“1.1 You warrant and undertake to the Bank that you have exercised and will continue to exercise all reasonable skill, care and diligence to be expected of a monitoring surveyor experienced in overseeing and reviewing projects of a similar size, scope and complexity to the Development and that you will perform your duties accordingly… 2. INITIAL REPORT You will be required to provide an initial report on the Development in which you should, as a minimum, cover the areas indicated below. ... 2.1 verify all costs in the Borrower’s Development appraisal with particular reference to construction costs and your considered opinion of levels of contingency employed in the Borrower’s Development appraisal or cash flow and with regard to construction costs prepare your own estimate for the proposed construction works; 3. PERIODIC REPORTS 3.1 You are expected to inspect the site at least once a month (or as may be agreed with the Bank) and where you consider it appropriate to attend site progress meetings and also to review the minutes of such meetings. After your site inspection you are to provide an appropriate report which should include, but not be limited to, the following: 3.1.1 your own valuation of the construction works in progress; 3.1.2 a commentary on the progress of the Development with particular reference to quality control, any matters adverse to the Bank’s position and their implication in respect of the completion of the Development and its timing; 3.1.3 a check on drawdown requests so as to ensure all constituent amounts are justified in accordance with the Facility; 3.1.4 a review of actual expenditure incurred against the cashflow statement and an update on the projections accordingly, confirming at the time of each drawdown in accordance with the Facility that the undrawn balance of the Facility will be sufficient to meet in full all cost to be incurred in achieving practical completion of the Development; 3.1.5 verification that the Professional Team and building contractor receive funds from the Borrower if payment under their contracts and appointments are not to be made directly by the Bank; ... 3.2 During the construction period you are expected to bring to the Bank’s attention immediately (orally in the first instance, but to be confirmed in writing) any material change to the design, the building contract or any other contracts or other documents relating (directly or indirectly) to the Development.”
“A. I know what the word provisional sums are -- Q. Can you explain to his Lordship in one or two sentences what your understanding is of that? A. Prelims are -- from my understanding of prelims in a building contract are certain scoping of works and costs that are incurred in advance of actually doing the work itself. In some cases that may be some basic groundworks, it may be some other planning bits and pieces, it could be the professionals drawing up a plan and that is my understanding. MR. JUSTICE EDWARDS-STUART: Pause a minute. You are talking about prelims. We are talking about provisional sums. A. Forgive me, then, I have misunderstood. Then maybe my understanding is not correct.”
“Our own valuation required us to critically appraise and analyse the valuation once the quantity surveyor had had his chance to review it with the contractor. We use that as the basis for our assessment of the appropriateness of the valuation based on the works undertaken on site. We would obviously then compare that with the basic documents, such as the contractor’s own analysis which we obviously had, and that would be the basis for what we would certify within our report.”
“A. They put, they reported the construction costs, but they also reported confusingly, that there was enough money in the facility to cover, to complete the project. Therefore, you would deduce cover the construction costs, so, yes, they reported in one way that there was insufficient money, and in another way they reported that there was sufficient money. It wasn’t clear. Q. We will look at that in more detail. MR. JUSTICE EDWARDS-STUART: It wasn’t just not clear, Mr. Payne, it was flatly contradictory on its face, wasn’t it? A. My Lord, yes.”
“9 A reasonable and competent lender would correct any error which had been made by a monitoring surveyor regarding the amount of the loan facility made available by the lender. 10 The Defendant had drawn attention to the consideration or implementation of the construction of the Third Floor in each of its Progress Reports from Progress Report 4 onwards and had stated that it understood that the costs of the Third Floor works would be met from outside the Claimant’s Development Loan facility. 11 Mr. Mannering should have obtained, but did not obtain, details of: 11.1 the proposed Third floor Extension when first advised by the Defendant that this was being considered; 11.2 the costs of the proposed Third Floor works; and 11.3 the source and availability of the funding of the Third Floor works and reported this information to his Credit Office with a recommended course of action, but did not do so.” 11.1 the proposed Third floor Extension when first advised by the Defendant that this was being considered; 11.2 the costs of the proposed Third Floor works; and 11.3 the source and availability of the funding of the Third Floor works and reported this information to his Credit Office with a recommended course of action, but did not do so.”
