“Overall we feel we can alter the scheme to allow the build cost to be about£350,000 ….I feel that this could be the way forward. Prior to the contractor and myself developing the proposal could you confirm the alterations are acceptable”; e) on18th April 2011 the Defendants responded to the proposals, copying MCC in, and requested further costing information, raising detailed questions and observations; f) on16th May 2011 Mr Elliott issued MCC with a sketch showing various savings and a revised schedule which MCC was asked to price; g) on7th June 2011 MCC forwarded comments on the proposals to Mr Elliott; h) on24th June 2011 the results of the cost reduction/value engineering exercise were submitted to the Defendants and a date arranged for a site visit. The Defendants wanted further savings. On27th June 2011 Mr Elliott advised that he would seek further savings in consultation with MCC. Mr Elliott expressly asked Mr Crispin for the “go ahead” on27th June 2011 . If given, he would revise the drawings. Mr Crispin responded with the instruction : “Yes, please go ahead.”; i) on14th July 2011 a meeting took place attended by Mr Elliott, the Defendants and MCC. The purpose was to finalise changes to the project to enable Mr Elliott to revise his drawings so that MCC could price the revised scheme; j) on19th July 2011 Mr Elliott issued to the Defendants revised GA drawings and the revised section (“the revised scheme”), stating that : “Hopefully the drawings indicate all the design changes as discussed”
“Malcolm is looking at the costs, I have told him to use the current scheme. I know you may want the utility larger, but we need a baseline to work to.”
“PRE CONTRACT MINUTES No. 1 OPEN Architecture and Surveying Ltd On 9th August at 10.00 File Ref: 09071 8.5 … 1.1 Introductions Action 1.1.1 Appointments: Client Mr S Crispin Contractor Malcom Charles Contract Administrator Richard Elliott Structural Engineer Paul Considine 1.1.1.1 Project Description: ALL Double storey rear and side addition to a 4 bed property. External works to consist of a new patio and driveway. 1.2 Contract OPEN Architecture and Surveying Ltd On 9th August at 10.00 File Ref: 09071 8.5 Client Mr S Crispin Contractor Malcom Charles Contract Administrator Richard Elliott Structural Engineer Paul Considine 1.2.1 Priorities, Preparation of Contract Documents The contract documents are to consist of the following information JCT Building Contract for a Home owner/occupier with Consultant. Open Architecture’s Drawings Open Architecture’s Preliminaries Structural Engineer’s Drawings Contractors priced document Contract to be based on the drawings 107 T3 and 109 T3, OA to issue an architect’s instruction for the scheme to be based on the revised drawings 107 T4, 109 T4. Contractor to cost accordingly. 1.2.2 OA to prepare contract documents 3 copies to be signed. OA … 1.2.5 Commencement Date:9th September 2011 CO 1.2.6 Completion Date: 33 weeks after commencement date (Excluding public holidays). ALL Item 1.2.7 Contract Sum: ACTION£369,861 1.2.8 Insurances: Client to inform their Insurance company CL Contractor to send a copy of his insurance to OA. Contractor is insured UP TO£5 000 000 CO 1.2.9 Standards and Quality: Standards are set out in the contract documents, final standards on finishes etc by Contract Administrator. ALL 1.2.10 Pre-Ordering of Materials: Only allowed with written consent from the Contract Administrator 1.2.11. Information outstanding: Updated contract drawings to be issued. CO Contractor to prepare an information release schedule. (i.e. he is to look at what information is outstanding to enable him to build the project) 1.2.12 Contract Intent It is understood from these minutes that the Client Mr and Mrs Crispin wish to enter into a contract with Malcolm Charles Ltd for the alterations and additions to 28 Lyndhurst Drive, Sevenoaks, Kent. These minutes are to be taken as a letter of intent with both parties. All the particulars of the contract are set out in these minutes. 1.3 Contractors Matters 1.3.1 Date of Possession:9th September 2011 . ALL 1.3.2 Master Programme: Contractor to provide a programme prior to commencement of the contract. It is to consist of the information below • Contain adequate separate work elements to measure their progress and integration with services installations • Allocate specific dates for specialist sub-contract works, including supply of information, site operations, testing and commissioning • Accommodate public utilities, etc. • The Contractor must also provide for competent testing and commissioning of services as set out in the contract documents, and should be reminded that the time allocated for commissioning is not a contingency period for the main contract works. … 1.3.6 Working Hours ALL 07.30 to 16.30 hrs Monday to Friday … 1.3.12 Samples : Samples will be required Client to confirm, typically bricks, floor finishes, tiles, ironmongery. All samples will be emailed to the client prior to approval. 1.4 Statutory Procedures… 1.5 Health & Safety… 1.6 Consultant’s Matters… 1.7 Cost Control and Certification… Ordering of materials : Contractor only order from drawings and specifications 1.7.3 Variations Procedures, Change Control: ALL All alterations to the contract are to be via the Contract Administrator with a written instruction. Any alterations that are carried out without prior knowledge to the Contract Administrator are at the Contractors risk. … 1.7.4 Valuation Procedures: Contractor to be paid at 28 day intervals initial certificate to be issued After 14 days of commencement of the contract, certificates to be issued on a monthly basis. Contract Administrator to monitor valuations with Contractor, with the use of the project programme, cash flow and works Carried out on site. … 1.7.7 VAT: This a vatable project… 1.8 Communications and Procedures… 1.9 Meetings 1.9.1 Pattern and Procedures: ALL 6 no formal meetings will be held during the contract at every 4 weeks Informal meetings will be held as and when required. Initially there will be meetings every 2 weeks. Informal meeting with the contractor and Architect on a weekly basis. Client to provide details of his representative who will attend the meetings. … 1.2 Any Other Business 1.10.1 Finalise of the design, Open to revised the scheme and issue amended drawings to all parties 1.10.2 Revised cost based on the revised scheme …”
“Is it OK now to spend money?”
