“The Aluminium frame - horizontal rails, have been secured to the Vertical rails using Sheradised Steel screws. If Salt water gets into this area electrolytic action will occur and premature decay will set in. However I would have expected that Carea who designed and supplied the system would have considered this at the design stage. ?”
“Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.”
“In determining the meaning of the language of a commercial contract, and unilateral contractual notices, the law therefore generally favours a commercially sensible construction. The reason for this approach is that a commercial construction is more likely to give effect to the intention of the parties. Words are therefore interpreted in the way in which a reasonable commercial person would construe them. And the standard of the reasonable commercial person is hostile to technical interpretations and undue emphasis on the niceties of language.”
“. . . the reliance placed in some cases on commercial common sense and surrounding circumstances (eg in Chartbrook Ltd v Persimmon Homes Ltd[2009] UKHL 38 ,[2009] 1 AC 1101 , paras 16-26) should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most obviously to be gleaned from the language of the provision. Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in a contract. And, again save perhaps in a very unusual case, the parties must have been specifically focussing on the issue covered by the provision when agreeing the wording of that provision.”
“Before the commencement of the Defects Liability Period for a Section the Contractor shall without further charge to the Employer supply 4 copies of [as built drawings] together with detailed maintenance and operations manuals for all aspects of such Section of Works . . . together with the Health and Safety File for such Section and manufacturer’s guarantees and (where applicable) unqualified commissioning certificates for all plant and equipment and proprietary materials incorporated in that section of the Works.”
“a state in which the Works or a Section are complete in all respects and free from apparent defects save for any minor items of incomplete work or minor defects the existence, completion or rectification of which would not, in the opinion of the Employer’s Agent, prevent or interfere with the use . . . of the Works by the Employer . . . and the documents specified in clause 5.5 have been delivered to the Employer.”
“16Practical Completion and Defects Liability Period 16.1 When a Section has reached practical completion and complied with clause 5.5 the Employer shall give the Contractor a written statement to that effect, which statement shall not be unreasonably delayed or withheld, and practical completion of such Section shall be deemed for all the purposes of this Contract to have taken place on the day named in such statement... 16.2 Any defects, shrinkages or other faults which shall appear prior to the commencement of or in a Section within the Defects Liability Period for such Section and which are due to failure of the Contractor to comply with his obligations under this Contract… shall be specified by the Employer in a Schedule of Defects for such Section which he shall deliver to the Contractor as an instruction of the Employer not later than 14 days after expiration of the said Defects Liability Period, and within a reasonable time after receipt of such Schedule the defects, shrinkages and other faults therein specified shall be made good by the Contractor at no cost to the Employer unless the Employer otherwise instructs and if the Employer does so otherwise instruct then an appropriate deduction in respect of any such defects, shrinkages or other faults not made good shall be made from the Contract Sum. 16.3 Notwithstanding clause 16.2 the Employer may whenever he considers it necessary to do so, issue instructions requiring any defect, shrinkage or other fault which shall appear prior to the commencement of or in a Section within the Defects Liability Period for such Section and which is due to failure of the Contractor to comply with his obligations under this Contract… to be made good and the Contractor shall within a reasonable time after receipt of such instructions comply with the same at no cost to the Employer unless the Employer otherwise instructs and if the Employer does so otherwise instruct then an appropriate deduction in respect of any such defects, shrinkages or other faults not made good shall be made from the Contract Sum. Provided that no such instructions shall be issued after delivery of a Schedule of Defects for such Section or after 14 days from the expiration of the Defects Liability Period for such Section. 16.4 Where the Employer’s Requirements specify a period or periods within which any defects notified to the Contractor shall be remedied, the Contractor shall comply with such requirements. 16.5 When any defects, shrinkages or other faults which the Employer may have required to be made good under clauses 16.2 or 16.3 shall have been made good he shall issue a notice to that effect, which notice shall not be unreasonably delayed or withheld, and completion of making good defects in the relevant Section shall be deemed for all purposes of this Contract to have taken place on the day named in such notice (the ‘Notice of Completion of Making Good Defects’). 16.6 When practical completion of all the Sections has been achieved… the Employer shall give the Contractor a written statement to that effect and Practical Completion of the Works shall for the purpose of clause 30.5.1 be deemed to have taken place on the day named in such statement.” 16.1 When a Section has reached practical completion and complied with clause 5.5 the Employer shall give the Contractor a written statement to that effect, which statement shall not be unreasonably delayed or withheld, and practical completion of such Section shall be deemed for all the purposes of this Contract to have taken place on the day named in such statement... 