“ISG has suffered loss as a consequence of CC’s breaches, in the sum of£35,000 plus VAT. This sum must be repaid to ISG forthwith, plus interest plus costs.”
“As a matter of law, if a defendant has been paid in advance but fails fully to perform its obligations as it promised to do, it follows that the claimant can recover its advance payment by virtue of total failure of consideration. That is exactly what has occurred in this matter.”
“In the event, ISG has incurred a loss and is entitled to recover in restitution the sum of£35,000 plus VAT by reason of a total failure of consideration.”
“32.1 That CC acted in breach of contract as set out above. 32.2 That as a result ISG suffered the loss summarised above. 32.3 That CC owes sums to ISG as a consequence. 32.4 That ISG is entitled to payment by CC in the sum of£35,000 plus VAT, or such other greater or lesser sum as the Adjudicator may decide is due. 32.5 That ISG is entitled to interest on such sums.”
“ISG are not entitled to the remedy that they have claimed (restitution) in adjudication at all because that is an equitable remedy not within an adjudicator’s jurisdiction/power.”
“There is no pleaded or factual basis on which the adjudicator can find any breach of contract/partial failure of consideration other than a 100% failure to perform (which is clearly not the case on the evidence).”
“This confirms that ISG’s restitutionary claim is not made under the sub-contract - because restitutionary claims are not made under contracts, they are made in equity, restitution being an equitable remedy - and as such the adjudicator has no jurisdiction/power to decide it.”
“On discharge of a contract of this kind a buyer who has paid the whole or part of the price in advance is entitled, in the absence of any agreement to the contrary, to recover what he has paid by reason of a total failure of consideration. He therefore has a right to recover in restitution any payments he has made in respect of the price, a right which is quite distinct from any right he may have (if he is the injured party) to recover damages for the loss of his bargain. In the present case the parties made specific provision for the repayment of instalments and Gearbulk could not, of course, recover both under the contract and in restitution; to do so would result in double recovery. In fact, however, Gearbulk is not seeking to recover the advance payments since it has already done so. There is no inherent inconsistency, however, in recovering instalments of the price under Article 10 and recovering damages for loss of bargain at common law.”