“5. Changing the work details Only the consultant can change the work details on the customer’s behalf. Changes will be dealt with as follows : a) if the changes increase the amount of work shown in the work details and the contractor agrees the changes, he will quote a price for the extra work and time involved. The customer will then decide whether to go ahead with the changes. If the customer agrees to the changes the consultant will instruct the contractor. b) If the changes reduce the amount of work shown in the work details the contractor will make an appropriate reduction in the price. c) If the changes alter the cost of any items in the work details without increasing or reducing the amount of work involved, an appropriate adjustment of the price will be made to reflect those changes.”
“Richard, Another question about the contract, having spotted the VAT omission, payment is in full on completion is that correct?...”
“..payment will be based on the contractor’s valuations and by our certificates on a monthly basis. We will hold a retention of 5% on the scheme, 2.5% released on practical completion and the remainder at the end of practical completion. Malcolm will be producing a cash flow forecast to help with the managing of funds….”
“Who do we contact to arrange for Keys for Lyndhurst.”
“Monday 12th as agreed”
“We are not ready to start work until we have a proper contract; there are details in there that are not yet finalised. My building insurance is not in place for construction and there are still cost issues and details that haven’t been finalised. It would not be right or fair for parties involved to start work until everything is in good order. Please do not start work on Monday.”
“It’s a bit late now to stop it! There will be abortive costs. Deliveries and contractors are all arriving tomorrow as agreed.”
“I can understand your concern, but the three things are in place for a contract. Contract value – this has been stated. Description of the works – as contract drawings. Time scale- 33 weeks. Could you confirm that Malcolm can start tomorrow.”
“During the summer we had a quote from another firm at 10% less with a superior job spec (incl extra roof work for the attic etc). We decided to stick with you. Both sides must work together to find a further 10% cost reduction on the total job price and get the dormer window over the stairs done. Your foundation work budget in particular looks very expensive.”
“Need to backload the payment terms, our situation is more difficult than it was last week.”
“To be honest we really do not know what to do. We are so far away and actually scared to move forward with such a big project that we have no control over. I know Malcolm has put a lot of effort in and you have of course too but all those revised costings today have only undermined our confidence. We can only realistically put the project on hold while we regroup a bit. But we want to be reasonable about it. What would you do in our situation?”
“The job could not go ahead as proposed, it had to stop. We haven’t worked out exactly if/how to proceed. Please let me know what I owe you for the plumber.”
“…the first requirement for the formation of a contract is that the parties should have reached agreement. Generally speaking, agreement is reached when an offer made by one of the parties…is accepted by the other… Such an agreement may, however, lack contractual force because it is incomplete, because its terms are not sufficiently certain, because its operation is subject to a condition which fails to occur or because it was made without any intention to create legal relations. An agreement may also lack contractual force on the ground of want of consideration…”
“The Principles 45. The general principles are not in doubt. Whether there is a binding contract between the parties and if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a pre-condition to a concluded and legally binding agreement.”
“5.1 After the completed JCT Standard Form had been issued to them on30th August 2011 , the Defendants provided the Claimant with keys to the property to enable to the works to start on9th September 2011 and thereby the Defendants evinced an intention to be bound by the terms of the Contract; or 5.2 Alternatively at the said meeting between the parties on9 August 2011 when all of the essential elements of the Contract were agreed with access being provided to the property by the Defendants as described in paragraph 5.1 above.”
“The customer or the contractor can have disputes decided within 21 days by an adjudicator appointed under an adjudication scheme for this contract. The adjudication scheme is run the Royal Institute of Chartered Surveyors (RICS), the Royal Institute of British Architects (RIBA) or the National Specialist Contractors Council (NSCC). This is as well as the right to go to court.”
“34. As the minutes of the meeting make clear, Mr and Mrs Crispin were very keen to get started but at the date of the meeting, formal documents had not been prepared and were unlikely to be so before Mr and Mrs Crispin left to return to China. Because of this it was agreed that the minutes of the meeting were to be taken as the contract pending the completion and signing of the formal documents…Minute 1.2.12 of the meeting states : “It is understood from these minutes that the Client Mr and Mrs Crispin with to enter into a contract with [MCC] for the alterations and additions to [the property]. These minutes are to be taken as a letter of intent with both parties. All particulars of the contract are set out in these minutes.” “35…It is not possible to start on site without having placed orders or organised materials, sub-contractors or labour…I specifically asked at the end of the meeting for the minutes to be taken as their intent, based on these agreed terms to form a contract now and specifically asked whether we were ok to place orders. My exact words were “Is it ok now to spend money?”
“Sam, Who do we contact to arrange for Keys for Lyndhurst.”