“32. I recall having a conversation with Mr. Symons on receipt of the report which covered the summary of the Revised Initial Report. I recall going through the summary of the report on the telephone with him and him satisfying me that the development cost could be completed within the budget. I do not think that I went through the rest of the report with Mr. Symons, as I remember focusing on the summary part of the report. 33. I confirmed our conversation in my e-mail dated07/09/2006 11:01.”
“That a£100,000 guarantee be provided by James Chukwu to cover any future overspends or higher costs should a new builder need to be appointed partway through the build. On this basis the bank accepted the potential future overspends issue.”
“Thank you for your e-mail. We have been waiting for an update on this job as, as you know, it has been some time since we have received any info, although I have been in touch with Andrew intermittently. The situation as far as we are concerned, is that we were awaiting further, revised information from the Borrower reflecting a revised scope of works with a reduced costing. We made a number of comments as part of our review and the Borrower’s team were reviewing things. If possible, we would like the opportunity to review any revised info on behalf of the Bank prior to any release of funds as previously, the anticipated costs of the works were in excess of the available facility. That said, the process of drawdown would normally be as follows: Copy of valuation of works and certificate sent to McBains Cooper for approval, McBains Cooper visit to site and meet with team to assess progress et cetera. Borrower forwards “Drawdown Request Letter” to Bank, copied to McBains Cooper detailing the amount of funds requested, a breakdown thereof including VAT elements and enclosing copies of backup invoices. McBains Cooper issue a report to Bank detailing Costs, Progress and Authorising Drawdown if appropriate. It may be easier for us to have a conversation about this, if you wish.”
“I believe that the Bank was indeed only part funding the Development as professional and other fees were to be paid from the Borrower’s current account and thus funded by the Borrower. Therefore, overall, in acting as it did, in my opinion I consider that the Bank acted as a reasonably competent lender would have done at the time as the Defendant’s impression that the Bank was part funding the Development was correct.”
“No deduction was made from the sum certified by Clark. McBains’ file contains no cost report, no verification of any figures, no photographs and no details of any visits to the Property in relation to the [umpteenth] Report.”
“First, in order to sustain an action of deceit, there must be proof of fraud, and nothing short of that will suffice. Secondly, fraud is proved when it is shown that a false representation has been made (1) knowingly, or (2) without belief in its truth, or (3) recklessly, careless whether it be true or false.”
“Although I have treated the second and third as distinct cases, I think the third is but an instance of the second, for one who makes a statement under such circumstances can have no real belief in the truth of what he states.”
“We can confirm that, in our view, sufficient funds remain in the total facility at this time to complete the development.”
“We can confirm that, in our view, sufficient funds remain in the total facility at this time to complete the development, as we understand that additional costs are to be funded by the Borrower from outside of the Facility.”
“10. The Defendant had drawn attention to the consideration or implementation of the construction of the Third Floor in each of its Progress Reports from Progress Report 4 onwards and had stated that it understood that the costs of the Third Floor works would be met from outside the Claimant’s Development Loan facility. 11. Mr. Mannering should have obtained, but did not obtain, details of: 11.1 the proposed Third Floor extension when first advised by the Defendant that this was being considered; 11.2 the costs of the proposed Third Floor works; and 11.3 the source(s) and availability of the funding of the Third Floor works and reported this information to his Credit Office with a recommended course of action, but did not do so.”
“We noted, at the time, that the third paragraph of the letter referred to the contract value for the works as£2,540,059 whereas the fourth paragraph refers to the total facility of£2,250,000 . I believe that Nicky raised this with Julian Symons by telephone. However, it did not concern us unduly because the contract sum was considerably lower than the facility and we accepted it as a typo. This error continued until report 15.”
