"45. From these cases and the CPR I draw the following principles: 1. In exercising its discretion the Court will consider all the circumstances of the case and seek to give effect to the overriding objective. 2. Amongst the matters to be considered will be: (a) the reasons and justification for the application which must be made in good faith; (b) the balance of prejudice to the parties; (c) whether any party has been the author of any prejudice they may suffer; (d) the prospects of success of any issue arising from the withdrawal of an admission; (e) the public interest, in avoiding where possible satellite litigation, disproportionate use of Court resources and the impact of any strategic manoeuvring. 3. The nearer any application is to a final hearing, the less change of success it will have, even if the party making the application can establish clear prejudice. This may be decisive if the application is shortly before the hearing."
“16.8 The allegation in paragraph 18(7) is denied. It is admitteddenied that Pennine’s records suggest that it used less stone than it should have done and/or that its columns were deficient for that or any other reason… 16.12 Subject to what is stated at paragraph 16.8 above, the first sentence of paragraph 18(11) is admitted. It is repeated that the size of the stone columns included in Pennine’s calculations was nominal only. Accordingly the fact that the diameter of the stone columns constructed was less than that assumed in those calculations did not make it obvious that the work undertaken would not and could not comply with the contractual settlement limits. The allegation that it should have been obvious to Mowlem that vibro compaction were conducted to their design could not comply with the settlement limits in the Specification is denied (not least because the claimant has misstated those limits. No admissions are made as to what should have been obvious to Pennine. 17.1 It is admitted that the design and/or calculations undertaken by Pennine werewas defective and that had that design and those calculations been carried out with reasonable skill and care Pennine would have realised that the vibro replacement works wereand not capable of achieving a floor that achieved a maximum settlement of 30mm at the centre and 15mm at the edge on the assumptions set out in paragraph 7.3 above. Store Areas 17.2 It is admitted that in the respects set out below, Pennine’s calculations with regard to the store areas contained some over optimistic and/or wrongly assessed values and errors, which, if corrected and based on the 500 mm diameter columns in fact installed, under a load of 15 kN/m² of the working platform would have resulted in a settlement prediction after vibro replacement of approximately 40 mm. It is further admitted that acting competently Pennine would have alerted Mowlem of this settlement prediction, who in turn would have alerted John Allen. 17.2.1 It is admitted that the stone column diameter used in the calculations was greater than that achieved on site. It is denied that this was negligent. The stone column diameter used in the calculations was nominal only. 17.2.2 In any event, stone column stiffness parameters used in the calculations were extremely conservative… 17.2.3 Pennine’s method for the load split between stone columns and the ground was computed accurately using the Baumann and Bauer calculation method. It is denied that it was negligent of Pennine to use this method… 17.2.4 Whilst it is admitted that the earth pressure coefficients for the soil and column material assume by Pennine in their calculations were incorrectly assessed, it is denied that the settlement reduction factor of 0.6 was of itself unrealistic or negligent… 17.2.7 The soil Mv values adopted by Pennine were in fact reasonable estimates of the average compressibility of the grounds based on the site investigation and laboratory test data available to them at the time… 17.2.8 It is admitted that in their settlement calculations Pennine adopted an inappropriate value for µ of 0.6 by way of a correction factor for the very soft clay... 17.2.9 Pennine’s settlement calculations were basedon Hobbs’ linear dispersion of load spread below the slab…This was optimistic, but not negligent… 17.2.10 It is denied that Pennine was under an obligation to give consideration to secondary consolidation settlement or was negligent in failing to do so… 17.2.11 Whilst it is admitted that Pennine’s calculations did not include an additional allowance for dead loads including the load of the supermarket floor slab, it is denied that Pennine or Mowlem was under a contractual obligation to ensure that they did. The Warehouse 17.3 It is admitted that Pennine’s calculations with regards to the warehouse contained wrongly assessed values and errors, which, if corrected and based on the 500mm diameter columns in fact installed, under a load of 31.5 kN/m² on the working platform would have resulted in a settlement prediction after vibro replacement of approximately 80 mm. It is further admitted that acting competently Pennine would have alerted Mowlem of this settlement prediction, who in turn would have alerted John Allen. The Defendant’s case is that Pennine’s calculations drastically underestimated total settlement by employing an unrealistic settlement reduction factor, an unduly optimistic Mv factor (being half measured value), failing to give any consideration to secondary consolidation settlement and adopting a generous allowance for stress reduction with depth. 17.4 It is further admitted that Pennine’s design was not competent by reason of its unrealistic settlement reduction factor and an unduly optimistic Mv factor. 17.4 It is denied that Mowlem should have appreciated that Pennine’s design and/or calculations were was incompetent or that the design parameters of a maximum settlement of 30mm at the centre and 15 mm at the edge on the assumptions set out in paragraph 7.3 above could not be met utilising that design and/or those calculations either in the store areas or in the Warehouse. 17.4.1 Further or alternatively, if the Defendant’s case as to the basis of these criteria set out in paragraph 7.3.1 above fails, it's case is that the criterion that there should be maximum settlement of 15 mm at the edge were in fact met because, in accordance with John Allen’s design, the edges of the floor slab were supported on piles. Pennine’s workmanship 17.5 Save that it is admitted that its columns were too smallerthan the nominal value shown in its calculations, it is denied not admitted that Pennine’s workmanship was defective. If and in so far as the workmanship was defective it is denied that it was an effective cause of any failure of the vibro compaction works to achieve the design parameters of a maximum settlement of 30 mm at the centre and 15 mm at the edge as those parameters are correctly to be understood, or at all. 19.1 The causes or cracking to the floor slab and excessive slopes to the supermarket floor are a combination of (1) errors in the ground conditions report by LBH Wembley and (2) errors in the foundation design prepared by John Allen and (3) errors in the design undertaken by Pennine. Subject to proof of the extent of the same, it may be that a minor contributory factor was all workmanship by Pennine.”