“Project Agreement and Other Project Documents 4.9 Except where expressly stated to the contrary in this Contract and without prejudice to Clause 4.10, 47 [Effect of Termination] and 48 [Compensation on Termination], the Building Contractor shall perform and assume, as part of its obligations, the Building Contractor’s obligations set out in Schedule 37 [FM Assumptions] …”
“Completion Criteria” means the Completion Tests as defined in Part 2 of Schedule 12 (Outline Commissioning Programme) and as may be applicable to each Phase; “Completion Process” means the process and procedures for carrying out of the notifications, testing, inspections and completion certification as defined in Part 1 of Schedule 12 as may be applicable to each Phase of the Works the dates for which shall be incorporated in the Final Commissioning Programme; “Defects” means any defect or fault in the Works and/or the Facilities (not being a Snagging Matter) which in relation to a Phase occurs after the relevant Phase Actual Completion Date and prior to the date falling twelve (12) months after the Phase Actual Completion Date due to a failure by [the Building Contractor] [Project Co] to meet the Trust’s Construction Requirements [and/or Project Co’s Proposals] or otherwise to comply with its obligations under this [Contract] [Agreement]; “Final Commissioning Programme”
“SCHEDULE 12, Outline Commissioning Programme”
“The obligations and responsibilities of the parties in relation to the completion and commissioning process are set out in clause 22 of the Project Agreement, which should be read in conjunction with this Completion Process.” … Inspection and commissioning process Where appropriate, the Independent Tester shall, in conjunction with the Contractor, Project Co and the Trust, develop the detailed tests on completion necessary to support the Completion Criteria. This process shall also include defining all key inspection and witness activity points. Once these tests are established, the Independent Tester shall agree a programme with Project Co for inspections/witnessing and visits to correlate with the key activity points. As part of the programme agreement, it is the intention to review and agree the procedure to be followed for acceptance of the specific work activities before the activities are progressed on site. Project Co shall procure that the Contractor will establish quality controls through inspection and test plans (ITPs) for specific activities in line with the construction status drawings and specifications. The intention is that ITP’s (sic) are to be in place prior to the commencement of any activity to which they refer. The ITP’s will identify the type and frequency of the inspections to be carried out and how the results are to be recorded … … Envelope inspections will be carried out to each building in accordance with the agreed programme and ITP requirements. External works inspections will be completed in agreed phased sections. Inspections and witnessing of internal finishes will be carried out on a department by department basis in accordance with the agreed programme. Within each department once final fix operations have been progressed, the Contractor will carry out a builders clean followed by an initial inspection. Any snagging work identified during the initial inspection will be attended to and the area re-inspected again to confirm all outstanding items have been addressed. The Independent Tester will be notified of the availability of the Department for inspection and will be given the opportunity to carry out or witness the inspection in accordance with the agreed programme … … This process will continue throughout the project to a point where building activities are sufficiently complete to allow commissioning activities to progress … For each phase prior to commencement of commissioning and in accordance with the following schedule of information release dates the Trust shall provide Project Co with a draft of the Final Commissioning Programme relating to the relevant Phase.”
“For each of these Phases the Completion Criteria to be satisfied to enable the Independent Tester to issue the Phase Actual Completion Certificate are set out below:”
“The Independent Tester shall carry out an initial full review of the design of the Project and thereafter shall monitor the development of the design to verify that it complies with the design is described in schedules 8 and 10 to the Project Agreement. If in the professional judgment of the Independent Tester, because of the results of monitoring the sample or other circumstances, more verification work is required, it shall provide a detailed report in respect of that and, if so agreed (acting reasonably) (or determined as between Project Co and the Trust by the Dispute Resolution Procedure) any change in the work scope in this respect resulting in a changing fees will be borne by Project Co, the Trust or the Contractor as they shall agree or as determined by the Dispute Resolution Procedure.”
“ ... it’s reiterated within the FCP; it gets picked up in the FCP. As your Lordship will see from the document I’m about to show you, what the parties did is lift those 15 points and then put them into a schedule and they both adopted it. So they fed into it, under section 5, the tests on completion. They fed in a series of items, which they had agreed as being tests which would be passed, whether those tests were walk-round inspections or other tests.”
“That the issue of the state of completion of the works that are the subject of the Construction Contract generally, and in particular Phases 8 and 9, should be considered by the Independent Tester against the Completion Criteria contained in Schedule 12, Part 2, to the Construction Contract and the Project Agreement and in the light of the judgment dated [ ] July 2014, without those criteria being amended, varied or otherwise influenced by any extant dispute between the Project Company and the Trust under the Project Agreement.”