5.3 of the Building Contract which are set out in the attached Schedule 1.” (iii) By clause 2.3: “The Contractor agrees and acknowledges that it shall not be entitled to any extension of time pursuant to clause 25 of the Building Contract arising out of the occurrence of any event which has taken place on or before the date of this Deed, whether or not the Contractor has given notice in respect of such event.” (iv) The Dates for Completion of Sections B and C were now28 January 2011 and, for Section D,25 February 2011 . The rates for liquidated and ascertained damages were now£86,000 per week for Section B and£18,000 per week for Section C. (v) Clause 2.5 then provided that: “The parties acknowledge that the Contract Sum has been adjusted to take into account full deduction of liquidated and ascertained damages which would have been payable by the Contractor for Section B and Section C up to28 January 2011 , as specified in paragraph 20 of Schedule 1.”
“11 Sub-Contractor’s obligation – carrying out and completion of Sub-Contract Works – extension of Sub-Contract time 11.1 The Sub-Contractor shall carry out and complete the Sub-Contract Works in accordance with the details in the Appendix, part 4, and reasonably in accordance with the progress of the Works and in accordance with the Contractor’s programme for the Works as issued by the Contractor from time to time but subject to the notice to commence work on site as stated in the Appendix, part 4, and to the operation of clause 11. ….. 11.2.1 If and whenever it becomes apparent that the commencement, progress or completion of the Sub-Contract Works or any part thereof is being or is likely to be delayed, the Sub-Contractor shall forthwith give written notice to the Contractor of the material circumstances including, insofar as the Sub-Contractor is able, the cause or causes of the delay and identify in such notice any matter which in his opinion comes within clause 11.3.1. 11.2.2 In respect of each and every matter which comes within clause 11.3.1, and identified in the notice give (sic) in accordance with clause 11.2.1, the Sub-Contractor shall, if practicable in such notice, otherwise in writing as soon as possible after such notice: .1 give particulars of the expected effects thereof; and .2 estimate the extent, if any, of the expected delay in the completion of the Sub-Contract Works or any part thereof beyond the expiry of the period or periods stated in the Appendix, part 4 or beyond the expiry of any extended period or periods previously fixed under clause 11 which results therefrom whether or not concurrently with delay resulting from any other matter which comes within clause 11.3.1; and ….. 11.3 If on receipt of any notice, particulars and estimate under clause 11.2 the Contractor properly considers that: 11.3.1 any of the causes of the delay is an act, omission or default of the Contractor, his servants or agents or his sub-contractors, their servants or agents (other than the Sub-Contractor, his servants or agents) or is the occurrence of a Relevant Event; and 11.3.2 the completion of the Sub-Contract Works is likely to be delayed thereby beyond the period or periods stated in the Appendix, part 4, or any revised such period or periods, then the Contractor shall, in writing, give an extension of time to the Sub-Contractor by fixing such revised or further revised period or periods for the completion of the Sub-Contract Works as the Contractor then estimates to be reasonable. …. 11.7 If the expiry of the period when the Sub-Contract Works should have been completed in accordance with clause 11.1 occurs before the date of practical completion of the Sub-Contract Works established under clause 14.1 or 14.2, the Contractor may and not later than the expiry of 16 weeks from the aforesaid date of practical completion of the Sub-Contract Works, the Contractor shall either: .1 fix such period or periods for completion of the Sub-Contract Works longer than that previously fixed under clause 11 …. as the Contractor properly considers to be fair and reasonable … .2 fix such period or periods for completion of the Sub-Contract Works shorter than that previously fixed under clause 11 as the Contractor properly considers to be fair and reasonable …. .3 confirm to the Sub-Contractor the period or periods for the completion of the Sub-Contract Works previously fixed. … 11.9 No decision of the Contractor under clauses 11.2 to .7 inclusive shall fix a period or periods for completion of the Sub-Contract Works which will be shorter than the period or periods stated in the Appendix part 4.”
