“On the Date of Possession possession of the site ... shall be given to the Contractor who shall thereupon begin the Works and regularly and diligently proceed with the same and shall complete the same on or before the Completion Date.”
“1. By the Deed of Variation made the second day of October 2009 it was recorded that the Contractor represented that the Certificate of Fitness and Practical Completion of Block B would be achieved by7 October 2009 and the Certificate of Fitness and Practical Completion of Block F would be achieved by7 November 2009 . 2. The Certificate of Fitness and Practical Completion of Block B was not achieved until10 November 2009 . 3. The certificate of Fitness and Practical Completion of Block F has not been achieved at the date of this Notice. 4. By reason of the failure to achieve Certificate of Fitness and Practical Completion in respect of Blocks B and F by7 October 2009 and7 November 2009 , respectively, I give Notice under Clause 27.2.1.2 of the Contract that the Contractor has failed to proceed regularly and diligently with the Works and that the default in respect of Block F continues.”
“NOTICE UNDER CLAUSE 27.2.2 1. By a notice under Clause 27.2.1.2 of the Contract given to the Contractor dated4 December 2009 , the Architect gave notice to the Contractor that the Contractor had failed to proceed regularly and diligently with the Works and that the default in respect of Block F continued. 2. The contractor has continued the specified default for 14 days and by this further notice the Employer determines the employment of the Contractor under this Contract. This further notice shall take effect on the date of its receipt by the Contractor.”
“We refer to the Notice under Clause 27.2.2 of the Contract served on our client, [Gibralcon], today in purported determination of our client’s employment under the Contract. ... For the reasons we will address below, it is apparent that you have failed to terminate our client’s employment under the contract and that your notice constitutes a repudiated breach of contract. We hereby confirm our client’s acceptance of the same. In summary, your attempt to terminate our client’s employment under the Contract is unlawful because: 1. The Architect’s notice of default, which is a precondition to any right you may have to terminate our employment, has not been served in accordance with the requirements of the Contract. 2. In the circumstances of this contract, at the4th December 2009 , our client’s failure to provide Certificate(s) of Fitness for and achieve Practical Completion of Blocks B and F on7th October 2009 and7th November 2009 respectively cannot be construed as a failure on their part to proceed regularly and diligently. 3. The Architects purported notice of default and/or your attempt to terminate our client’s employment under the Contract have been given unreasonably and/or vexatiously. 4. There occurred a ‘Site Lock Out’ between the 14th and the23rd December 2009 . 5. The Employer’s purported notice to determine our client’s employment under the Contract was and is not valid. We will briefly expand upon the above. The Architect’s Purported Notice of Default 1. On the4th December 2009 our client’s project manager, Jose Felix Triano, received an email from the Architect which attached a purported notice under clause 27.2.1.2. 2. Clause 27.1 requires any notice given under clause 27.2.1 to be in writing and given by actual delivery or by special delivery or recorded delivery. 3. Clause 1.7 requires notices to be served to an agreed address or the last known principal business address or our registered office or our principle (sic) office. Mr. Triano’s email address is none of these. 4. A further shortcoming in the Architect’s purported notice of default is that this was not issued ‘in writing’. As a consequence of there being no inclusion within the contract of Annex 2 (relating to EDI - Electronic Data Interchange”) it remains the case that where the contract stipulates that any communication is to be in writing, then communication in any other will not be valid. Consequently the attachment to the Architect’s e-mail dated the4th December 2009 , has not under our Contract been received in writing and is invalid.”
“547 On the basis of the wording of the Notice of Adjudication in Adjudication No 2 [see 16 and 17 above], neither do I consider that I have the jurisdiction to consider my decided Valuation of those three Variations, compared to the Certificate No 51 certified Valuations for same, in the aggregate for the purposes of deciding any amount [Gibralcon] are now entitled to be paid. 548 In other words I do not consider that in this Decision I can set off any Certificate No 51 over-certification I find there has been on any of those three Variations against any Certificate No 51 under-certification I find there has been on any other of those three Variations. And if I did I would be trespassing into areas concerning the Gross Value of the Works and I have not been invited, nor am I authorised, to go there so I do not.”