“I did note that there was a discrepancy between the projected contract value for the works (£2,540,059 ) in paragraph 3 of the letter, and the total facility (£2,250,000 ) named at paragraph 4 of the letter. This was not a major concern at the time, as the Bank knew that the facility provided was actually£2,625,000 and I understood that McBains were aware of this. I presumed that it was likely that McBains had simply made a typographical error. Given that the figure in the report was actually lower than the facility, we did not pursue the point. Had it been higher, we would have sought a corrections/clarifications in order to avoid any risk of an overspend.”
“The amount borrowed will be repayable in full on demand, but it is the Bank’s present intention to make the facility available to you until30 June 2008 (the “Repayment Date”).”
“And the other question potentially is around should we have lent to a religious institution, bearing in mind the highly - the high reputation risk in relation to religious institutions, but also in relation to the PR impact, should we have actually had to pull the plug on this.”
“AI 5 666.25 Performance Bond 28,518.75 Removal of Asbestos 47,434.70”
“We have not been advised of any Contract Variations to date. As noted above, we understand that the Client is considering an additional third floor of accommodation however, we have not viewed any details of this to date.”
“We understand that the additional cost (sic) for the third floor accommodation are currently being quantified and are expected to be [in] the region of£250,000 . The Borrower is expected to instruct these works shortly and it is understood that any such additional expenditure is, at present, to be funded separately from the agreed facility.”
“My understanding, my Lord, was that the borrower, my client, was going to raise additional funds which would pay for the third floor. Because the contract, the building contract, was between my client as the employer and the contractor; therefore, monies that were due to the contractor would be included within my monthly valuations and certificates.”
“We have not been advised of any Contract Variations to date. As noted above however, we understand that the Client has now instructed the works to provide the additional third floor of accommodation.”
“...the conditions which related to McBains Cooper ...were communicated to them. However, I do not have a copy of that correspondence.”
“I do not recall how they were communicated, and, if that was in writing, I do not have a copy of that correspondence.”
“Site set-up is complete and works are progressing on site with strip out of the building and preliminary demolition largely complete. Asbestos removal is also now largely complete following the completion of investigation work. Some additional asbestos has however been identified but the Contractor is remains (sic) generally on programme.”
“I can’t be certain, but I do recall phoning in about the meeting and then attending site within that period, and I do remember, as I briefly referred to earlier, my Lord, the asbestos situation in that there wasn’t - asbestos wasn’t being removed from the entire site, or indeed the entire building, but there were certain areas that we were unable to access.”
“We say he must have got it from Clark over the telephone and we also say that at the time he did so, Mr. Clark - not Mr. Symons - must have had the valuation V5 in front of him.”
“All present plus apologies plus J Chukwu and J Symons at McBains Cooper.”
“DD 7 received as below. I have started to look at this and will ensure payment is available by the due date. I do not appear to have received a copy of Interim Certificate No 7 which I read from your note was to follow under separate cover. Could you please forward this. Also, a brief update of current progress on site would also be much appreciated.”
“On11 August 2008 , I visited the site prior to working on my progress report. Site works undertaken in the period included some substructure works such as the installation of ground beams and pile caps. I recall a discussion with Will Clark about whether the delays to finalising the decking and staircase packages was due to him trying to negotiate a price with Acre at a level acceptable to the Borrower, in view of the fact that he would have to fund the additional 3rd floor costs. I do not recall Will Clark’s response, however I do recall being of the opinion that as the quantum of the additional 3rd floor works was evolving, he was coming under pressure to manage those costs very carefully.”
“Well, my answer is, my Lord, as I said in previous instances, I attended site, I always attended site, on most occasions I attended site before I did my report. To the best of my recollection and reconstruction, it was on that date and it would make sense that it would be before I did my report, the day before I actually sent my report out.”