“4. Contract Sum 4.1 The Parties agree that the Contract Sum shall be£93,978,887 as set out in Schedule 3 hereto and that there shall be no further adjustment of the Contract Sum in respect of any matter arising on or before the date of this Deed including without limitation those matters set out in Schedule 3 hereto. 4.2 The Parties acknowledge that the revised Contract Sum has been calculated and agreed by the Parties as at the date of this agreement as having taken into account all provisional sums, Changes, loss and/or expense and any other deductions and/or additions referred to in clause 30.5.3 of the Building Contract. 4.3 The Contractor agrees and acknowledges that it shall not be entitled to any extension of time pursuant to clause 25 or to loss and/or expense pursuant to clause 26 of the Building Contract arising out of the occurrence of any event which has taken place or could reasonably be foreseen on or before the date of this Deed, whether or not the Contractor has given notice in respect of such event. ……” (iv) Clause 5 was headed Liquidated Damages and was in the following terms: “5.1 The Contractor acknowledges that the Dates for Completion of Sections B, C and D have not been achieved by the Dates for Completion varied by the Supplemental Agreement dated25 November 2010 (the “Supplemental Agreement”). 5.2 The Parties acknowledge that the Contract Sum has been adjusted and the retention arrangement modified, as set out in Schedule 3 and Clause 5 hereto, to satisfy all the Contractor’s liability for liquidated and ascertained damages payable by the Contractor for delays to completion of Sections B and C up to22 July 2011 . 5.3 The Parties agree that the new Dates for Completion of Sections B and C shall be22 July 2011 and that the new Date for Completion of Section D shall be30 September 2011 . 5.4 The Parties confirm that the rates for liquidated damages accrued after the Dates for Completion shall be as follows: Section B:22nd July 2011 £68,000 per week or pro-rata for part thereof. Section C:22nd July 2011 £18,000 per week or pro-rata for part thereof Section D:30 September 2011 [Not applicable] Section B:22nd July 2011 £68,000 per week or pro-rata for part thereof. Section C:22nd July 2011 £18,000 per week or pro-rata for part thereof Section D:30 September 2011 [Not applicable] …………. 5.6 In the event that any of the new Dates for Completion are not achieved, the Contractor acknowledges that the right of the Employer to claim liquidated damages in accordance with the Building Contract shall remain unfettered.”
“Question 1 Does Clause 25 confer upon the Architect jurisdiction to grant an extension of time for the completion of the Works in respect of a Relevant Event occurring during a period of culpable delay?” “Question 2 In granting an extension of time in respect of the Relevant Event occurring during a period of culpable delay, ought the Architect to award a “gross” extension (that is, one that re-fixes the Completion Date at the calendar date upon which the work would reasonably be expected to be completed having regard to the calendar date upon which it is instructed) or ought it to be a “net” extension (that is, one which calculates the revised Completion Date by taking the date currently fixed and adding the number of days which the Architect regards as fair and reasonable)?”
“In that case the question was what was to happen if during a period of culpable delay an event occurred which entitled the contractor to a JCT contract to an extension of time. The pragmatic and sensible answer was to add the further time to the relevant completion date. I see no reason why that approach should not also apply to the FCEC form ….”
“Should Practical Completion of either Section B or C of the Works (as certified by the Employer in accordance with the Main Contract ) occur at a date later than28 January 2011 , then the following shall apply: .1 If for whatever reason Practical Completion of Section B or C of the Works occurs between29 January 2011 and11 March 2011 (inclusive), then the Parties agree to waive any claims either may have against the other for any losses, whether arising under the Main Contract, the Sub-Contract or otherwise, in respect of any delay to completion of the Works or the Sub-Contract Works during such period; save to the extent the Sub-Contractor causes such delay to Practical Completion of either Section, the Contractor shall be entitled to recover such Liquidated and Ascertained damages as are deducted by the Employer under the Main Contract as a result. .2 If for whatever reason Practical Completion of Section B or C of the Works occurs after11 March 2011 , the Parties’ liabilities and entitlements to recover any losses arising as a result of such delay beyond11 March 2011 shall be determined in accordance with the provisions of this Sub-Contract.”