“Notwithstanding the date hereof no proceedings shall be commenced against the Contractor after the expiry of twelve years from the date of issue of the last written statement by the Client that practical completion of the Project has been achieved under the Contract”
“Subject to the following provisions of this section, any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise)”
“…should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most obviously to be gleaned from the language of the provision”