16.2 Any defects, shrinkages or other faults which shall appear prior to the commencement of or in a Section within the Defects Liability Period for such Section and which are due to failure of the Contractor to comply with his obligations under this Contract… shall be specified by the Employer in a Schedule of Defects for such Section which he shall deliver to the Contractor as an instruction of the Employer not later than 14 days after expiration of the said Defects Liability Period, and within a reasonable time after receipt of such Schedule the defects, shrinkages and other faults therein specified shall be made good by the Contractor at no cost to the Employer unless the Employer otherwise instructs and if the Employer does so otherwise instruct then an appropriate deduction in respect of any such defects, shrinkages or other faults not made good shall be made from the Contract Sum. 16.3 Notwithstanding clause 16.2 the Employer may whenever he considers it necessary to do so, issue instructions requiring any defect, shrinkage or other fault which shall appear prior to the commencement of or in a Section within the Defects Liability Period for such Section and which is due to failure of the Contractor to comply with his obligations under this Contract… to be made good and the Contractor shall within a reasonable time after receipt of such instructions comply with the same at no cost to the Employer unless the Employer otherwise instructs and if the Employer does so otherwise instruct then an appropriate deduction in respect of any such defects, shrinkages or other faults not made good shall be made from the Contract Sum. Provided that no such instructions shall be issued after delivery of a Schedule of Defects for such Section or after 14 days from the expiration of the Defects Liability Period for such Section. 16.4 Where the Employer’s Requirements specify a period or periods within which any defects notified to the Contractor shall be remedied, the Contractor shall comply with such requirements. 16.5 When any defects, shrinkages or other faults which the Employer may have required to be made good under clauses 16.2 or 16.3 shall have been made good he shall issue a notice to that effect, which notice shall not be unreasonably delayed or withheld, and completion of making good defects in the relevant Section shall be deemed for all purposes of this Contract to have taken place on the day named in such notice (the ‘Notice of Completion of Making Good Defects’). 16.6 When practical completion of all the Sections has been achieved… the Employer shall give the Contractor a written statement to that effect and Practical Completion of the Works shall for the purpose of clause 30.5.1 be deemed to have taken place on the day named in such statement.”
“If during the carrying out of the Works any work or any materials or any goods are discovered not to be in accordance with this contract, the Contractor shall, upon such discovery or being notified of such discovery, state in writing to the Employer the action which the Contractor will immediately take at no cost to the Employer to establish that there is no similar failure in work already executed or materials of goods already supplied…”
“570 PROPOSALS FOR RECTIFICATION OF DEFECTIVE WORK/PRODUCTS • As soon as possible after any part(s) of the work or any products are known to be not in accordance with the Contract, or appear that they may not be in accordance, submit proposals to CA for opening up, inspection, testing, making good, adjustment of the Contract Sum, or removal and re-execution. • Such proposals may be unacceptable to the CA and contrary instructions may be issued.”
“the Works briefly described in the First recital and referred to in the Employers Requirements and the Contractor’s Proposals and including any change made to those works in accordance with this Contract including any remaining work required to complete the provision of the construction phase Health and Safety Plan in a form acceptable to the Planning Supervisor and any making good of defects following Practical Completion.” (The words in italics were added by amendment) In my view, this amendment extends the definition of the Works beyond practical completion so as to include the actual work of making good defects, whether done during the Defects Liability Period or subsequently pursuant to a schedule of defects issued pursuant to clause 16.2. But what the amendment does not do is to extend the obligation to notify imposed by clause 8.7 until the issue of a certificate of Making Good Defects irrespective of whether or not the contractor is actually carrying out work at the time. The discovery of the non-compliant work has to occur “during the carrying out of the Works”
“ ‘Defects’ in clauses 16.2 and 16.3 included omissions, in particular incomplete work, including (as a result of the amendments added to the standard clause) such matters that were apparent before the defects liability period commenced including matters that should have been notified by Morgan Sindall pursuant to its obligations under clause 8.7.”
“7.3 In this Agreement, “Assumed Liabilities” means, in relation to the Business: … … (c) all performance obligations and liabilities arising under or in respect of each of the Completed Contracts and which arise or fall due for performance from and after Completion up until a defects liability certificate (“DLC”) is issued in respect thereof together with all liabilities arising from any such performance that is defective or from the acts or omissions of [Morgan Sindall] after Completion in connection with the defects of which [Morgan Sindall] is made aware to the extent [Morgan Sindall] knew or ought reasonably to have known such liability arising in respect of the period from Completion to the issue of a DLC.”
“if none stated is 6 months from the day named in the Employer’s statement as to practical completion of the Section.”
“All external cladding subject to completion, final clean and client snagging.”
“. . . there is authority for the proposition that a contractor is required, during the defects liability period to rectify defects of which he is aware that ought to have precluded practical completion from being certified. In particular, in Pearce & High v Baxter, the employer sought to rely upon defects that had become apparent during the rectification period but which had not been notified to the contractor during, or at the end of, that period and which had first been notified in the employer’s defence and counterclaim.”
“Before considering these authorities, I shall describe the background against which clause 2.5 operates. The contractor’s obligation is “with due diligence and in a good and workmanlike manner [to] carry out and complete the Works in accordance with the Contract documents using materials and workmanship of the quality and standards therein specified” (clause 1.1). When the architect issues his certificate of practical completion (clause 2.4), the contractor leaves the site. He has, apart from special arrangement, no more work to do. Clause 2.5 then provides for “defects . . . or other faults” which appear during the defects liability period which follows. The only express provisions are that these “shall be made good by the Contractor entirely at his own cost unless the Architect shall otherwise instruct.”
“I confirm that the works outstanding to the apartments, agreed at our meeting on 13th August, have been completed.”
“Please find enclosed the Final Payment Certificate No. 30 for the above Works carried out by Morgan Ashurst (formerly AMEC Construction Ltd). The Final Certificate corresponds with the signed Statement of Final Account dated12 June 2008 in the sum of£17,250,000 and releases the 1.5% Retention held against the Apartments Section of the Works following the issue of the Making Good Defects Certificate.”
“It is essential in English law that the duty should be established: the mere fact that a man is injured by another’s act gives in itself no cause of action: if the act is deliberate, the party injured will have no claim in law even though the injury is intentional so long as the other party is merely exercising a legal right: if the act involves a lack of due care, again no case of actionable negligence will arise unless the duty to be careful exists.”
“Also, I hope our completion of defects on the hotel and substantial completion of the defects works on the flats will allow you to pay the balance without holding any retention. The team will remain on site dealing with current issues.”
“Yes Michael has done the deal with Steve Slater, you will be glad to hear. Please therefore produce a final account statement for signature, we won’t release the monies until the drainage issue is sorted and the hotel certificate of making good of defects is issued. We should withhold the retention on the apartments, Michael what did you agree with Steve here, if you let us all know then JLL can produce the appropriate statement.”
“Please find attached your statement of Final Account . . . stating that we agree to accept a sum of£17,250,000.00 in full and final settlement for the works and services executed under our contract to the Works to the Malmaison Liverpool duly signed on the understanding that:- Retention of£88,080.65 + VAT to be released upon issue of the Defects Completion Certificate Works outwith the agreed Scope of the Main Contract undertaken by Morgan Ashurst for Malmaison (Liverpool) Ltd (eg. water drainage repairs, extra bollards and silicone to pods) are valued and paid for separately to this agreement.”
“Gentlemen Please see the attached letter. I am fed up with the ongoing problems that we are having. I would like to arrange a meeting about these problems before Jones Lang Lasalle sign off the defects period. Can we meet early next week in London? In addition to the enclosed note, I have just heard today that flat 36 has been flooded due to balcony leaks from the penthouse floors above. This is an ongoing problem and can only be solved by the balcony floors being sealed. We are suffering ongoing losses with tenants having to be relocated while the flooding issue is dealt with. I have not been able to let the penthouses because of ongoing issues like this and I am now claiming loss of rent from either MWB or from the retention monies held from Morgan Ashurst. I look forward to hearing from you. This is very urgent.”
“As it’s been nearly 12 months since the business sale, all the Schedule 16 projects should in theory be through the defects period. As you know, once we have the DLC certificate, liability reverts back to AMEC. To make sure we return to AMEC what is rightfully theirs, could you please by 17th July forward copies of all the DLC certificates we have in relation to the Schedule 16 projects. If we have not yet achieved completion of defects, could you advise the likely date for completion instead.”
“Please see attached email issued last week relating to progress and open issues, with Monday 11th August scheduled for final sign off meeting at Princess dock, the main issues which are still rumbling around which JLL cant comment upon is Herbie’s insistence on recovering lost revenue from someone and altering the layout of the carpark.”
“Look forward to issue of Making Good Defects Certificate on Monday 18th August.”
“Malmaison Liverpool - Apartments Making Good Defect Certificate.”
“13.9 - Making Good Defects Certificate.doc.”
“Malmaison Liverpool - Making Good Apartment Defects Certificate 18 08 08.doc”
“Princess Dock Apartments - Certificate of Making Good Defects” and the text of the e-mail was as follows: “Stuart Please find attached the certificate of making good defects for the Princess Dock apartments.”
“Do the Assumed Liabilities include incomplete work and/or defects which MS either knew about, was made aware of, or ought reasonably to have known about, within the period commencing27 July 2007 and ending on the date when a DLC was issued”
“AMEC’s case on these points is that: (1) Morgan Sindall was AMEC’s agent following Completion under the BSA and was therefore obliged to notify AMEC of defects of which it was or ought to have been aware; and (2) Morgan Sindall was under an implied duty to warn Malmaison of defects which it was aware or ought to have been aware which risked causing personal injury or damage to property if not rectified.”
"Of course, I am not saying they would have to tell us unless they know about it, because obviously if they don’t know about it they can’t tell us"